First Notice | | 5/4/2013 | 6/4/2013 | | DONE |
Christina Prado
|
|
|
mailed 6-4-13///complete 6-6-13
|
Permanent Occupancy | | | 4/24/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/16/2013 | 4/17/2013 | 4/17/2013 | A | PASS |
Jim Sly
|
|
|
derek Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 4/16/2013 | 4/16/2013 | 4/16/2013 | P | CANC |
Jim Sly
|
|
|
Derik phone
|
BLD-Final | 4/15/2013 | 4/16/2013 | 4/16/2013 | A | NR |
Jim Sly
|
|
|
Derik Phone #: ###-#### Need Mech final.
|
BLD-Ceiling Grid Inspection | 4/3/2013 | 4/4/2013 | 4/4/2013 | A | CANC |
Jim Sly
|
|
|
zach Phone #: ###-#### per Ed cancel this inspection request
|
BLD-Framing/Rough-in | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | PASS |
Jim Sly
|
|
|
Derrick ###-####
|
BLD-Ceiling Grid Inspection | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | PASS |
Jim Sly
|
|
|
Zach ###-####
|
BLD-Framing/Rough-in | 4/2/2013 | 4/2/2013 | 4/2/2013 | P | CANC |
Jim Sly
|
|
|
Ceiling grid inspection-Derrick Phone #: ###-#### Re-sched.......
|
BLD-Ceiling Grid Inspection | 4/2/2013 | 4/2/2013 | 4/2/2013 | P | CANC |
Jim Sly
|
|
|
zack Phone #: ###-#### Re-sched........
|
FIRE-Final Inspection | 4/2/2013 | 4/2/2013 | 4/2/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 2/20/2013 | 2/20/2013 | 2/20/2013 | P | PASS |
Jim Sly
|
|
|
DERRICK Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/4/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/31/2013 | | 1/31/2013 | | PASS |
Tim L. Woodard
|
|
|
Approved resubmitted plans. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 1/31/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 1/31/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/31/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 1/31/2013 | | DONE |
Tisha Gallop
|
|
|
called Cortland and left mssg that permit is ready and fee, need GC form.
|
Plan assigned to (TLW) | 1/11/2013 | | 1/31/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Plan resubmittals received | | | 1/29/2013 | | DONE |
Christina Prado
|
|
|
received one response letter and three sets of plans marked A0.1, A.0 & E2; Gave to Tim Woodard for additional review
|
Routing PW Sewer Rating | 1/11/2013 | | 1/11/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2013 | | 1/11/2013 | | PASS |
Connie Baumgartner
|
|
|
Replacing one drinking fountain with a high / low unit. TLW
|
Routing - Addressing | 1/9/2013 | | 1/10/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLAN CHECK | 12/27/2012 | | 1/9/2013 | | FAIL |
Tim L. Woodard
|
|
|
|
1st review completed | | | 1/9/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 12/26/2012 | | 12/27/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Connie in sewer rating. Tim will determine requirements for any additional fixtures and will send back to sewer rating for review.
|
Application received | | 11/21/2012 | 12/26/2012 | | DONE |
Christina Prado
|
|
|
payment received 12-26
|
Plans ACCEPTED BY PLAN TECH | | | 12/26/2012 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/26/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - Addressing | 12/26/2012 | | 12/26/2012 | | PASS |
April Wing
|
|
|
|
Intake Approval | | | 12/26/2012 | | PASS |
Tim L. Woodard
|
|
|
|