Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD12-03094
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 450 E GOWEN RD
Project NameCommercial Tire
Customer Number 
ePlanReviewNo
Description
Commercial Tire - To construct a new 48,500 square foot, one story, concrete tilt-up industrial building with a 1,500 square foot office mezzanine and related site improvements. The building will contain a tire sales area, tire installation area, administrative offices, tire storage warehouse and a tire retread plant. This building is fully fire sprinklered. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 12/4/201312/2/2013 DONE
Print Statement  12/2/2013 DONE
DetailsTisha Gallop
Third Notice 11/4/201311/29/2013 DONE
faxed to Van Auker
Second Notice 10/11/201310/30/2013 DONE
Faxed 10-30-13
First Notice 9/7/201310/1/2013 DONE
BLD-Final8/27/20138/28/20138/28/2013APASS
DetailsJim Storey
late morning/early afternoon - jim Phone #: ###-####
Permanent Occupancy  8/28/2013 DONE
DetailsBarbara Stitt
Zoning Approval8/21/20138/21/20138/21/2013 DONE
DetailsAndrea Tuning
FIRE-Final Inspection8/15/20138/16/20138/16/2013APASS
DetailsForrest France
Inspection passed, fire life safety finaled.
FIRE-Final Inspection8/14/20138/14/20138/14/2013ANR
DetailsForrest France
Pending C/N items
FIRE-Final Inspection8/8/20138/12/20138/12/2013APART
DetailsForrest France
Items noted during fire life safety inspection include; hydrant orientation per BMC title 7, buffing equipment is not yet installed for verification of note #2 items 1-3, operational permit req. per fire code review note #7, post signage per note #10(B) as discussed, gates are not yet installed, see note #8 for racking over 8". EM lights/exit signs and PFE's okayed.
BLD-Ceiling Grid Inspection7/30/20137/31/20137/31/2013PPASS
DetailsJim Storey
jim Phone #: ###-####
BLD-Wall Bracing7/9/20137/10/20137/10/2013APASS
DetailsJim Storey
ron Phone #: ###-#### gyp sheer ok to cover
BLD-Energy code compliance7/2/20137/3/20137/3/2013APASS
DetailsJim Storey
jim Phone #: ###-####
BLD-Framing/Rough-in6/27/20136/28/20136/28/2013PPASS
DetailsJim Storey
jim Phone #: ###-#### paripet framing at west roof ok to cover.
BLD-Framing/Rough-in6/25/20136/26/20136/26/2013PPART
DetailsJim Storey
Jim Phone #: ###-#### framing ok pending plm
BLD-Framing/Rough-in6/18/20136/19/20136/19/2013APART
DetailsJim Storey
tim Phone #: ###-#### diaphram nailling and hardware ok on mez. framing stairs ok rise and run.
BLD-Conference6/11/20136/11/20136/11/2013APASS
DetailsJim Storey
reviewed stair drawnings for rise and run nose to nose/ handrail requirments/ 1 hr protection and support.
BLD-Other5/30/20136/3/20136/3/2013APART
DetailsJim Storey
Metal building roof insp//Jim Phone #: ###-#### change to deck atchment hilti sys. need review by engineer of record to field review of drag strut change to resolve forces/ nuts to be tightened at pannel angle/ r-25 required for roof deck insulation/ si ro address in report.
BLD-Foundation5/21/20135/22/20135/22/2013APASS
DetailsJim Storey
JIM Phone #: ###-####
BLD-Footing5/20/20135/21/20135/21/2013PPASS
DetailsJim Storey
Jimmy-early as possible please--rebar inspection please Phone #: ###-#### pads west canopy rebar ok
BLD-Footing5/3/20135/6/20135/6/2013APASS
DetailsJim Storey
Jim-Re-bar inspection Phone #: ###-####
BLD-Footing4/30/20135/1/20135/1/2013APASS
DetailsJim Storey
late AM for rebar - Jim Phone #: ###-#### north and east ft ok
BLD-Other4/24/20134/24/20134/24/2013PPASS
DetailsJim Storey
rebar - jim Phone #: ###-####
BLD-Other4/19/20134/24/20134/24/2013APASS
DetailsJim Storey
jim - rebar Phone #: ###-#### si reports ok
BLD-Other4/19/20134/23/20134/24/2013APASS
DetailsJim Storey
jim - rebar Phone #: ###-#### si reports ok
BLD-Other4/19/20134/22/20134/22/2013APASS
DetailsTom Arcoraci
jim - rebar Phone #: ###-#### si
BLD-Foundation4/1/20134/1/20134/1/2013PPART
DetailsJim Storey
jim Phone #: ###-#### placed with s/i ok
BLD-Footing3/26/20133/27/20133/27/2013APASS
DetailsJim Storey
late am please// footing rebar // Jim Phone #: ###-#### se dock ft and rebar ok
BLD-Footing3/22/20133/25/20133/25/2013APASS
DetailsJim Storey
JIm-Late am please Phone #: ###-#### 5 interior peirs ok pending si report
BLD-Footing3/20/20133/21/20133/21/2013APASS
DetailsJim Storey
Jim Phone #: ###-#### sub grade ok at dock area engineer redesign for step footting due to rock out cropings encountered in two locations. si reports pending.
BLD-Conference2/21/20132/22/20132/22/2013APASS
DetailsJim Storey
Jim Phone #: ###-#### reviewed for si and esc before exuvation begins
Issue PAID IN FULL permit  2/20/2013 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK1/23/2013 1/24/2013 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  1/24/2013 DONE
DetailsJohn Menard
Print Occupancy Form  1/24/2013 DONE
Permit Ready to Issue  1/24/2013  
Telephone call  1/24/2013  
1-24-13 called David B. permit ready and fee given ///dld
Plan assigned to (JCM)11/26/2012 1/24/2013 PASS
DetailsJohn Menard
Plan resubmittals received  1/22/2013 DONE
DetailsTisha Gallop
received transmittal and two copies of plan sheet SP-1; inserted by LEG and routed to Planning (Andrea).
Routing - PLANNING1/22/2013 1/22/2013 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK1/2/2013 1/18/2013  
DetailsJohn Menard
Routing - PUBLIC WORKS1/18/2013 1/18/2013 PASS
DetailsConnie Baumgartner
Routing PW Street Lights1/18/2013 1/18/2013 PASS
DetailsMike D Hedge
Routing - PLAN CHECK1/18/2013 1/18/2013  
DetailsJohn Menard
Plan resubmittals received  1/18/2013  
1-18-13 received 1 letter of transmittal,2 copies of sheet SP-1 & 3 copies of sheets L1.0 inserted by Gayle Jensen & taken back to John M.
Routing - Design Review1/18/2013 1/18/2013 FAIL
DetailsAndrea Tuning
The applicant has not shown the eastern driveway to be paved and the internal planter islands to be 8-feet in width) inside of curb to inside of curb). Also the lighting plan does not match the electrical plan. All pole lighting shall be located outside of the planters and away from all trees.
Plan resubmittals received  1/17/2013  
Recieved 2 copies of sheets E0.1 and E1.1 inserted into plans by Architect and taken back to John Menard's desk
Routing Off Site - STRUCTURAL1/2/2013 1/7/2013 PASS
DetailsJohn Menard
1-2-13 called Action Couriers for pick up of resubmittals - Received letter from consulting structural engineer approving revisions. JCM
Plan resubmittals received  1/4/2013  
Received 2 copies of sheet E1.1 and inserted in to plans then taken back to John Menards desk
Routing - FIRE1/2/2013 1/2/2013 PASS
DetailsScott Arellano
Attached comments to plans.
Routing - PLAN CHECK12/27/2012 1/2/2013  
DetailsJohn Menard
Plan resubmittals received  12/28/2012  
12-28-12 received 3 structural calcs,3 response letters and 3 copies of sheets S-0,S-1,S-2,S-3,S-4,S-5,S-6,S-7,S-8,S-9,S-10,S-14,S-15 inserted by Gale Jensen and taken back to John M.
Routing - PUBLIC WORKS12/21/2012 12/27/2012 FAIL
DetailsConnie Baumgartner
Failed by Mike Hedge for lighting issues.
Routing PW Drainage12/26/2012 12/27/2012 PASS
DetailsBrian Murphy
Routing PW Sewer Design12/24/2012 12/24/2012 PASS
DetailsMike Sheppard
Added valve and sewer tap requirements to plans
Routing PW Street Lights12/24/2012 12/24/2012 FAIL
DetailsMike D Hedge
Still no street lights indicated on the plan. I have a call into Munger Engineering to work this out.
Plan resubmittals received  12/21/2012  
12-21-12 received 1 correction letter for John M & 1 correction letter for Scott A , 2 copies of sheets A-0,SP-1,SP-2,A-1,A-2,A-3,A-5,A-7,A-8,A-9,A-10,M-1,P-1 inserted by David Bloodgett . sent back to PW ///dld
Routing - PLAN CHECK12/17/2012 12/21/2012  
DetailsJohn Menard
Route to Impact Fee Review12/12/201212/17/201212/17/2012 PASS
DetailsCindy M. Gould
1st review completed  12/17/2012 FAIL
Failed Planning, Plan Check, Fire and Structural.
Routing - FIRE12/11/2012 12/17/2012 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Plan resubmittals received  12/14/2012 DONE
DetailsTisha Gallop
received two additional copies of resub on 12/13 (C1, C2, C3, C4, C5) taken to Brian Murphy.
Plan resubmittals received  12/13/2012 DONE
rec'd three copies of sheets C-1; C-2; C-3; C-4; C-5 - inserted by eng. Also rec'd extra copy of C-5 and narrative for ESC - taken back to fire review
Plan resubmittals requested  12/12/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK12/6/2012 12/12/2012 FAIL
DetailsJohn Menard
John Menard
Routing - PLUMBING12/6/2012 12/7/2012 PASS
DetailsDaryl Spivey
1. Flammable/grease interceptor tank to be vented seperately from sanitary line. See enclosed diagram.
2. May require additional backflow protection.
3. Per plans and 2003 UPC.
Routing - PLANNING12/7/2012 12/7/2012 FAIL
DetailsAndrea Tuning
The applicant has not met the Conditions of Approval. The applicant shall:
Construct two driveways that intersect Gowen Road.
Install a total of 17 Class II or Class III street trees on Gowen Road.
Install a Class II tree within each of the proposed planter islands located to the north of the proposed building.
The drainage pond shall be adequately landscaped.
All pole lighting must also be located outside of all planter islands and shall not interfere with any proposed trees.

Once the applicant has complied with the previous conditions of approval, teh applicant should submit the drawings to Design Review staff for review and final approval.


Andrea
Routing Off Site - STRUCTURAL11/26/2012 12/6/2012 FAIL
DetailsJohn Menard
Received comment list from consulting structural engineer requesting revisions. JCM
Routing - Erosion and Sediment12/5/2012 12/6/2012 PASS
DetailsKimberly M. Johnson
approved with redlines. PD to submit clean copy with redline changes incorporated for stamp.
Plan resubmittals requested  12/6/2012 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing - PUBLIC WORKS11/27/2012 12/5/2012 FAIL
DetailsConnie Baumgartner
Routing PW Sewer Rating12/5/2012 12/5/2012 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste12/5/2012 12/5/2012 PASS
DetailsPeter J. McCullough
Routing PW Environmental12/5/2012 12/5/2012 PASS
DetailsWalt Baumgartner
Routing PW Street Lights12/5/2012 12/5/2012 FAIL
DetailsMike D Hedge
Under the DRH process, DRH12-00255, street lights were required but they are missing on the plans.
Routing PW Drainage11/30/2012 12/4/2012 FAIL
DetailsBrian Murphy
need revision
Routing PW Sewer Design11/28/2012 11/30/2012 FAIL
DetailsMike Sheppard
Add Note for tapping permit and add 2" ball valve
Routing - Addressing11/28/2012 11/28/2012 PASS
DetailsApril Wing
Routing - PLANNING Land Div11/26/2012 11/27/2012 PASS
DetailsTodd Tucker
Application received 11/26/201211/26/2012 PASS
Plans ACCEPTED BY PLAN CHECK  11/26/2012 DONE
Plans, engineering calculations and documents accepted for plan review process.
Plans ACCEPTED BY PLAN TECH  11/26/2012 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  11/26/2012 DONE
DetailsTisha Gallop
Pending Assignment by JCM11/26/2012 11/26/2012 DONE
DetailsJohn Menard
Telephone call  11/26/2012 DONE
DetailsTisha Gallop
called Action Couriers for pick up