BLD-Final | 5/15/2013 | 5/16/2013 | 5/16/2013 | A | PASS |
Jim Sly
|
|
|
ryan Phone #: ###-#### C/C issued.
|
DOC - Permit Finaled | 5/16/2013 | 5/16/2013 | 5/16/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 4/5/2013 | 4/5/2013 | 4/5/2013 | P | PASS |
Jim Sly
|
|
|
Ryan ###-####
|
BLD-Conference | 4/4/2013 | 4/5/2013 | 4/5/2013 | A | CANC |
Jim Sly
|
|
|
ryan Phone #: ###-####
|
Inspection Record Card- Bld | | | 4/2/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Framing/Rough-in | 3/29/2013 | 4/1/2013 | 4/1/2013 | A | PART |
Jim Sly
|
|
|
ryan Phone #: ###-#### Framing pass No sticker for Mech rough-in.......Called Ryan....
|
BLD-Framing/Rough-in | 3/18/2013 | 3/19/2013 | 3/20/2013 | P | PART |
Jim Sly
|
|
|
Ryan Phone #: ###-#### Shear approved......only.
|
BLD-Wall Bracing | 3/15/2013 | 3/18/2013 | 3/18/2013 | A | FAIL |
Jim Sly
|
|
|
ryan Phone #: ###-#### Met with Contr......Eddie.
|
BLD-Footing | 2/4/2013 | 2/5/2013 | 2/5/2013 | A | PASS |
Jim Sly
|
|
|
jeff Phone #: ###-####
|
BLD-Footing | 1/11/2013 | 1/14/2013 | 1/14/2013 | P | NR |
Jim Sly
|
|
|
jeff Phone #: ###-#### Temp in the teens.....Hole dug a few days ago....ground frozen....cannot allow to pour.
|
Issue PAID IN FULL permit | | | 1/10/2013 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 1/3/2013 | | |
|
|
|
|
Plan assigned to (CDM) | 12/7/2012 | 12/7/2012 | 1/3/2013 | | PASS |
Carl D Madsen
|
|
|
project dox
|
Routing - MECHANICAL | 1/3/2013 | | 1/3/2013 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/3/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/3/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/3/2013 | | DONE |
|
|
|
|
Routing - MECHANICAL | 12/31/2012 | | 12/31/2012 | | FAIL |
Troy James
|
|
|
comments from previous review has not been addressed. Eplan
|
1st review completed | | | 12/18/2012 | | FAIL |
|
|
|
Failed pending Mechanical approval
|
Routing - PLAN CHECK | 12/7/2012 | | 12/18/2012 | | PASS |
Carl D Madsen
|
|
|
project dox
|
Route to Impact Fee Review | 12/7/2012 | 12/12/2012 | 12/11/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Payment Received | | | 12/7/2012 | | DONE |
|
|
|
Payment received via Govolutions
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/7/2012 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/7/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 12/7/2012 | | 12/7/2012 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - PLANNING | 12/7/2012 | | 12/7/2012 | | PASS |
Colleen T Carroll
|
|
|
Driveway can not be gravel. Asphalt or concrete required
|
Routing - Addressing | 12/7/2012 | | 12/7/2012 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 12/7/2012 | | 12/7/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 12/6/2012 | | FAIL |
|
|
|
need elevation height and checklist
|
Application received | | | 11/28/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 28 2012 4:01PM
|