Case Summary (BLD) | | | 10/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Case Summary (BLD) | | | 10/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 11/7/2013 | 11/7/2013 | 11/8/2013 | P | PASS |
Dave Hannah
|
|
|
mike Phone #: ###-####
|
DOC - Permit Finaled | 11/8/2013 | 11/8/2013 | 11/8/2013 | A | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 11/5/2013 | 11/5/2013 | 11/5/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved approval letters from geotechnical engineer and civil engineer. Bond in place for revegetation. Project is completed and occupancy is approved for PW. Jason Taylor ###-####
|
BLD-Final | 11/1/2013 | 11/1/2013 | 11/4/2013 | P | NR |
Dave Hannah
|
|
|
DEB Phone #: ###-####
|
BLD-Final | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | NR |
Dave Hannah
|
|
|
DEB Phone #: ###-#### needs hill side final first
|
Plan assigned to (CDM) | 10/23/2013 | 10/23/2013 | 10/31/2013 | | PASS |
Carl D Madsen
|
|
|
Plan modification on Guardrails
|
Routing - PLAN CHECK | 10/23/2013 | | 10/31/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/31/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2013 | | |
|
|
|
|
Telephone call | | | 10/31/2013 | | |
|
|
|
10-31-13 called left message for Brent permit ready and fee given ///dld
|
Issue PAID IN FULL permit | | | 10/31/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/23/2013 | | DONE |
Christina Prado
|
|
|
Received plan modification for deck guardrails - Received two sets of plan shets marked A3.1, A3.2, A4.1 & A4.3 as well as two sets of structural calcs:Taken to Carl for review
|
BLD-Other | 9/9/2013 | 9/9/2013 | 9/10/2013 | P | PASS |
Dave Hannah
|
|
|
Deb -this is to check for fire treated wood - Steve will be on site to help Phone #: ###-####
|
BLD-Other | 9/6/2013 | 9/9/2013 | 9/9/2013 | A | NR |
Dave Hannah
|
|
|
DEB- TREATED WOOD IN DRIVEWAY Phone #: ###-####
|
BLD-Framing/Rough-in | 8/13/2013 | 8/14/2013 | 8/14/2013 | A | PART |
Jim Sly
|
|
|
fire rated soffits - deb Phone #: ###-#### Looked at 1x6 tongue and groove cedar and found stamps on the back of them. The stamps were smeared and un-readable. Should be fire rated treated. I talked to Deb about this and maybe we can get an invoice of what was ordered. Also told her if her soffit vents have not yet been approved by the City........that needs to be done. Don't know where treated cedar will be installed or even if it's been approved by Fire Dept. Deb to talk to Dave about this
|
BLD-Framing/Rough-in | 6/20/2013 | 6/20/2013 | 6/20/2013 | A | PASS |
Dave Hannah
|
|
|
Deb Jones Phone #: ###-####
|
BLD-Framing/Rough-in | 6/19/2013 | 6/19/2013 | 6/20/2013 | P | PASS |
Dave Hannah
|
|
|
Deb Jones Phone #: ###-####
|
BLD-Wall Bracing | 6/14/2013 | 6/14/2013 | 6/14/2013 | P | PASS |
Dave Hannah
|
|
|
deb Phone #: ###-####
|
Routing - MECHANICAL | 5/30/2013 | | 5/30/2013 | | PASS |
Troy James
|
|
|
another resubmittal of the manual j
|
BLD-Footing | 5/2/2013 | 5/3/2013 | 5/3/2013 | A | PASS |
Dave Hannah
|
|
|
dave Phone #: ###-####
|
BLD-Framing/Rough-in | 4/4/2013 | 4/5/2013 | 4/5/2013 | A | NR |
Dave Hannah
|
|
|
Jerimiah Phone #: ###-####
|
BLD-Footing | 3/13/2013 | 3/14/2013 | 3/14/2013 | A | PART |
Tony Young
|
|
|
brent Phone #: ###-####,, interior slab ftgs
|
PubWorks Subgrade Approval | 3/14/2013 | 3/14/2013 | 3/14/2013 | | DONE |
Jason C. Taylor
|
|
|
Footing subgrade for the interior footings between the 4' foundation and the upper retaining wall (both previously placed) has been approved by the projects geotechnical engineer (MTI). Footing inspection can be scheduled with building depatment. Jason Taylor ###-####
|
Plan resubmittals received | | | 2/28/2013 | | DONE |
|
|
|
new acca report
|
Routing - MECHANICAL | 2/28/2013 | | 2/28/2013 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Foundation | 2/22/2013 | 2/25/2013 | 2/25/2013 | A | PART |
Tony Young
|
|
|
Brent Phone #: ###-####,,6" 4ft, 6" 6' and tall retaining walls ok per plan
|
BLD-Footing | 2/20/2013 | 2/21/2013 | 2/21/2013 | A | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
BLD-Foundation | 2/14/2013 | 2/15/2013 | 2/15/2013 | A | PART |
Dave Hannah
|
|
|
jess Phone #: ###-#### lower wall ok to place concrete
|
BLD-Footing | 2/12/2013 | 2/12/2013 | 2/13/2013 | P | PASS |
Dave Hannah
|
|
|
Jeff Phone #: ###-####
|
PubWorks Subgrade Approval | 2/12/2013 | 2/12/2013 | 2/12/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved letter from geotechnical enginner approving subgrade for lower retaining wall footings. Ok to schedule footing inspection. Jason Taylor ###-####.
|
BLD-Foundation | 1/30/2013 | 1/30/2013 | 1/30/2013 | P | PASS |
Dave Hannah
|
|
|
Brent Phone #: ###-####
|
BLD-Foundation | 1/24/2013 | 1/24/2013 | 1/24/2013 | P | PART |
Tony Young
|
|
|
Brent Phone #: ###-####,, work in progress on retaining wall,, will cover and maybe pour Friday at 11am? then cover up for cure
|
BLD-Footing | 1/17/2013 | 1/18/2013 | 1/18/2013 | A | PART |
Dave Hannah
|
|
|
Brent Phone #: ###-#### first phase upper ftgs crew has ftgs covered and running heaters ok to place concrete
|
BLD-Footing | 1/16/2013 | 1/16/2013 | 1/16/2013 | P | FAIL |
Dave Hannah
|
|
|
Brent- Phone #: ###-#### ground was frozen and needed to add verts
|
Routing PW Grading-Hillside | 1/16/2013 | | 1/16/2013 | | PASS |
Jason C. Taylor
|
|
|
Footing subgrade for the uphill footing line has been approved by the projects geotechnical engineers (MTI). Footing inspections for those areas can be scheduled with the city. Jason Taylor (###-####)
|
Issue PAID IN FULL permit | | | 1/9/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/21/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/21/2012 | | |
|
|
|
|
Telephone call | | | 12/21/2012 | | |
|
|
|
12-21-12 called Mike permit ready and fee given ///dld
|
Routing - Erosion and Sediment | 12/19/2012 | | 12/20/2012 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - FIRE | 12/20/2012 | | 12/20/2012 | | PASS |
Scott Arellano
|
|
|
Approval of this building is contingent upon the residence installing a fire sprinkler system in accordance with NFPA 13D as an acceptable code alternate to inadequate fire department vehicle access. A separate permit will be required. Plans indicate the installation of one new fire hydrant along starcrest drive.
|
Routing - Addressing | 12/20/2012 | | 12/20/2012 | | PASS |
April Wing
|
|
|
Please note comments on the address change form.
|
Routing - PLAN CHECK | 12/20/2012 | | 12/20/2012 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 12/20/2012 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/20/2012 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2012 | | |
|
|
|
|
Routing - MECHANICAL | 12/18/2012 | | 12/19/2012 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/13/2012 | | 12/18/2012 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Addressing | 12/18/2012 | | 12/18/2012 | | FAIL |
April Wing
|
|
|
Still working on address issue.
|
Routing PW Grading-Hillside | 12/13/2012 | | 12/13/2012 | | PASS |
Jim Wyllie
|
|
|
Comply with conditions in letter from Boise City Public Works to applicant dated 12-13-12. Prior to scheduling a footing inspection applicants geotechnical engineer shall submit a letter to Public Works approving building footing subgrade. Jim Wyllie (###-####)
|
Routing - PUBLIC WORKS | 12/13/2012 | | 12/13/2012 | | FAIL |
Connie Baumgartner
|
|
|
Failed by Jim Wylie
|
Routing PW Grading-Hillside | 12/4/2012 | | 12/11/2012 | | FAIL |
Jim Wyllie
|
|
|
Need to resolve previous building permit issues. Permit was never completed. Anticipate receipt of letter from MTI that will resolve this matter. Need to have geotechnical engineer approve footing setbacks from decending and ascending slopes. Jim Wyllie (###-####)
|
Route to Impact Fee Review | 11/29/2012 | 12/4/2012 | 12/4/2012 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Rating | 12/4/2012 | | 12/4/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Meeting | | | 11/30/2012 | | DONE |
Scott Arellano
|
|
|
*Fire Marshal note. Slope of the driveway exceeds maximums allowed (14.9%) and will require fire sprinklers to meet access requirements.
|
Plans ACCEPTED BY PLAN TECH | | | 11/30/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 11/30/2012 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/30/2012 | | DONE |
Christina Prado
|
|
|
|
Routing - Addressing | 11/30/2012 | | 11/30/2012 | | FAIL |
April Wing
|
|
|
Address is out of sequence.
|
Application received | | 11/29/2012 | | | |
|
|
|
|