Second Notice | | 6/14/2013 | 6/19/2013 | | DONE |
Christina Prado
|
|
|
completed 6-19-2013
|
First Notice | | 5/30/2013 | 6/4/2013 | | DONE |
Christina Prado
|
|
|
mailed 6-5-13
|
FIRE-Final Inspection | 5/17/2013 | 5/20/2013 | 5/20/2013 | A | PASS |
Forrest France
|
|
|
Correction items field verified. Fire life safety passed.
|
BLD-Final | 5/17/2013 | 5/20/2013 | 5/20/2013 | A | PASS |
Dave Hannah
|
|
|
Kent Phone #: ###-####
|
Permanent Occupancy | | | 5/20/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 5/9/2013 | 5/10/2013 | 5/10/2013 | P | PART |
Jim Sly
|
|
|
Late in the day, if possible. thx Phone #: ###-#### >> Inspection requested via web by Todd Weltner OK for Temp Occ .OK for Perm when Fire Alarm, Fire Life, and Plumbing Perms. Corrections....Check (2) doors and hardware at front of Bldg. Check lower part of handrail at stairway to Mezzanine.
|
FIRE-Final Inspection | 5/9/2013 | 5/10/2013 | 5/10/2013 | P | PART |
Forrest France
|
|
|
Final pending project related fire alarm permit (under review), install three missing exit signs per approved plan and as discussed, post max. occupant load signs, doors and hardware at the main entry to be completed. Temporary occuapncy approved with conditions.
|
FIRE-Alarm Testing | 5/9/2013 | 5/10/2013 | 5/10/2013 | A | PART |
Forrest France
|
|
|
Completed functional test of two relocated manual pull stations and verification of offsite monitoring.
|
Zoning Approval | 5/10/2013 | 5/10/2013 | 5/10/2013 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 5/2/2013 | 5/2/2013 | 5/3/2013 | P | PASS |
Dave Hannah
|
|
|
Kent-ceiling grid inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 4/19/2013 | 4/19/2013 | 4/19/2013 | A | PASS |
Dave Hannah
|
|
|
Please call Kent to coordinate. Request inspection at 11:00. thx Phone #: ###-#### >> Inspection requested via web by Todd Weltner
|
Print Occupancy Form | | | 4/16/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 4/16/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 4/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 2/22/2013 | 2/22/2013 | 4/8/2013 | | PASS |
Carl Westfall
|
|
|
BITTERCREEK ALEHOUSE/RED FEATHER LOUNGE (20 days - March 20) ePlanReview
|
Routing - PLAN CHECK | 4/4/2013 | | 4/8/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines" after the resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/4/2013 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/29/2013 | | DONE |
|
|
|
Because the ePlan standards were not followed, the uploaded sheets were deleted and the workflow was sent back to the Architect. The revised drawings were not given the exact name as the drawings they were intended to replace.
|
Plan resubmittals requested | | | 3/21/2013 | | DONE |
|
|
|
Finished workflow in ePlan
|
1st review completed | | | 3/20/2013 | | |
|
|
|
|
Routing - FIRE | 2/22/2013 | | 3/20/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - PLAN CHECK | 2/22/2013 | | 3/19/2013 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on March 8 and was finished on March 19. Revised drawings were required. See the plan review report.
|
Routing - PLUMBING | 2/22/2013 | | 2/26/2013 | | PASS |
Bill VanDegrift
|
|
|
1) vent connections must be made 6" above flood level of fixtures.
2) R.P.will be required upstream of the filter system.
|
Routing - Addressing | 2/22/2013 | | 2/25/2013 | | PASS |
April Wing
|
|
|
Change the address from 242 N 8th St to 246 N 8th St to reflect correct address for site.
|
Routing - PUBLIC WORKS | 2/22/2013 | | 2/22/2013 | | PASS |
|
|
|
|
Routing - Design Review | 2/22/2013 | | 2/22/2013 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH12-00335
|
Routing PW Environmental | 2/22/2013 | | 2/22/2013 | | PASS |
Walt Baumgartner
|
|
|
Ensure any plumbing pipe changes routes all kitchen wastewater to existing Grease INterceptor
|
Routing Off Site - C.D.H | 2/22/2013 | | 2/22/2013 | | PASS |
Byron Grover
|
|
|
|
Routing PW Sewer Rating | 2/22/2013 | | 2/22/2013 | | PASS |
|
|
|
|
Pending Assignment by JCB | 2/22/2013 | | 2/22/2013 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 2/21/2013 | | PASS |
|
|
|
Old plan intake void. New plan intake approved.
|
Intake Approval | | | 1/3/2013 | | FAIL |
|
|
|
Sheets still not oriented properly.
|
Intake Approval | | | 1/3/2013 | | PASS |
|
|
|
Plan intake approved
|
Intake Approval | | | 12/6/2012 | | FAIL |
|
|
|
Please refer to the circled items on the plan intake checklist. Architectural sheets not oriented properly, planning approval of exterior changes not provided, and new beam in the basement not designed. Please resolve these items.
|
Application received | | | 12/4/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 4 2012 11:23AM
|