BLD-Conference | 7/24/2017 | 7/25/2017 | 7/25/2017 | A | DONE |
Mike Jordan
|
|
|
Stop by project. Noted that interior has been demolished. Cole architects are doing the new set of drawings. Noted that seperate electrical and plumbing permits have been issued.
|
BLD-Conference | 6/1/2017 | 6/19/2017 | 6/19/2017 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Other | 5/3/2017 | 6/1/2017 | 6/1/2017 | A | DONE |
Mike Jordan
|
|
|
Check status. Tenant vacated?. Tenant not yet vacated. per conversation with Jonathan Welch, business has been sold to a new owner. New owner is actively looking for a new reatail space while also negotiating with current building owner to stay at make space code compliant. I noted to jonathan that since building has been sold, a new permit and set of plans is required to be submitted to planning for review and approval. Jonathan also noted that at the moment, the business is closed. Another inspection has been scheduled for June 19th.
|
BLD-Aging Inspection | 4/4/2017 | 4/4/2017 | 4/4/2017 | | PEND |
Mike Jordan
|
|
|
Pending until May 2017.
|
BLD-Conference | 3/1/2017 | 3/2/2017 | 3/2/2017 | A | DONE |
Mike Jordan
|
|
|
Has tenant vacated or still planning on vacating?Spoke to Jonathan. He noted that it is their intention is to be vacated by the end of May. Also noted that they building owner wants them to stay but noted to the building owners that space must be brought into full compliance for them to stay. Will check in My on status.
|
First Notice | 11/21/2016 | 11/21/2016 | 12/12/2016 | | DONE |
Candy A. Nichols
|
|
|
mailed 12-12-16
|
CHANGE STATUS TO (ISS) | | | 11/30/2016 | | PEND |
Bob Archibald
|
|
|
Occupancy will be monitored till March 2017 when tenant is expected to vacate. Will uodate permit status at that time.
|
BLD-Final | 11/18/2016 | 11/21/2016 | 11/21/2016 | A | DONE |
Mike Jordan
|
|
|
Verify signage has been installed.
|
DOC - Permit Finaled | 11/21/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/22/2016 | 9/23/2016 | 9/26/2016 | P | PART |
Bob Archibald
|
|
|
Call 20 minutes before to meet there // Jonathan Phone #: ###-####. Fire extinquisher installed, Signage requested at rear door.
|
BLD-Conference | 9/22/2016 | 9/22/2016 | 9/22/2016 | P | DONE |
Mike Jordan
|
|
|
Verify status. Give 5 day notice or pending legal action. 5 day notice posted. Also called and spoke to Jonathan Welch. I told him that he had 5 day notice posted. Jonathan noted that he would call for buikding final for friday the 23rd.
|
BLD-Other | 8/23/2016 | 8/24/2016 | 8/24/2016 | A | PEND |
Mike Jordan
|
|
|
Status? Is tenant vacating space? Per Jonathan Welch, Items corrected. Also noted that they are moving in March of 2017. Jonathan to schedule final.
|
BLD-Conference | 6/27/2016 | 6/28/2016 | 6/28/2016 | A | DONE |
Mike Jordan
|
|
|
Needs to place fire extinguishers on wall.
|
BLD-Conference | 6/27/2016 | 6/27/2016 | 6/27/2016 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Other | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | FAIL |
Mike Jordan
|
|
|
Check status.Panic Hardware and lighting corrected? Can we final? This is pending fire. Per fires notes, quick response heads are required. Per tenant, they do not have the funds to do this.
|
FIRE-Final Inspection | 3/8/2016 | 3/9/2016 | 3/9/2016 | A | FAIL |
Troy Cobbley
|
|
|
Panic hardware at the front and rear exit doors and ADA hardware on the interior doors is not installed per the approved plans. Per the building inspector he will cover these items.
Mount fire extinguishers as discussed, provide exit discharge lights, provide additional exit sign/emergency light to rear exit as per plan, provide quick responce sprinkler heads per project scope of work, provide sprinkler modifications as required (sprinkler heads too close to one another).
|
BLD-Conference | 2/26/2016 | 3/4/2016 | 3/4/2016 | A | DONE |
Mike Jordan
|
|
|
No fire/lifesafety inspection yet. Contacted Jonathan to get status update. Jonathan noted that he has been severley ill, but is almost over being ill. Jonathan noted that he would schedule a life/safety inspection next week. Another building conferance has been set up for nest friday 3-11-16.
|
BLD-Conference | 2/24/2016 | 2/26/2016 | 2/26/2016 | P | FAIL |
Mike Jordan
|
|
|
as per Jonathan, a life safety inspection was to be scheduled for today. The inspection was not scheduled. Will check back in 5 days.
|
BLD-Conference | 2/23/2016 | 2/24/2016 | 2/24/2016 | P | DONE |
Mike Jordan
|
|
|
Followup on status?. Rescheduled conferance for friday afteenoon 2-26. Spoke with Jonathan, no progress to date. Per Jonathan, going to have life/safety inspection friday in the am.
|
BLD-Conference | 1/29/2016 | 2/4/2016 | 2/4/2016 | A | DONE |
Mike Jordan
|
|
|
Door hardware issues and exit signage has been reapired. Needs to schedule life/safety inspection. Also needs to provide letter from HVAC for required CFM.
|
BLD-Conference | 1/22/2016 | 1/29/2016 | 1/29/2016 | A | CANC |
Mike Jordan
|
|
|
Moved to next thursday, Doors not yet repaired.
|
BLD-Conference | 12/31/2015 | 1/22/2016 | 1/22/2016 | A | DONE |
Mike Jordan
|
|
|
Spoke to Jonathan (tenant).. Commercial door is repairing doors on tueday. AN electrician has installed/repaired exit signs. An inspection has been scheduled for next friday(Jan29th) to walk through.
|
BLD-Conference | 12/22/2015 | 12/31/2015 | 12/31/2015 | A | PEND |
Mike Jordan
|
|
|
Meet with jonathan on site to go over progress made. Work is in progress. Tenants have contracted an electrician to install the required exit signs, orepak is repairing the main exit and providing panic hardware on rear exit. Fire extinguishers have been purchased and need to be installed as per approved plan. Tenant is also going to get verification that the work done to existing HVAC units has been completed to provide the additional CFM as required. Per tenant, January will be first "rent free" month.
|
BLD-Conference | 12/11/2015 | 12/22/2015 | 12/22/2015 | A | DONE |
Mike Jordan
|
|
|
Check back. A phone call was made to speak with jonathan welch. He noted that he has purchased fire extingushers, panic hardware and exit signs. Jonathan noted that he will be installing these items over the next several days. A building conferance has been scheduled for Dec. 31st. Will meet Jonathan Welch on site and go over progress that has been made.
|
Plan Reviewer's activity | | | 12/14/2015 | | DEFR |
Jason Blais
|
|
|
Email from applicant below:
The school has received a reply from the landlord, and they are delaying rent to free up some money to complete the needed items. We can have all the exit issues completed in the next week or two, and everything else should be able to complete within 45 days. Would this be acceptable?
Thank You for all your patience.
Jonathan Welch
|
BLD-Conference | 12/4/2015 | 12/11/2015 | 12/11/2015 | A | NH |
Jim Sly
|
|
|
Check on 5 day notice. Bldg. locked. no one at site. left correction notice that 5 day notice is up. Contact Boise City P D S Dept.
|
BLD-Conference | 12/3/2015 | 12/4/2015 | 12/4/2015 | P | DONE |
Mike Jordan
|
|
|
Issue 5 day N&O to obtain CO. A five day Notice of violation was issued and correction notice. Doors were locked, violtation posted on window.
|
BLD-Conference | 6/25/2015 | 6/26/2015 | 6/26/2015 | A | DONE |
Mike Jordan
|
|
|
Please call 30min prior for access - Jonathan Phone #: ###-####
|
Fees Due Hold | 2/4/2015 | | 2/5/2015 | | DONE |
|
|
|
|
Change Expiration Date Only | | | 1/20/2015 | | DONE |
Jason Blais
|
|
|
Extension requested. A 180 day extension from 1/14/15 is granted. This is the first extension request for an issued permit. A building conference inspection also needs to be requested.
|
Permit Ready to Issue | | | 1/14/2014 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 1/14/2014 | | DONE |
Barbara Stitt
|
|
|
|
Issue PAID IN FULL permit | | | 1/14/2014 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CJW) | 1/3/2013 | 1/3/2013 | 12/30/2013 | | PASS |
Carl Westfall
|
|
|
DRAGON BRUSHIDO MARITAL ARTS - Project reassigned to Carl Westfall - ePlanReview
|
Routing - PLAN CHECK | 12/24/2013 | | 12/30/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/24/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/3/2013 | | 12/24/2013 | | PEND |
Carl Westfall
|
|
|
Waiting for revised drawings
|
Extend Review Timeline | | | 12/2/2013 | | DONE |
Jason Blais
|
|
|
Extended for 45 days. Resubmittals will be submitted by the end of this week.
|
Extend Review Timeline | | | 8/8/2013 | | DONE |
Jason Blais
|
|
|
|
Telephone call | | | 8/7/2013 | | DONE |
|
|
|
Called Bill Matter to ask about the status. He was not available but will call be back.
|
Plan assigned to (DRS) | 12/6/2012 | 12/6/2012 | 1/3/2013 | | DEFR |
Dan Stuart
|
|
|
ePlanReview case - Project reassigned to Carl Westfall
|
Routing - PLAN CHECK | 12/6/2012 | | 12/19/2012 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review report attached under Agency Comments in ePlan Review and a copy was also emailed to Bill Matter.
|
1st review completed | | | 12/19/2012 | | FAIL |
|
|
|
Failed in plan review
|
Plan resubmittals requested | | | 12/19/2012 | | DONE |
|
|
|
Copy of Plan Review Report attached to ePlanReview under Agency Comment File and a copy was also emailed to Bill Matter.
|
Routing - Addressing | 12/6/2012 | | 12/10/2012 | | PASS |
April Wing
|
|
|
|
Routing - FIRE | 12/6/2012 | | 12/7/2012 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. No comments attached to plans.
|
Routing - PUBLIC WORKS | 12/6/2012 | | 12/7/2012 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 12/7/2012 | | 12/7/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 12/6/2012 | | PASS |
|
|
|
Drawings uploaded by applicant on Dec. 5.
|
Application received | | | 12/4/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 4 2012 2:40PM
|
BLD-Conference | 3/4/2016 | 3/11/2016 | | A | |
Mike Jordan
|
|
|
|