BLD-Final | 8/21/2013 | 8/22/2013 | 8/22/2013 | A | PASS |
Jim Storey
|
|
|
clint Phone #: ###-####
|
DOC - Permit Finaled | 8/22/2013 | 8/22/2013 | 8/22/2013 | P | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 8/22/2013 | 8/22/2013 | 8/22/2013 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | NR |
Jim Storey
|
|
|
clint Phone #: ###-####
|
PubWorks Occupancy Approval | 8/13/2013 | 8/13/2013 | 8/13/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved engineers approval for grading and drainage. Public Works approves occupancy.
Note: This project house was flipped without the building departments approval.
|
PubWorks Occupancy Approval | 7/29/2013 | 7/29/2013 | 7/29/2013 | | FAIL |
Jason C. Taylor
|
|
|
Recvieved civil engineers approval for grading and drainage. Site is not complete and needs final grading done on east side of house to complete the grading/drainage. Occupancy is not approved. Jason Taylor ###-####.
|
BLD-Energy code compliance | 5/20/2013 | 5/21/2013 | 5/21/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 5/16/2013 | 5/17/2013 | 5/17/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall no air seal check at uinsulation insp.
|
BLD-Other | 5/16/2013 | 5/16/2013 | 5/16/2013 | P | PASS |
Jim Storey
|
|
|
Fire soffit - Clint Phone #: ###-#### canlights encapsulated ok
|
Plan resubmittals received | | | 5/13/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 5/13/2013 | | 5/13/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 5/1/2013 | 5/1/2013 | 5/1/2013 | P | PASS |
Jim Storey
|
|
|
joey Phone #: ###-#### exterior ok fire treated soffit material ok
|
BLD-Wall Bracing | 4/25/2013 | 4/26/2013 | 4/26/2013 | A | PASS |
Jim Storey
|
|
|
joey Phone #: ###-####
|
BLD-Foundation | 3/25/2013 | 3/26/2013 | 3/26/2013 | A | PASS |
Jim Storey
|
|
|
Anton Phone #: ###-#### 10:30 if possable.
|
BLD-Foundation | 3/25/2013 | 3/25/2013 | 3/25/2013 | P | DEFR |
Jim Storey
|
|
|
Anton Phone #: ###-####
|
BLD-Footing | 3/20/2013 | 3/21/2013 | 3/21/2013 | A | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 3/20/2013 | 3/20/2013 | 3/20/2013 | P | PART |
Jim Storey
|
|
|
after 4 - Anton Phone #: ###-#### set backs ok wip
|
PubWorks Subgrade Approval | 3/20/2013 | 3/20/2013 | 3/20/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved geotechnical engineers subgrade approval letter. Building department may be scheduled for footing inspections. Jason Taylor ###-####
|
OVERRIDE | | | 3/7/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
left message with Tahoe giving fees due
|
Override - Parcel Holds | | | 3/7/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (PEP) | 3/6/2013 | 3/6/2013 | 3/6/2013 | | DONE |
Perry Paine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/1/2013 | | 3/6/2013 | | PASS |
Carl D Madsen
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/6/2013 | | DONE |
Christina Prado
|
|
|
received three sets of plans marked C1; taken to Perry for further review
|
Routing PW Grading-Hillside | 3/6/2013 | | 3/6/2013 | | PASS |
Jason C. Taylor
|
|
|
Grading and Drainage plan approved. This lot will require a subgrade inspection prior to scheduling of building inspector for footings. Jason Taylor ###-####
|
CHANGE STATUS TO (REV) | | | 3/6/2013 | | DONE |
Christina Prado
|
|
|
Still need PW - Hillside/Grading approval
|
Plan assigned to (PEP) | 3/5/2013 | 3/5/2013 | 3/5/2013 | | PASS |
Perry Paine
|
|
|
|
Plan assigned to (CDM) | 2/8/2013 | 2/8/2013 | 3/5/2013 | | DEFR |
Carl D Madsen
|
|
|
|
1st review completed | | | 3/5/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2013 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/28/2013 | | 3/1/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing PW Grading-Hillside | | | 2/28/2013 | | FAIL |
Jason C. Taylor
|
|
|
Needs revised grading plan.
|
Routing - MECHANICAL | 2/28/2013 | | 2/28/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/28/2013 | | 2/28/2013 | | PASS |
David Moser
|
|
|
Approved as redlined, the wall next to the main side door shall not encroach into the 3 foot side setback.
|
Routing - Addressing | 2/8/2013 | | 2/28/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2013 | | 2/28/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 2/8/2013 | 2/13/2013 | 2/11/2013 | | PASS |
James McMahon
|
|
|
|
Application received | | 12/5/2012 | 2/8/2013 | | DONE |
|
|
|
|
Intake Approval | | | 2/8/2013 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/8/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/8/2013 | | DONE |
|
|
|
|
Intake Approval | | | 12/6/2012 | | FAIL |
Christina Prado
|
|
|
This is hillside- need to submit proper plans, app & docs
|