BLD-Final | 9/19/2013 | 9/19/2013 | 9/19/2013 | P | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
DOC - Permit Finaled | 9/19/2013 | 9/19/2013 | 9/19/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 3/20/2013 | 3/20/2013 | 3/21/2013 | P | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 3/19/2013 | 3/19/2013 | 3/20/2013 | P | PASS |
Tony Young
|
|
|
matt Phone #: ###-####
|
BLD-Framing/Rough-in | 3/18/2013 | 3/18/2013 | 3/19/2013 | P | PART |
Tony Young
|
|
|
matt Phone #: ###-####,, need to verify seal package,, ok to start insulation,, will need egress out of front bedroom,, only new areas reviewed,, not the remodel area at this point
|
BLD-Wall Bracing | 3/6/2013 | 3/7/2013 | 3/7/2013 | A | PASS |
Tony Young
|
|
|
matt Phone #: ###-####,, exterior ok to cover
|
BLD-Footing | 2/6/2013 | 2/6/2013 | 2/6/2013 | P | PART |
Tony Young
|
|
|
matt Phone #: ###-####,, wine celler footing off of existing basement ok
|
Fees Due Hold | 1/26/2013 | | 2/6/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Foundation | 1/22/2013 | 1/22/2013 | 1/28/2013 | P | PEND |
Tony Young
|
|
|
pete Phone #: ###-####
|
BLD-Foundation | 1/18/2013 | 1/18/2013 | 1/22/2013 | P | PART |
Tony Young
|
|
|
pete Phone #: ###-####,, basement wall... heater and cover on site
|
BLD-Footing | 1/14/2013 | 1/15/2013 | 1/15/2013 | A | PART |
Tony Young
|
|
|
Pete Phone #: ###-####,, tented and heated now,, ok to pour basement footings,, will abide by ACI 360R
|
BLD-Footing | 1/11/2013 | 1/14/2013 | 1/14/2013 | A | PEND |
Tony Young
|
|
|
Pete Phone #: ###-####,, said the contractor will tent and heat hole,, re-scheduled for tues am
|
BLD-Footing | 1/11/2013 | 1/11/2013 | 1/14/2013 | P | FAIL |
Tony Young
|
|
|
Pete Phone #: ###-####,, cold weather concrete provisions not provided for.. temps around 0 degrees at night..
|
OVERRIDE | | | 12/26/2012 | | |
|
|
|
|
Routing Walk-In (Zoning) | 12/26/2012 | 12/26/2012 | 12/26/2012 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (PW Hillside) | 12/26/2012 | 12/26/2012 | 12/26/2012 | P | PASS |
Jason C. Taylor
|
|
|
Subgrade inspection report from MTI dated 12-26-12. Please be sure to call for footing inspection before placing foundation elements. Jason Taylor (###-####)
|
Routing Walk-In (BLD) | 12/26/2012 | 12/26/2012 | 12/26/2012 | P | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 12/26/2012 | 12/26/2012 | 12/26/2012 | | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 12/26/2012 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/26/2012 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/26/2012 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/26/2012 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/26/2012 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (PW Hillside) | 12/14/2012 | 12/14/2012 | 12/20/2012 | P | DONE |
Jason C. Taylor
|
|
|
Needs footing plans engineered/stamped. No footing elevations or grading on plans.
Jason Taylor ###-####
|
Routing Walk-In (BLD) | 12/14/2012 | 12/14/2012 | 12/14/2012 | P | FAIL |
Perry Paine
|
|
|
|
Application received | | 12/14/2012 | 12/14/2012 | | DONE |
Barbara Stitt
|
|
|
|
1st review completed | | | 12/14/2012 | | DONE |
|
|
|
|