Print Statement | | | 11/27/2013 | | DONE |
Tisha Gallop
|
|
|
e-mailed to Cecyl Brock at EKC
|
Third Notice | | 11/5/2013 | 11/26/2013 | | DONE |
|
|
|
|
Third Notice | | 10/15/2013 | 10/31/2013 | | DONE |
|
|
|
e-mailed to Brian Ellsworth at EKC
|
Second Notice | | 9/8/2013 | 10/10/2013 | | DONE |
|
|
|
Faxed 10-1-13
|
First Notice | | 8/9/2013 | 8/29/2013 | | DONE |
Christina Prado
|
|
|
mailed 8-29-13
|
BLD-Final | 7/29/2013 | 7/30/2013 | 7/30/2013 | A | PASS |
Jim Storey
|
|
|
joe Phone #: ###-####
|
Permanent Occupancy | | | 7/30/2013 | | DONE |
|
|
|
|
BLD-Final | 7/26/2013 | 7/29/2013 | 7/29/2013 | A | DEFR |
Jim Storey
|
|
|
joe Phone #: ###-####
|
FIRE-Final Inspection | 7/25/2013 | 7/26/2013 | 7/29/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed after corrections made while on site.
|
FIRE-Final Inspection | 7/22/2013 | 7/23/2013 | 7/26/2013 | P | NR |
Forrest France
|
|
|
Pending project related fire alarm
|
BLD-Final | 7/26/2013 | 7/26/2013 | 7/26/2013 | P | DEFR |
Jim Storey
|
|
|
late afternoon - last possible -joe Phone #: ###-####
|
Zoning Approval | 7/23/2013 | 7/23/2013 | 7/23/2013 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 7/15/2013 | 7/16/2013 | 7/16/2013 | A | NR |
Forrest France
|
|
|
Project is not in condition for fire life safety final at this time. Finishes underway, project related fire alarm work incomplete.
|
FIRE-Final Inspection | 7/12/2013 | 7/15/2013 | 7/15/2013 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Joe Phone #: ###-#### To be rescheduled for tomorrow morning.
|
Case Summary (BLD) | | | 7/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
(F) Reprint permit | | | 7/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 7/15/2013 | | DONE |
Tisha Gallop
|
|
|
e-mailed to Molly at EKC
|
FIRE-Conference | 6/20/2013 | 6/20/2013 | 6/20/2013 | A | DONE |
Forrest France
|
|
|
Regarding cabinet and bracket heights for new and existing fire extinguishers.
|
FIRE-Final Inspection | 5/23/2013 | 5/24/2013 | 5/29/2013 | P | DONE |
Forrest France
|
|
|
Intended for an on site conference
|
FIRE-Final Inspection | 5/24/2013 | 5/28/2013 | 5/28/2013 | P | PART |
Forrest France
|
|
|
On site conference with the electrical contractor and general contractor regarding exit sign and EM lighting per IFC requirements. Discussed locations of areas to be included at the first through sixth floors, stair towers, and exit discharge.
|
BLD-Other | 5/24/2013 | 5/24/2013 | 5/24/2013 | P | PASS |
Jim Storey
|
|
|
james Phone #: ###-#### fire stopping ok on sharts ada rm's at pt repair
|
BLD-Other | 5/20/2013 | 5/21/2013 | 5/21/2013 | A | PART |
Jim Storey
|
|
|
fire chase insp//James Phone #: ###-#### corewall ok and firestopping in progress/ soffit need 5/8 on coridor side at entrys/ plm clean out brass cap and fire stop anular space.
|
BLD-Concrete | 5/15/2013 | 5/15/2013 | 5/15/2013 | P | PASS |
Jim Storey
|
|
|
Joe Phone #: ###-#### pt pour back of slab ok to proceed
|
FIRE-Sprinkler Rough-in | 5/13/2013 | 5/13/2013 | 5/13/2013 | A | PART |
Forrest France
|
|
|
Fire sprinkler work at the first floor lobby sheetrock soffits and grid ceiling areas okayed for cover.
|
BLD-Conference | 5/3/2013 | 5/6/2013 | 5/6/2013 | A | FAIL |
Jim Storey
|
|
|
joe Phone #: ###-#### c/.n 32 clear with ada doors in ada rm's
|
FIRE-Conference | 4/25/2013 | 4/29/2013 | 4/29/2013 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding fire sprinkler work, existing coverage issues, and new manual pull station locations.
|
BLD-Footing | 4/22/2013 | 4/22/2013 | 4/22/2013 | P | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. Column pad footings for new porte cochere Per RFI from stapley engineering. Will have have special inspection.
|
BLD-Conference | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Jim Storey
|
|
|
james Phone #: ###-#### pt coulpers w/ cable protection in place. ok to cover.
|
Plan Reviewer's activity | | | 4/9/2013 | | DONE |
Sam Zahorka
|
|
|
Rusty – I don’t believe I responded directly to the issue described below of whether free movement of the couplers is critical to the system.
It is my opinion that the use of a foam disk (or other form of compressible material) at the ends of the couplers will not materially affect the performance of the repair. If the disks are not used, the couplers will act like intermediate stressing anchors (which is a common approach used in new construction).
Kent Soelberg
(o) ###-####
(c) ###-####
From: Rusty Boicourt [mailto:boicourtr@mti-id.com]
Sent: Monday, April 01, 2013 5:22 PM
To: Soelberg, Kent/BOI
Cc: 'szahorka@cityofboise.org'; gregl@stapley.net
Subject: PT repair status
Hi Kent,
We successfully tensioned all re-coupled PT strands this morning without any difficulty. The above photos show the basic staggered orientation of the banded strands and the final orientation after tensioning. We achieved ~4700 psi (to result in 24.5 kips effective load) on each strand. Elongation varied from about 8 inches to a little over 10 inches (no more than 7% elongation).
Because the strands sit so close to each other the plastic conduit encasement could not be used. So we propose to wrap the strands together in a single ensheathment using grease tape. This is the standard practice recommended by Vector and others and specified in PTI DC80.3-12/ICRI 320.6 section 4.5.7.1.4 Sheathing Repair. The emphasis seems to be corrosion resistance and not movement of the strands after embedment in new concrete. If free movement is critical to the system, we can include a compressible material (foam disk) at the ends of the couplers prior to tape wrap to allow the couplers to move back and forth a bit parallel to the cable.
Please reply with any concerns/comments/ideas. We can complete the repairs as soon as tomorrow.
Thank you,
Rusty Boicourt, P.G.
NDE & Materials Specialist
From: Kent.Soelberg@CH2M.com [mailto:Kent.Soelberg@CH2M.com]
Sent: Monday, April 01, 2013 2:08 PM
To: Rusty Boicourt
Subject: I just talked to Sam
He tells me you are sending me an update to the procedures. I will hold off sending my comments to Sam until I hear from you. I am hoping to feeling well enough tomorrow to go out to another project site in the morning as scheduled, so it would be nice to button yours up today if possible. Call my cell if you have any questions.
Kent Soelberg
(o) ###-####
(c) ###-####
|
Routing Off Site - STRUCTURAL | 3/28/2013 | | 4/8/2013 | | PASS |
Sam Zahorka
|
|
|
Sam – it looks like my involvement is done with this one. Although I never provided you with any formal review comments (the repairs moved faster than my paperwork), I can tell you that in the discussions I had with both Rusty and Greg last Friday I was able to outline my primary concerns:
1. The engineer (Greg) should get the recommended stressing loads from the PT supplier
2. The splice chuck locations should allow free movement of the chucks during the stressing operation
3. The procedures should require the inspector to document the applied jacking force and elongations
In the end, it looks like each of my concerns were addressed. While I do not have access to all of the design information, in general my sense is the final repair will allow for safe use of the structure with only a moderate reduction in overall capacity.
|
BLD-Other | 3/29/2013 | 4/1/2013 | 4/1/2013 | A | PART |
Jim Storey
|
|
|
post tension cable insp//James Phone #: ###-#### work ok to proceed e mail with engineer ok as well as elonggations discused w/si on site.
|
Plan Reviewer's activity | | | 4/1/2013 | | DONE |
Sam Zahorka
|
|
|
Site visit completed with Jim Storey the structural inspector. Observed the corrections for the PT strands being cut. Identified new strands, sleeves, couplers. Waiting for Outsource structural reviewers final approval letter.
|
Telephone call | | | 3/19/2013 | | DONE |
Sam Zahorka
|
|
|
Left message with the engineer Greg Leishman to return my telephone call. Need engineered solution for the PT cable repair to share with the sstructural inspector.
|
BLD-Conference | 3/18/2013 | 3/18/2013 | 3/18/2013 | P | PASS |
Jim Storey
|
|
|
Joe Phone #: ###-####
|
BLD-Other | 2/19/2013 | 2/19/2013 | 2/19/2013 | P | PASS |
Jim Storey
|
|
|
Fire proofing inspection please-Joseph Phone #: ###-####
|
Telephone call | | | 2/15/2013 | | DONE |
Sam Zahorka
|
|
|
Spoke with Brian Ellsworth the contractor. Let him know the engineer has contacted the Building offical to explain the process and steps being taken to correct the cutting of the post tension cables. The engineer is writing a response and will email to the Building Department ASAP. I also let Brian know the parcel hold/tags will be removed to allow inspections and that the CDHD approved plans have been received.
|
Telephone call | | | 2/15/2013 | | DONE |
Sam Zahorka
|
|
|
Called the Structural inspector and let him know about the correspondance between the Engineer and the Building Official. Let the inspector know the parcel tag/hold has been removed to allow inspections due to the reassurance provided from the engineer to the buildingofficial that the post tension cables are being repaired.
|
Plan resubmittals received | | | 2/14/2013 | | DONE |
Tisha Gallop
|
|
|
received CDHD approved stamped plans; taken to Sam Zahorka.
|
Plan Reviewer's activity | | | 2/12/2013 | | DONE |
Sam Zahorka
|
|
|
It was brought to my attention by the field inspector that the post tension cables were cut by the contractor. Direction was given to contact the architect and engineer of record for this project.
|
Telephone call | | | 2/12/2013 | | DONE |
Sam Zahorka
|
|
|
Called the architect Gerald Goldbach and the Engineer Greg Leishman. Let them know about the filed inspectors findings of the post tension cables being cut by the contractor. Informed them that engineering and permits are required to repair. The engineered repair solution once submitted to the building department will be outsourced to structural review for approval.
|
FIRE-Conference | 2/1/2013 | 2/4/2013 | 2/4/2013 | A | DONE |
Forrest France
|
|
|
Regarding fire alarm and sprinkler trade permits.
|
FIRE-Conference | 1/30/2013 | 1/30/2013 | 1/30/2013 | P | DONE |
Forrest France
|
|
|
|
BLD-Conference | 1/30/2013 | 1/30/2013 | 1/30/2013 | P | PART |
Jim Storey
|
|
|
call Joe Phone #: ###-#### walked job site/ arch to respond to shaft conditions found.
|
BLD-Conference | 1/29/2013 | 1/30/2013 | 1/30/2013 | A | DEFR |
Jim Storey
|
|
|
call Joe Phone #: ###-####
|
OVERRIDE | | | 1/25/2013 | | |
|
|
|
|
Plan assigned to (SRZ) | 12/17/2012 | 12/17/2012 | 1/25/2013 | | PASS |
Sam Zahorka
|
|
|
1st review completed - Holiday Inn Express
|
Issue PAID IN FULL permit | | | 1/25/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 1/24/2013 | | 1/25/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2013 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 1/25/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 1/25/2013 | | DONE |
Christina Prado
|
|
|
called Brian to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 1/25/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 1/23/2013 | | 1/24/2013 | | PASS |
Tim Frost
|
|
|
|
Routing - PLAN CHECK | 1/9/2013 | | 1/23/2013 | | PASS |
Sam Zahorka
|
|
|
Issuance Pending Fire plan review to PASS.
|
Plan resubmittals received | | | 1/16/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets COV.1, A1.0, A1.1, A1.2, A1.3, A1.4, A1.5, A3.1, A8.0; taken to Sam Zahorka.
|
1st review completed | | | 1/9/2013 | | DONE |
|
|
|
Failed - Plan Check, Fire
|
Plan Reviewer's activity | | | 1/9/2013 | | DONE |
|
|
|
Emailed failed reviewed to RP
|
Telephone call | | | 1/9/2013 | | DONE |
Sam Zahorka
|
|
|
Telephoned the architect Gerald Goldbach and reviewed needed corrections with him over the telephone. Emailed the special inspection application #310 to him to forward to the architect to complete. Waiting for resubmittals.
|
Routing - FIRE | 1/8/2012 | | 1/9/2013 | | FAIL |
Scott Arellano
|
|
|
|
Routing - PLAN CHECK | 12/26/2012 | | 1/8/2013 | | FAIL |
Sam Zahorka
|
|
|
Corrections are needed. Routed to Fire plan review.
|
Routing - Design Review | 12/21/2012 | | 12/26/2012 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - CZC12-00262
|
Routing - Erosion and Sediment | 12/20/2012 | | 12/21/2012 | | PASS |
Kimberly M. Johnson
|
|
|
waiver approved
|
Routing - PUBLIC WORKS | | | 12/20/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 12/19/2012 | | 12/20/2012 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 12/17/2012 | | 12/18/2012 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/17/2012 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/17/2012 | | PASS |
John Menard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/17/2012 | | DONE |
Christina Prado
|
|
|
|
Pending Assignment by JCB | 12/17/2012 | | 12/17/2012 | | DONE |
Jason Blais
|
|
|
|
Application received | | 12/17/2012 | | | |
|
|
|
|
Routing Off Site - C.D.H | 12/17/2012 | | | | |
Sam Zahorka
|
|
|
Needs Central District Health Department approval for dining/kitchenette area. Called contractor and he will bring down CDHD approval documents.
|