Third Notice | | 6/9/2013 | 6/10/2013 | | DONE |
|
|
|
|
Third Notice | | 4/28/2013 | 6/4/2013 | | DONE |
|
|
|
faxed
|
Second Notice | | 4/1/2013 | 4/23/2013 | | DONE |
|
|
|
|
First Notice | | 3/18/2013 | 3/22/2013 | | DONE |
|
|
|
Faxed 3-22-13
|
BLD-Final | 3/7/2013 | 3/8/2013 | 3/8/2013 | P | PASS |
Jim Storey
|
|
|
todd Phone #: ###-####
|
FIRE-Final Inspection | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety is approved pending one fire extinguisher is placed in the existing cabinet as discussed.
|
Permanent Occupancy | | | 3/8/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 3/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - MECHANICAL | 2/25/2013 | | 2/25/2013 | | PASS |
Troy James
|
|
|
Forgot to add activity for approved mechanical. Reviewed through the eplan.
|
BLD-Framing/Rough-in | 2/3/2013 | 2/4/2013 | 2/4/2013 | A | PASS |
Jim Storey
|
|
|
Front door should be unlocked. Phone #: ###-#### >> Inspection requested via web by Todd Weltner
|
OVERRIDE | | | 1/30/2013 | | |
|
|
|
|
Telephone call | | | 1/30/2013 | | DONE |
Tisha Gallop
|
|
|
sent e-mail to Richard Honsinger/Architect and Todd Weltner/Verical Corp that permit ready, fees due, need to come in to pay and receive inspection card.
|
Issue PAID IN FULL permit | | | 1/30/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 1/30/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 1/30/2013 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 1/28/2013 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 1/10/2013 | | 1/28/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/10/2013 | | 1/28/2013 | | PASS |
Tim L. Woodard
|
|
|
Approved with attached letter from Tenant about occupant load. TLW
|
Routing - FIRE | 1/10/2013 | | 1/15/2013 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Routing - MECHANICAL | 1/10/2013 | | 1/14/2013 | | FAIL |
Troy James
|
|
|
eplan
Need .6 cfm per square foot exhuast from the pedicure area.
|
Routing - Erosion and Sediment | 1/10/2013 | | 1/11/2013 | | PASS |
Clint A Smith
|
|
|
ESC plan waiver approved with attached conditions.
|
Routing - PLUMBING | 1/10/2013 | | 1/11/2013 | | PASS |
Daryl Spivey
|
|
|
1. RPBP's required on hot and cold supply to pedicure stations.
2. Install per 2009 ISPC.
|
Intake Approval | | | 1/10/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2013 | | 1/10/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 1/10/2013 | | 1/10/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Intake Approval | | | 12/19/2012 | | FAIL |
Tim L. Woodard
|
|
|
Richard,
Please correct the follow items and resubmit the drawings for prescreen: first, sheets A2.11 and A2.31 need to be reuploaded in the horizontal orientation (as required by the Electronic Upload Guide); second, provide mechanical plans stamped and signed be an Idaho licensed engineer; third, provide plumbing plans stamped and signed be an Idaho licensed engineer; lastly, provide a plumbing fixture analysis. Additional information on these items can be found as change marks to the Minor TI Submittal Checklist.
Best regards,
Tim Woodard
City of Boise
###-####
|
Application received | | | 12/18/2012 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2012 2:34PM
|