(AMORE NAIL SALON – Bown Crossing Market Place - BLDG A - 1st FLR) Permit is to remodel an existing 1,075 square foot salon and turn this space into a nail salon. Approval contingent upon adhering to the approved plans on file. Work to include: [construction of interior non-bearing walls to create a pedicure area, a manicure area, a new break room, and a wash room], installation of new doors / accessible hardware, installation of new accessible counter, and finishes in compliance with chapter 8 of the 2009 IBC. NOTE: This tenant space was previously occupied by “SUN VALLEY TANNING LLC” under BLD09-02031. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 6/9/20136/10/2013 DONE
Third Notice 4/28/20136/4/2013 DONE
faxed
Second Notice 4/1/20134/23/2013 DONE
First Notice 3/18/20133/22/2013 DONE
Faxed 3-22-13
BLD-Final3/7/20133/8/20133/8/2013PPASS
DetailsJim Storey
todd Phone #: ###-####
FIRE-Final Inspection3/7/20133/8/20133/8/2013APASS
DetailsForrest France
Fire life safety is approved pending one fire extinguisher is placed in the existing cabinet as discussed.
Permanent Occupancy  3/8/2013 DONE
DetailsTisha Gallop
Print Occupancy Form  3/6/2013 DONE
DetailsBarbara Stitt
Routing - MECHANICAL2/25/2013 2/25/2013 PASS
DetailsTroy James
Forgot to add activity for approved mechanical. Reviewed through the eplan.
BLD-Framing/Rough-in2/3/20132/4/20132/4/2013APASS
DetailsJim Storey
Front door should be unlocked. Phone #: ###-#### >> Inspection requested via web by Todd Weltner
OVERRIDE  1/30/2013  
Telephone call  1/30/2013 DONE
DetailsTisha Gallop
sent e-mail to Richard Honsinger/Architect and Todd Weltner/Verical Corp that permit ready, fees due, need to come in to pay and receive inspection card.
Issue PAID IN FULL permit  1/30/2013 DONE
DetailsChristina Prado
Print Occupancy Form  1/30/2013 DONE
DetailsChristina Prado
Permit Ready to Issue  1/30/2013 DONE
DetailsTisha Gallop
1st review completed  1/28/2013 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/28/2013 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)1/10/2013 1/28/2013 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK1/10/2013 1/28/2013 PASS
DetailsTim L. Woodard
Approved with attached letter from Tenant about occupant load. TLW
Routing - FIRE1/10/2013 1/15/2013 PASS
DetailsScott Arellano
Attached IFC comments to plans.
Routing - MECHANICAL1/10/2013 1/14/2013 FAIL
DetailsTroy James
eplan
Need .6 cfm per square foot exhuast from the pedicure area.
Routing - Erosion and Sediment1/10/2013 1/11/2013 PASS
DetailsClint A Smith
ESC plan waiver approved with attached conditions.
Routing - PLUMBING1/10/2013 1/11/2013 PASS
DetailsDaryl Spivey
1. RPBP's required on hot and cold supply to pedicure stations.
2. Install per 2009 ISPC.
Intake Approval  1/10/2013 PASS
DetailsTim L. Woodard
Routing - PUBLIC WORKS1/10/2013 1/10/2013 PASS
DetailsBeverly Mountain
Routing - Addressing1/10/2013 1/10/2013 PASS
DetailsJason C. Taylor
Intake Approval  12/19/2012 FAIL
DetailsTim L. Woodard
Richard,

Please correct the follow items and resubmit the drawings for prescreen: first, sheets A2.11 and A2.31 need to be reuploaded in the horizontal orientation (as required by the Electronic Upload Guide); second, provide mechanical plans stamped and signed be an Idaho licensed engineer; third, provide plumbing plans stamped and signed be an Idaho licensed engineer; lastly, provide a plumbing fixture analysis. Additional information on these items can be found as change marks to the Minor TI Submittal Checklist.

Best regards,

Tim Woodard
City of Boise
###-####
Application received  12/18/2012 DONE
Application submitted via PDS Online on Dec 18 2012 2:34PM