BLD-Framing/Rough-in | 2/12/2013 | 2/12/2013 | 2/12/2013 | P | PASS |
Tom Arcoraci
|
|
|
please call 30min prior - matt Phone #: ###-#### insulation ok also
|
BLD-Foundation | 1/4/2013 | 1/7/2013 | 1/7/2013 | A | PASS |
Dave Hannah
|
|
|
Greg late am if possible Phone #: ###-####
|
BLD-Footing | 1/3/2013 | 1/4/2013 | 1/4/2013 | A | PASS |
Dave Hannah
|
|
|
Matt Phone #: ###-#### crew is tenting and heating ftg and stem wall gruond is frost free
|
Routing Walk-In (PW Hillside) | 1/3/2013 | 1/3/2013 | 1/3/2013 | P | PASS |
Jason C. Taylor
|
|
|
Geotechnical report/subgrade recieved (MTI) conditions approved. Footing Inspection needs to be scheduled with City. Jason Taylor (###-####)
|
Routing Walk-In (Zoning) | 1/3/2013 | 1/3/2013 | 1/3/2013 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 1/3/2013 | 1/3/2013 | 1/3/2013 | P | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 1/3/2013 | 1/3/2013 | 1/3/2013 | | PASS |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 1/2/2013 | 1/2/2013 | 1/3/2013 | | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 1/3/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/3/2013 | | |
|
|
|
|
1st review completed | | | 1/3/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/3/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/3/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 1/3/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/3/2013 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 1/2/2013 | 1/2/2013 | 1/2/2013 | P | FAIL |
Perry Paine
|
|
|
need soils report, engineering for foundation and ESC waiver request submitted
|
Routing Walk-In (PW Hillside) | 1/2/2013 | 1/2/2013 | 1/2/2013 | A | FAIL |
Perry Paine
|
|
|
need soils report
|
Application received | | 1/2/2013 | | | |
|
|
|
|