Print Statement | | | 11/21/2013 | | DONE |
|
|
|
|
Print Statement | | | 6/7/2013 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 5/18/2013 | 6/4/2013 | | DONE |
Christina Prado
|
|
|
completed 6-7-13
|
Permanent Occupancy | | | 5/8/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 5/6/2013 | 5/7/2013 | 5/7/2013 | P | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
FIRE-Final Inspection | 5/6/2013 | 5/7/2013 | 5/7/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
FIRE-Conference | 4/23/2013 | 4/24/2013 | 4/24/2013 | A | DONE |
Forrest France
|
|
|
On site discussion with contractor regarding life safety issues including exit signs, EM lights, PFE's.
|
BLD-Ceiling Grid Inspection | 4/12/2013 | 4/15/2013 | 4/17/2013 | A | NR |
Dave Hannah
|
|
|
tom Phone #: ###-####
|
Print Occupancy Form | | | 4/12/2013 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 4/12/2013 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/12/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 4/1/2013 | 4/1/2013 | 4/8/2013 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 4/3/2013 | | 4/8/2013 | | DONE |
Carl Westfall
|
|
|
Routing completed (CJW was on vacation Thursday April 4 and Friday April 5.
|
Routing PW Sewer Rating | 4/3/2013 | | 4/4/2013 | | PASS |
Connie Baumgartner
|
|
|
New toilet, shower, and lavatory.
|
BLD-Other | 4/2/2013 | 4/3/2013 | 4/3/2013 | A | PASS |
Dave Hannah
|
|
|
fireblocking - tom Phone #: ###-#### patching fireproofing
|
Routing - PLAN CHECK | 4/1/2013 | | 4/3/2013 | | PASS |
Carl Westfall
|
|
|
2nd plan mod approved with "red lines".
|
Plan Modification Accepted | | | 4/1/2013 | | DONE |
Christina Prado
|
|
|
Maria Scott requested 2nd plan modification to change Storage #6177 to a Shower room. Includes changing ACT ceiling to hard lid and adding plumbing elements as noted on plan sheets and elevations. Check with Carl Westfall prior to scheduling inspections
|
FIRE-Conference | 3/21/2013 | 3/21/2013 | 3/22/2013 | P | DONE |
Forrest France
|
|
|
Regarding fire sprinkler coverage
|
BLD-Framing/Rough-in | 3/15/2013 | 3/15/2013 | 3/19/2013 | P | PASS |
Dave Hannah
|
|
|
tom Phone #: ###-####
|
BLD-Framing/Rough-in | 3/12/2013 | 3/13/2013 | 3/14/2013 | A | PART |
Dave Hannah
|
|
|
tom Phone #: ###-#### ok to cover top of walls in conf rooms so they can build soffits
|
CHANGE STATUS TO (ISS) | | | 3/11/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 3/8/2013 | | |
|
|
|
|
Plan assigned to (CJW) | 3/4/2013 | 3/4/2013 | 3/7/2013 | | PASS |
Carl Westfall
|
|
|
MICROSOFT - plan modification
|
Routing - PLAN CHECK | 3/4/2013 | | 3/7/2013 | | PASS |
Carl Westfall
|
|
|
1st plan mod reviewed and approved
|
BLD-Conference | 3/1/2013 | 3/1/2013 | 3/4/2013 | P | DONE |
Dave Hannah
|
|
|
tom Phone #: ###-#### needs to resubmit new floor plans
|
Plan Modification Accepted | | | 3/4/2013 | | |
|
|
|
Plan Modification Accepted - Tracey from Mcalvain construction called requesting plan mod workflow to be started. Plans assigned to Carl Westfall.
|
Permit Ready to Issue | | | 2/22/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 2/22/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 1/4/2013 | 1/4/2013 | 2/6/2013 | | PASS |
Carl Westfall
|
|
|
MICROSOFT BOISE SALES OFFICE (20 days - Jan 31) ePlanReview - Microsoft
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/4/2013 | | 2/5/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines" after resubmittal review.
|
Routing PW Sewer Rating | 2/5/2013 | | 2/5/2013 | | PASS |
Connie Baumgartner
|
|
|
A sink is being added. Failed to send this to Connie the first time.
|
Plan resubmittals received | | | 2/4/2013 | | DONE |
|
|
|
|
1st review completed | | | 1/30/2013 | | FAIL |
|
|
|
Failed building
|
Routing - FIRE | 1/4/2013 | | 1/30/2013 | | PASS |
Tim Frost
|
|
|
Completed by Tim Frost 1/8/13
|
Routing - PLAN CHECK | 1/4/2013 | | 1/29/2013 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on Jan 18 and was finished on Jan 29. A lot of time was spent on how to deal with proposed A-3 on the 6th story. Revised drawings were required. See the plan review report.
|
Payment Received | | | 1/4/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 1/4/2013 | | PASS |
Tim L. Woodard
|
|
|
Passed - changed to a Major TI
|
Pending Assignment by JCB | 1/4/2013 | | 1/4/2013 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 1/2/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 2 2013 4:56PM
|