Third Notice | | 12/17/2017 | 1/12/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
Third Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Third Notice | | 10/17/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
Second Notice | | 9/29/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
First Notice | 8/31/2017 | 8/31/2017 | 9/19/2017 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 9-20-17
|
BLD-Final | 8/30/2017 | 8/30/2017 | 8/31/2017 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | PASS |
Jim Sly
|
|
|
|
BLD-Aging Inspection | 8/30/2017 | 8/30/2017 | 8/30/2017 | | CANC |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 4/17/2017 | 4/18/2017 | 4/18/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 8/29/2013 | 8/30/2013 | 8/30/2013 | A | FAIL |
Troy Cobbley
|
|
|
Life safety can be passed when the project related fire alarm permit has been finaled.
|
BLD-Final | 8/29/2013 | 8/29/2013 | 8/29/2013 | P | NR |
Jim Storey
|
|
|
|
Inspection Record Card- Bld | | | 8/2/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Conference | 7/26/2013 | 7/26/2013 | 7/26/2013 | A | PART |
Jim Storey
|
|
|
wing walls and ramp to resolve transition of lower floor to wheelchair lift access.
|
BLD-Concrete | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PASS |
Jim Storey
|
|
|
grout ok to back pour floor/ raised floor ok to cover.
|
BLD-Ceiling Grid Inspection | 7/17/2013 | 7/18/2013 | 7/18/2013 | A | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 7/10/2013 | 7/10/2013 | 7/10/2013 | P | FAIL |
Jim Storey
|
|
|
need beam stifners and top chord braces per engineering/ si insp for new windows upon p&z aproval reinsp. required.
|
BLD-Framing/Rough-in | 5/29/2013 | 5/30/2013 | 5/30/2013 | A | PASS |
Jim Storey
|
|
|
floor framing water closet west end ok .
|
Plan resubmittals received | | | 5/23/2013 | | DONE |
Tisha Gallop
|
|
|
received memo and 2 1/2" x 11" engineering details (5 sheets); put in Jim Story's box per his request.
|
FIRE-Final Inspection | 5/16/2013 | 5/16/2013 | 5/17/2013 | P | PART |
Troy Cobbley
|
|
|
Life safety is passed for the area clouded in red pen in the area dated "5/15" in the orange high-lited area. Egress approved by Romeo for this area.
|
BLD-Conference | 5/15/2013 | 5/16/2013 | 5/16/2013 | P | PASS |
Jim Storey
|
|
|
jason ###-#### offices north as well as documented exit path ok to occupy
|
BLD-Final | 5/14/2013 | 5/15/2013 | 5/15/2013 | P | DEFR |
Jim Storey
|
|
|
walk 1-b for occ of area.5/16
|
FIRE-Final Inspection | 5/14/2013 | 5/15/2013 | 5/15/2013 | A | CANC |
Troy Cobbley
|
|
|
Jeremy wants to reschedule for tomorrow - Phone #: ###-####
|
BLD-Final | 5/2/2013 | 5/2/2013 | 5/2/2013 | P | PASS |
Jim Storey
|
|
|
temp occ of phase 1b call center area. pdf file saved for area exiting plan aproved by fire dept and planreviw for call center temp occ.
|
FIRE-Final Inspection | 5/2/2013 | 5/2/2013 | 5/2/2013 | P | PART |
Troy Cobbley
|
|
|
The exiting from the phase of construction dated "5/3" and highlighted in purple is approved. The life safety in this area is passed as well. This area is to the immediate west of the call center.
|
FIRE-Final Inspection | 4/30/2013 | 5/1/2013 | 5/1/2013 | A | FAIL |
Troy Cobbley
|
|
|
Waiting for fire dept approval of the exiting from the phase of construction dated "5/3" and highlighted in purple. This area is to the immediate west of the call center.
|
BLD-Conference | 4/29/2013 | 4/29/2013 | 4/29/2013 | P | PASS |
Jim Storey
|
|
|
ceilling ok west rm for temp exit phase 1 b ok
|
BLD-Final | 4/23/2013 | 4/23/2013 | 4/23/2013 | P | PASS |
Jim Storey
|
|
|
Phase 1 A ok for occupancy
|
FIRE-Final Inspection | 4/22/2013 | 4/23/2013 | 4/23/2013 | A | PART |
Troy Cobbley
|
|
|
Life safety is passed in Area "1A" is ok to occupy as far as Fire is concerned. Emergency lighting is actually every light in the building and not scattered as per plan.
|
BLD-Other | 4/16/2013 | 4/17/2013 | 4/17/2013 | A | PART |
Jim Storey
|
|
|
need mech insp above ceilling/ remove papper on com lines in ceilling/ ok to drop tile will spot check// phase one temp exit signage above west door and clear exit path out of bldg..
|
BLD-Conference | 4/3/2013 | 4/5/2013 | 4/5/2013 | A | PASS |
Jim Storey
|
|
|
9:00 am meeting w/ idaho power had idaho power rep./ alta const rep and mec/plm/ele to review phased occ to area 1 fire will be getting aprovals from ronero sub mital should be in route by eary next week // occ to be set for 4/24/2013.
|
BLD-Conference | 4/3/2013 | 4/4/2013 | 4/4/2013 | A | PASS |
Jim Storey
|
|
|
complaint still working even though SWO is posted. bld13-000790 isued
|
BLD-Concrete | 3/27/2013 | 3/27/2013 | 3/27/2013 | P | PASS |
Jim Storey
|
|
|
grout under mes col. ok for cover on bld13-00028 unable to add activty on that permit.
|
BLD-Conference | 3/19/2013 | 3/20/2013 | 3/20/2013 | A | PASS |
Jim Storey
|
|
|
reviewed job progress/ drop off plm and ele resubmitals.
|
OVERRIDE | | | 3/19/2013 | | |
|
|
|
|
Plan assigned to (301) | 3/14/2013 | 3/14/2013 | 3/19/2013 | | DONE |
Jim Storey
|
|
|
|
Routing - PLAN CHECK | 3/14/2013 | | 3/19/2013 | | PASS |
Jim Storey
|
|
|
|
Routing - PLUMBING | 3/14/2013 | | 3/19/2013 | | PASS |
Jim Johnson
|
|
|
Per Jim
|
Routing - ELECTRICAL | 3/14/2013 | | 3/19/2013 | | PASS |
Daryl DeGrange
|
|
|
Per Jim
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2013 | | DONE |
Jim Storey
|
|
|
|
Permit Ready to Issue | | | 3/19/2013 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/19/2013 | | DONE |
Christina Prado
|
|
|
Per Jim Storey - resubmittals only - no fees due
|
Routing - MECHANICAL | 3/15/2013 | | 3/15/2013 | | PASS |
Troy James
|
|
|
new gas piping to exterior
|
Plan Modification Accepted | | | 3/14/2013 | | DONE |
Christina Prado
|
|
|
Received plan mod to ad gas line to bbq & add power to accomodate a future chair lift plans affected are as follows - P2.13, P4.00, E0.00, E1.02, E1.03, E1.21, E1.22, E1.23, E2.01, E2.02, E2.03, E2.04, E2.11, E2.12, E2.13, E2.14, E2.21, E2.22, E2.23, E2.24, E3.01, E5.01, E5.02, E5.03 & E6.01;routed to Jim Storey for review.
|
BLD-Footing | 3/6/2013 | 3/6/2013 | 3/6/2013 | A | PART |
Jim Storey
|
|
|
ft holes and soil ok for mez
|
Issue PAID IN FULL permit | | | 3/1/2013 | | DONE |
|
|
|
|
Plan assigned to (301) | 1/11/2013 | 1/11/2013 | 2/26/2013 | | PASS |
Jim Storey
|
|
|
|
1st review completed | | | 2/26/2013 | | PART |
|
|
|
pending responce from the arch. to resolve code issues that have been noted on reviewed set.
|
Routing - FIRE | 2/25/2013 | | 2/26/2013 | | PASS |
Scott Arellano
|
|
|
Attached IFC plan review comments to plans. See red lined annotations on plan sheet A0.01.
|
Routing - PLAN CHECK | 2/26/2013 | | 2/26/2013 | | PASS |
Jim Storey
|
|
|
|
Print permit w/o conditions | | | 2/26/2013 | | ```` |
|
|
|
|
1st review completed | | | 2/26/2013 | | ```` |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2013 | | ```` |
|
|
|
|
Inspection Record Card- Bld | | | 2/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 2/26/2013 | | |
|
|
|
|
Telephone call | | | 2/26/2013 | | |
|
|
|
2-26-13 called David Blodgett permit ready and fee given Also need GC & FORM ///DLD
|
Routing - PLUMBING | 2/25/2013 | | 2/25/2013 | | PASS |
Jim Johnson
|
|
|
plan mod. as per Idaho State plumbing code
|
Routing - PUBLIC WORKS | 2/20/2013 | | 2/20/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLUMBING | 1/11/2013 | | 1/10/2013 | | PASS |
Jim Johnson
|
|
|
as per plan and 2009 upc
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/9/2013 | | PASS |
Jim Storey
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | 1/7/2013 | | | |
|
|
|
|