FIRE-Final Inspection | 8/29/2013 | 8/30/2013 | 8/30/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 8/29/2013 | 8/29/2013 | 8/29/2013 | P | PART |
Jim Storey
|
|
|
handrail 12 at landinds/ si report
|
OVERRIDE | | | 7/30/2013 | | |
|
|
|
|
OVERRIDE | | | 7/30/2013 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/30/2013 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 7/30/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - Design Review | 7/30/2013 | | 7/30/2013 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 7/30/2013 | | 7/30/2013 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Telephone call | | | 7/30/2013 | | DONE |
Christina Prado
|
|
|
called David to advise plan mod #3 is ready and gave fees due
|
Permit Ready to Issue | | | 7/30/2013 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 7/8/2013 | | 7/30/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 7/8/2013 | | 7/30/2013 | | PASS |
Tim L. Woodard
|
|
|
Plan mod only changed location of windows. TLW
|
Routing - PLANNING | 7/8/2013 | | 7/8/2013 | | FAIL |
Andrea Tuning
|
|
|
The applicant will be required to complete a DR application prior to the building permit.
|
Plan resubmittals received | | | 7/8/2013 | | DONE |
Christina Prado
|
|
|
received two revised sheets marked A3.00 & A3.02; routed to Tim for further review
|
OVERRIDE | | | 6/14/2013 | | |
|
|
|
|
Telephone call | | | 6/14/2013 | | DONE |
Tisha Gallop
|
|
|
called David Blodgett and told him plan mod is ready and fees.
|
Plan assigned to (TLW) | 5/24/2013 | | 6/14/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/24/2013 | | 6/14/2013 | | PASS |
Tim L. Woodard
|
|
|
Added 1 hour for revised anchorage connection. No change to scope of work. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/14/2013 | | DONE |
Tim L. Woodard
|
|
|
|
BLD-Framing/Rough-in | 6/10/2013 | 6/10/2013 | 6/10/2013 | A | PASS |
Jim Storey
|
|
|
north west exterior entry ok to cover inside pending ele aproval.
|
Plan resubmittals received | | | 5/24/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheet A3.00; changed plans to REV status and taken back to Tim W.
|
Plan assigned to (TLW) | 3/15/2013 | | 4/9/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/8/2013 | | 4/9/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 4/9/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 4/9/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/9/2013 | | |
|
|
|
|
Telephone call | | | 4/9/2013 | | |
|
|
|
4-9-13 called David Blodgett permit ready and fee given Also called Alta construction they need to pay past due fees on bld11-0 ///dld
|
Routing - PLANNING | 4/5/2013 | | 4/8/2013 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 3/15/2013 | | 4/5/2013 | | PASS |
Tim L. Woodard
|
|
|
New windows and platform lift modifications approved. TLW
|
BLD-Concrete | 3/22/2013 | 3/22/2013 | 3/22/2013 | A | PASS |
Jim Storey
|
|
|
vestabule slab rebar ect ok to place pour back of interior slab east end ok
|
BLD-Footing | 3/19/2013 | 3/19/2013 | 3/19/2013 | A | PASS |
Jim Storey
|
|
|
exterior ft and walls rebar ok
|
Plan Modification Accepted | | | 3/15/2013 | | DONE |
Christina Prado
|
|
|
received plan modification to add a wheelchair access lift to mezzanine and window changes; received three sets of plans marke A0.00, A0.01, A0.02, A1.00, A1.01, A2.01, A2.02, A2.11, A2.12, A2.31, A3.00, A3.01, A3.02, A4.01, A5.01, S0.01, S1.01, S1.10, S2.01 & S2.10; Taken to Tim Woodard for review
|
BLD-Footing | 3/7/2013 | 3/7/2013 | 3/7/2013 | A | PASS |
Jim Storey
|
|
|
pending si report
|
Issue PAID IN FULL permit | | | 3/1/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 2/21/2013 | | |
|
|
|
|
Routing - FIRE | 2/12/2013 | | 2/21/2013 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Routing - PLAN CHECK | 2/21/2013 | | 2/21/2013 | | PASS |
Tim L. Woodard
|
|
|
Approved with plan review report & BLD13-00002. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2013 | | |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 2/21/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 2/21/2013 | | DONE |
|
|
|
|
Telephone call | | | 2/21/2013 | | DONE |
Christina Prado
|
|
|
called David to advise permit is ready pending GC info and gave fees due
|
Permit Ready to Issue | | | 2/21/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | | | 2/21/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 1/28/2013 | | 2/21/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 2/5/2013 | | 2/12/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - Erosion and Sediment | 2/4/2013 | | 2/5/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Plan resubmittals received | | | 2/4/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of ESC narrative; taken to Tim Woodard
|
1st review completed | | | 1/28/2013 | | FAIL |
|
|
|
Failed ESC & Fire
|
Routing - FIRE | 1/25/2013 | | 1/28/2013 | | FAIL |
Scott Arellano
|
|
|
Faxed & emailed Resubmittal item to architect.
|
Routing - PLAN CHECK | 1/16/2013 | | 1/25/2013 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines and with the finaling of BLD13-00021. TLW
|
Case Summary (BLD) | | | 1/25/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Erosion and Sediment | 1/14/2013 | | 1/15/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
Redlines sent to PD
|
Routing - PLANNING | 1/11/2013 | | 1/14/2013 | | PASS |
Andrea Tuning
|
|
|
|
Routing PW Sewer Rating | 1/11/2013 | | 1/11/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2013 | | 1/11/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 1/10/2013 | | 1/10/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/9/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/9/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/7/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | 1/8/2013 | | | |
|
|
|
|