BLD-Final | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####
|
BLD-Final | 6/30/2014 | 7/1/2014 | 7/1/2014 | A | PASS |
Tony Young
|
|
|
Bob Phone #: ###-####
|
DOC - Permit Finaled | 7/1/2014 | 7/1/2014 | 7/1/2014 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 12/2/2013 | 12/2/2013 | 12/2/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Wall Bracing | 9/24/2013 | 9/26/2013 | 9/27/2013 | P | PASS |
Tony Young
|
|
|
BOBBY Phone #: ###-####,, interior ok
|
BLD-Energy code compliance | 9/19/2013 | 9/20/2013 | 9/20/2013 | A | PASS |
Tom Arcoraci
|
|
|
bobby late morning Phone #: ###-####
|
BLD-Framing/Rough-in | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | PASS |
Tom Arcoraci
|
|
|
Bobby Phone #: ###-####
|
BLD-Wall Bracing | 9/17/2013 | 9/18/2013 | 9/18/2013 | A | PART |
Tony Young
|
|
|
bob - and soffit Phone #: ###-####,, exterior shear ok per ok from engineer allowing staples at 1/2 spacing,, soffits are work in progress,, ok.. will need interior shear later
|
BLD-Framing/Rough-in | 9/12/2013 | 9/13/2013 | 9/13/2013 | A | PART |
Tony Young
|
|
|
Shear inspection please-Bobby Phone #: ###-####,, need full set of plans,, missing main level shear plan,, need ok from engineer of record on using staples,, need alternate hold down on front right of entry door,(existing is on the other side of the window,, ok to nail sheeting around windows to start the flashing and setting of windows
|
Plan resubmittals received | | | 9/13/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 9/13/2013 | | 9/13/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 9/11/2013 | 9/12/2013 | 9/12/2013 | A | FAIL |
Jim Storey
|
|
|
Todd Phone #: ###-#### need to reprint city aproved set to be able to do insp.
|
BLD-Wall Bracing | 9/9/2013 | 9/10/2013 | 9/10/2013 | P | FAIL |
Tony Young
|
|
|
bob Phone #: ###-####,, NOT READY
|
BLD-Wall Bracing | 9/6/2013 | 9/9/2013 | 9/9/2013 | A | NR |
Tony Young
|
|
|
bob Phone #: ###-####
|
BLD-Foundation | 7/11/2013 | 7/12/2013 | 7/12/2013 | A | PART |
Tony Young
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 6/24/2013 | 6/24/2013 | 6/25/2013 | P | PASS |
Tony Young
|
|
|
Joe Phone #: ###-####please call prior to inspection,, remainder of exterior house footings
|
PubWorks Subgrade Approval | 6/24/2013 | 6/24/2013 | 6/24/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer for the entire lower level footings. Building department may be scheduled for footing inspections. Jason Taylor ###-####.
|
BLD-Foundation | 5/21/2013 | 5/22/2013 | 5/22/2013 | P | PART |
Tony Young
|
|
|
joe Phone #: ###-####,, walls on approved footings ok
|
BLD-Footing | 5/15/2013 | 5/15/2013 | 5/16/2013 | P | PART |
Tony Young
|
|
|
Joe-12:30 if possible as everyone will be there to meet with you Phone #: ###-####
|
BLD-Footing | 5/14/2013 | 5/15/2013 | 5/15/2013 | A | PART |
Tony Young
|
|
|
JOE Phone #: ###-####,, work in progress on areas from report
|
PubWorks Subgrade Approval | 5/15/2013 | 5/15/2013 | 5/15/2013 | | DONE |
Jason C. Taylor
|
|
|
Subgrade approval was recieved from geotechnical engineer approving the northern (upper) and eastern wall portions of the residence footings. Lower portions and garage have not been approved. Ponded water or wet and disturbed soil that exists in the keyway areas must be removed prior to placement of concrete. Jason Taylor ###-####.
|
BLD-Footing | 5/14/2013 | 5/14/2013 | 5/14/2013 | P | NR |
Tony Young
|
|
|
JOE Phone #: ###-####,, need soils subgrade approval,, on site visit
|
Routing PW Grading-Hillside | 5/14/2013 | | 5/14/2013 | | PASS |
Jason C. Taylor
|
|
|
Recieved supplemental engineering report for french drains by geotech. Project can proceed with placement of forms. Subgrade approval has not been recieved for placement of footings. Jason Taylor ###-####
|
Issue PAID IN FULL permit | | | 3/25/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | 1/10/2013 | 1/10/2013 | 3/5/2013 | | PASS |
Carl D Madsen
|
|
|
ePlan review
|
Routing - PLAN CHECK | 1/10/2013 | | 3/5/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 3/5/2013 | | 3/5/2013 | | PASS |
Susan Riggs
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/5/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/5/2013 | | |
|
|
|
|
Routing - Erosion and Sediment | 1/28/2013 | | 1/28/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - MECHANICAL | 1/28/2013 | | 1/28/2013 | | PASS |
Troy James
|
|
|
eplan
|
1st review completed | | | 1/15/2013 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/10/2013 | | 1/15/2013 | | FAIL |
Carl D Madsen
|
|
|
ePlan review
|
Routing PW Grading-Hillside | 1/10/2013 | | 1/14/2013 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan needs revised. Spoke with Todd from KM Engineering and Mike W. with Strata about drainage issues. See markups in Project Docs for details. Jason Taylor (###-####)
|
Payment Received | | | 1/10/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Route to Impact Fee Review | 1/10/2013 | 1/15/2013 | 1/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 1/10/2013 | | 1/10/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 1/10/2013 | | 1/10/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 1/10/2013 | | 1/10/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
ESC plan failed. Please refer to the ESC plan checklist.
|
Routing - FIRE | | | 1/10/2013 | | PASS |
Scott Arellano
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/10/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/10/2013 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/10/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/9/2013 | | FAIL |
Christina Prado
|
|
|
Stamp area and CFH
|
Application received | | | 1/8/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 8 2013 4:19PM
|
Routing - MECHANICAL | 1/10/2013 | | 1/15/2012 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - PLANNING | 1/10/2013 | | 1/10/2012 | | FAIL |
Susan Riggs
|
|
|
Need approval of hillside & foothill development permit. Waiting on Jason's review for hillside conditions.
|