Case Summary (BLD) | | | 11/15/2018 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/15/2018 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/15/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 10/7/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/19/2016 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 5/2/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/26/2016 | | DONE |
|
|
|
|
BLD-Final | 12/3/2015 | 12/3/2015 | 12/3/2015 | P | DONE |
Bob Archibald
|
|
|
All corrective provisions completed. Swimming pool will be finaled under its own permit #BLD13-03079.
|
DOC - C/O Approved | | | 12/3/2015 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 10/9/2015 | 10/9/2015 | 10/9/2015 | | DONE |
Jason C. Taylor
|
|
|
All site work and stabilization activities (retaining walls, hyrdo-mulch, rock mulch, etc.) as been completed. Site is finished and is approved for occupancy. Jason Taylor ###-####
|
SUPER- Supervisor's review | 10/1/2015 | 10/1/2015 | 10/1/2015 | | PEND |
Bob Archibald
|
|
|
All items listed on CN dated 4-25-14 with exception of public works approval on drainage and tennis court have been completed.
|
Routing PW Grading-Hillside | 8/7/2015 | | 8/7/2015 | | PASS |
Jason C. Taylor
|
|
|
Recieved structural engineers calculations for retaining wall construction. Alos, recieved verification from RPC that existing wall was built with a keyway. Wall is approved as constructed based on evidence provided. Jason Taylor ###-####.
|
BLD-Framing/Rough-in | 7/31/2015 | 8/3/2015 | 8/4/2015 | P | PASS |
Dave Hannah
|
|
|
Deck framing/repair. Lee @###-####
|
OVERRIDE | | | 7/22/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 7/17/2015 | 7/17/2015 | 7/22/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 7/17/2015 | | 7/22/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
deck revisions
|
Telephone call | | | 7/22/2015 | | DONE |
|
|
|
Called Patrick to let know plan mod is ready and how much is owed-please do no re-issue the permit
|
CHANGE STATUS TO (ISS) | | | 7/22/2015 | | DONE |
Christina Prado
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/22/2015 | | DONE |
|
|
|
please do in re-issue
|
Telephone call | | | 7/21/2015 | | DONE |
|
|
|
called homeowner Patrick Tierney to let him know that his plan modification for the retaining wall was ready to be picked up and fees due.
|
Plan Modification Accepted | | | 7/17/2015 | | DONE |
Christina Prado
|
|
|
Plan mod accepted for additional retaining wall modiications. Three sets of sheets C1.00 & C2.00 and three sets of revised structural calcs were accepted
|
Routing PW Grading-Hillside | 7/17/2015 | | 7/17/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the wall subgrade is acceptable must be approved by Public Works. Call Jason Taylor at ###-####
|
BLD-Conference | 7/16/2015 | 7/16/2015 | 7/16/2015 | A | PEND |
Bob Archibald
|
|
|
Informed Nate and Patrick that 17 Fire Marshal approved soffit vents would be required
|
BLD-Conference | 7/8/2015 | 7/8/2015 | 7/9/2015 | A | PEND |
Bob Archibald
|
|
|
Dave Hannah and I met with Legacy, roofing contractors, structural engineer and current contractor in regard to requirements for structural engineering on patio deck,10 ft retaining wall and attic space ventilation requirements. Structural engineer will provide design calcs for both deck and retaining wall and roofing contractor to provide attic ridge vent dimensions for calculation of additional soffit or roof venting.
|
PubWorks Subgrade Approval | 6/15/2015 | 6/15/2015 | 6/15/2015 | | DONE |
Jason C. Taylor
|
|
|
* FRONT RETAINING WALLS (ROCKERY) CLSM FOOTING***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
CHANGE STATUS TO (ISS) | | | 4/16/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 4/14/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 3/19/2015 | 3/19/2015 | 4/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
waiting on complete submittal for retaining walls and grading. Tierny Residence
|
Case Summary (BLD) | | | 4/14/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 4/14/2015 | | 4/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
exterior site only
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/14/2015 | | |
|
|
|
All requirements met****DO NOT RE ISSUE*******
|
Telephone call | | | 4/14/2015 | | DONE |
|
|
|
called Jason to let know plan mod was ready and how much is owed, Left message on his phone at office
|
Plan Modification Accepted | | | 4/13/2015 | | DONE |
|
|
|
plan mod received-1 transmittal & 3 sheets of C2.00-took to Adele S
|
Routing PW Grading-Hillside | 4/13/2015 | | 4/13/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the retaining wall footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing PW Grading-Hillside | 4/10/2015 | | 4/10/2015 | | FAIL |
Jason C. Taylor
|
|
|
Need 2 additoal copies of grading and driange plan. S1.1
|
Plan resubmittals received | | | 4/7/2015 | | DONE |
|
|
|
received 3 copies of sheet S1.1- put on Adele's desk
|
Routing PW Grading-Hillside | 3/27/2015 | | 4/2/2015 | | FAIL |
Jason C. Taylor
|
|
|
Plans need revised to include retaining wall drainage details. Jason Taylor ###-####.
|
Plan resubmittals received | | | 3/27/2015 | | DONE |
Candy A. Nichols
|
|
|
resubmittals recieved plan review response transmittal,2 boulder retaining wall calcs, 2 supplimental struc calcs, 3 sets of sheet C1.00, C2.00-2 sets of sheet S1.1 & took to Adele S
|
Plan resubmittals received | | | 3/19/2015 | | DONE |
|
|
|
received 3 copies of sheets C1.00 and C2.00- put on Adele's desk
|
Plan Reviewer's activity | | | 3/19/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
sheets recieved on 3/19/15 were grading and drainiage plans only, will route to PW.
|
Meeting | | | 2/25/2015 | | DONE |
Jason Blais
|
|
|
Meeting with Todd Weltner of Vertical Construction and several folks from the Land Group. Discussed new proposals and requirements to correct the site grading and retaining walls on the site. Legacy Homes, however, is still responsible for correcting outstanding items in or on the house itself.
|
Change Expiration Date Only | | | 12/16/2014 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 12/16/2014 | | DONE |
Jason Blais
|
|
|
Phone call with owner Patrick Tierney. Still working through civil mediation in hopes to find resolution to have outstanding items completed with the project. Patrick will send an email request for an extension on the permit.
|
BLD-Other | 4/25/2014 | 4/25/2014 | 4/25/2014 | P | PEND |
Bob Archibald
|
|
|
Correction Notice emailed to contractor.
|
BLD-Conference | 4/23/2014 | 4/23/2014 | 4/23/2014 | P | DONE |
Bob Archibald
|
|
|
Site visit and review with all trades.
|
BLD-Final | 3/19/2014 | 3/20/2014 | 3/21/2014 | P | FAIL |
Dave Hannah
|
|
|
david Phone #: ###-#### tempered glass front door hill side signoff
|
Plan Modification Accepted | | | 2/10/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 2/10/2014 | | 2/10/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Energy code compliance | 10/17/2013 | 10/17/2013 | 10/18/2013 | P | PASS |
Dave Hannah
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 10/15/2013 | 10/15/2013 | 10/15/2013 | P | PASS |
Dave Hannah
|
|
|
david Phone #: ###-####
|
BLD-Foundation | 10/14/2013 | 10/15/2013 | 10/15/2013 | A | PASS |
Dave Hannah
|
|
|
retaining wall // Josh Phone #: ###-####
|
BLD-Wall Bracing | 10/15/2013 | 10/15/2013 | 10/15/2013 | A | PASS |
Dave Hannah
|
|
|
david Phone #: ###-####
|
BLD-Framing/Rough-in | 10/11/2013 | 10/14/2013 | 10/15/2013 | P | PART |
Dave Hannah
|
|
|
david Phone #: ###-#### shear ok to cover ext but still needs a mec rough in inspection
|
BLD-Footing | 10/11/2013 | 10/14/2013 | 10/14/2013 | A | PASS |
Dave Hannah
|
|
|
after 10 // call before// footing for retaining wall // Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 10/9/2013 | 10/10/2013 | 10/11/2013 | P | NR |
Dave Hannah
|
|
|
david Phone #: ###-#### needs mec rough in and plumbing rough in
|
BLD-Framing/Rough-in | 10/8/2013 | 10/9/2013 | 10/9/2013 | P | CANC |
Dave Hannah
|
|
|
dAVID hiCKS Phone #: ###-#### // cancelled per David, will call back to reschedule
|
BLD-Foundation | 10/7/2013 | 10/8/2013 | 10/8/2013 | A | PART |
Jim Sly
|
|
|
Josh Phone #: ###-#### OK to pour retaining wall located furthest East. Engineer Brian Sielaff OK'd # 5 horiz. in lieu of # 6 as shown on plan. Stamped letter verified. Called Mike J. He gave me a verbal that rebar in footing was OK'd by him.........He was waiting for approval of subgrade from Geotech.
|
PubWorks Subgrade Approval | 10/1/2013 | 10/1/2013 | 10/1/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the retaining wall footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 9/27/2013 | 9/27/2013 | 9/27/2013 | A | NR |
Mike Jordan
|
|
|
josh Phone #: ###-####. East retaining wall per engineering and RFI. No concrete is allowed at this time. No approval on geotech report.
|
BLD-Footing | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | CANC |
Jim Sly
|
|
|
josh Phone #: ###-#### Canc by Contr.
|
PubWorks Subgrade Approval | 7/11/2013 | 7/11/2013 | 7/11/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer for the column pads on the north side of the residence. Building department may be scheduled for footing inspections. Jason Taylor ###-####.
|
BLD-Foundation | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | PASS |
Dave Hannah
|
|
|
found wall//Josh Phone #: ###-####
|
BLD-Other | 6/14/2013 | 6/17/2013 | 6/18/2013 | A | PART |
Dave Hannah
|
|
|
early am please//rebar//Josh Phone #: ###-#### first wall poor ok
|
BLD-Footing | 6/11/2013 | 6/11/2013 | 6/12/2013 | P | PASS |
Dave Hannah
|
|
|
Josh Phone #: ###-####
|
BLD-Footing | 6/10/2013 | 6/11/2013 | 6/11/2013 | A | NR |
Dave Hannah
|
|
|
Josh Phone #: ###-####
|
BLD-Footing | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | PART |
Dave Hannah
|
|
|
Josh Phone #: ###-#### basement ftgs and garage ftgs ok
|
PubWorks Subgrade Approval | 6/5/2013 | 6/5/2013 | 6/5/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer (MTI) for northeast basement corner footings. Building department may be scheduled for inspections. Jason Taylor ###-####
|
PubWorks Subgrade Approval | 6/4/2013 | 6/4/2013 | 6/4/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved engineers approval for basement, garage, and colum pads for south side of residence. Footings in crawl space on north side of residence were not approved. Placement of concrete elements in the approved areas can be scheduled with the building department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 5/14/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 5/6/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 3/11/2013 | 3/11/2013 | 5/6/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1ST REVIEW COMPLETED 3-20-13 /second plan review - re submittal recieved 4/26/13 comments sent 5-1-13 via email to Nate
|
Meeting | | | 5/6/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Met with Dave and he picked up the 2 sets fo revised plans that were dropped off 5/3/13 to get engineers stamp and corrections made to structural portion of the plans.
|
Routing - PLAN CHECK | 5/6/2013 | | 5/6/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 5/6/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/6/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 5/6/2013 | | DONE |
Christina Prado
|
|
|
called Nate to advise permit is ready for pick up and gave fees due
|
Override - Parcel Holds | | | 5/6/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 5/6/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 5/3/2013 | | DONE |
Christina Prado
|
|
|
eceived two copies of structural calcs and two copies of plan sheets 0.1, 0.2, 0.3, C1.0, C2.0, C3.0, C4.0, C5.0, S1.0, 1.1, 1.2, 2.1, 2.2, 3.1, 3.2, 4.1, 4.2, 4.3, 5.1, 5.2; taken to Adele.
|
Routing - PLAN CHECK | 4/29/2013 | | 5/1/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see second plan review comments in documents
|
Routing - MECHANICAL | 4/30/2013 | | 4/30/2013 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 4/29/2013 | | 4/29/2013 | | FAIL |
Troy James
|
|
|
emailed corrections to Integrity Heating
|
Routing PW Grading-Hillside | 4/25/2013 | | 4/26/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLANNING | 4/24/2013 | | 4/25/2013 | | PASS |
David Moser
|
|
|
Approved as redlined; The chimneys shall not exceed 35 feet in height. The chimneys need to be removed or relocated so they comply with the height limit of the A-1 zone
|
Plan resubmittals received | | | 4/24/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of structural calcs and three copies of plan sheets 0.1, 0.2, 0.3, C1.0, C2.0, C3.0, C4.0, C5.0, S1.0, 1.1, 1.2, 2.1, 2.2, 3.1, 3.2, 4.1, 4.2, 4.3, 5.1, 5.2; taken to Adele.
|
Routing - Erosion and Sediment | 3/22/2013 | | 3/26/2013 | | PASS |
Kimberly M. Johnson
|
|
|
recieved revised plans routed to KMJ 3/22/13 ajs
|
Plan resubmittals received | | | 3/22/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of narrative in binder and three copies of plan sheet C5.0; taken to Adele.
|
1st review completed | | | 3/21/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 3/20/2013 | | 3/20/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Emailed comments to Nate and Doug 3/21/13 also include WUI requirments. See documents for plan review letter sent.
|
Routing - FIRE | 3/18/2013 | | 3/20/2013 | | PASS |
Scott Arellano
|
|
|
FIRE SPRINKLERS REQUIRED
Notes on plat, item 7, the home is required to have a modified NFPA 13D fire sprinkler systems. In addition, to the NFPA 13D requirmenets all closets, bathrooms and attached garages are to be sprinklered
|
Routing - Erosion and Sediment | 3/15/2013 | | 3/18/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
LM for applicant; need ESC narrative
|
Routing - PUBLIC WORKS | 3/11/2013 | | 3/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - MECHANICAL | 3/15/2013 | | 3/15/2013 | | FAIL |
Troy James
|
|
|
emailed corrections to brownco
|
Routing - PLANNING | 3/15/2013 | | 3/15/2013 | | FAIL |
David Moser
|
|
|
CFH13-00007 Hillside Application is not complete.
|
Routing - Addressing | 3/11/2013 | | 3/14/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Grading-Hillside | 3/11/2013 | | 3/14/2013 | | FAIL |
Jason C. Taylor
|
|
|
CFH pending. Grading plan is preliminary, need final grading plan to proceed. Jason Taylor ###-####.
|
Plan resubmittals received | | | 3/14/2013 | | |
|
|
|
3-14-13 received 3 copies of sheet C2.0 sent to Adele
|
Route to Impact Fee Review | 3/11/2013 | 3/14/2013 | 3/12/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Intake Approval | | | 3/11/2013 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/11/2013 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 1/9/2013 | 1/9/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 1/9/2013 | | FAIL |
Barbara Stitt
|
|
|
|