BLD-Final | 6/5/2013 | 6/5/2013 | 6/6/2013 | P | PASS |
Dave Hannah
|
|
|
Garage code is 3204 Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
DOC - Permit Finaled | 6/6/2013 | 6/6/2013 | 6/6/2013 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 4/5/2013 | 4/5/2013 | 4/8/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen
|
BLD-Framing/Rough-in | 4/3/2013 | 4/4/2013 | 4/4/2013 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen. Foam all penetrations in draft stops Foam seal top and bottom plates at 6 " oval duct penetrations, 2nd. floor. Strap top plate at plumbing penetration in mud room. Nail off top chord of box 3 truss as per engineering. Justify over notched studs at exterior bearing wall min media room. Correction notice posted. Ok to insulate.
|
BLD-Energy code compliance | 4/3/2013 | 4/4/2013 | 4/3/2013 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen Inspection cancelled from web by: Braxton Hansen
|
BLD-Wall Bracing | 3/21/2013 | 3/22/2013 | 3/22/2013 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Braxton Hansen exterior ok to cover.
|
BLD-Foundation | 3/4/2013 | 3/4/2013 | 3/4/2013 | P | PASS |
Tom Arcoraci
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 3/1/2013 | 3/1/2013 | 3/4/2013 | P | PASS |
Dave Hannah
|
|
|
chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/4/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 1/29/2013 | | |
|
|
|
|
Plan assigned to (CDM) | 1/18/2013 | 1/18/2013 | 1/29/2013 | | PASS |
Carl D Madsen
|
|
|
|
Telephone call | | | 1/29/2013 | | DONE |
Tisha Gallop
|
|
|
called Seth and told him permit is ready and fee.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/29/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/29/2013 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 1/28/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/28/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/23/2013 | | 1/28/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 1/22/2013 | | 1/23/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/18/2013 | 1/24/2013 | 1/22/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 1/22/2013 | | 1/22/2013 | | PASS |
David Moser
|
|
|
|
Routing - PUBLIC WORKS | 1/18/2013 | | 1/22/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 1/18/2013 | 1/18/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 1/18/2013 | | 1/18/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/18/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/18/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 1/18/2013 | | PASS |
Tisha Gallop
|
|
|
|