Second Notice | | 4/11/2014 | 5/13/2014 | | DONE |
|
|
|
|
Print Statement | | | 5/13/2014 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 3/2/2014 | 4/1/2014 | | DONE |
|
|
|
Mailed 4-1-14
|
BLD-Final | 2/20/2014 | 2/20/2014 | 2/20/2014 | P | PASS |
Jim Sly
|
|
|
DAve Miller Phone #: ###-#### OK for perm occ.
|
Permanent Occupancy | | | 2/20/2014 | | DONE |
|
|
|
|
BLD-Final | 8/2/2013 | 8/5/2013 | 8/5/2013 | A | NR |
Jim Sly
|
|
|
Need final on separate foundation permit # BLD11-2178 and final letter of approval from Engineer of record, prior to calling for final structural inspection. Need to verify that all other finals have been done.
|
BLD-Final | 8/1/2013 | 8/2/2013 | 8/2/2013 | A | DEFR |
Mike Jordan
|
|
|
david Phone #: ###-####
|
BLD-Final | 6/24/2013 | 6/25/2013 | 6/25/2013 | P | CANC |
Jim Sly
|
|
|
dave Phone #: ###-####
|
BLD-Final | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | NR |
Jim Sly
|
|
|
Dave Miller Phone #: ###-#### Need approved plans and engineering
|
FIRE-Final Inspection | 6/21/2013 | 6/21/2013 | 6/21/2013 | P | PASS |
Forrest France
|
|
|
Life safety inspection completed.
|
Permit Ready to Issue | | | 4/10/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/10/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/10/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2013 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 2/4/2013 | | 4/8/2013 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 4/3/2013 | | 4/8/2013 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/3/2013 | | 4/5/2013 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 4/3/2013 | | DONE |
John Menard
|
|
|
Project structural response received through ProjectDox. JCM
|
Routing - PLAN CHECK | 3/11/2013 | | 3/18/2013 | | PASS |
John Menard
|
|
|
|
Plan resubmittals requested | | | 3/18/2013 | | DONE |
John Menard
|
|
|
Structural revisions requested through ProjectDox. JCM
|
Routing Off Site - STRUCTURAL | 3/11/2013 | | 3/14/2013 | | FAIL |
John Menard
|
|
|
|
1st review completed | | | 2/15/2013 | | FAIL |
John Menard
|
|
|
Failed structural review. JCM
|
Routing - PLAN CHECK | 2/4/2013 | | 2/15/2013 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 2/4/2013 | | 2/13/2013 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 2/6/2013 | | 2/6/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - PLANNING | 2/4/2013 | | 2/5/2013 | | PASS |
David Moser
|
|
|
OK as per CUP11-00028
|
Routing - PUBLIC WORKS | 2/4/2013 | | 2/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Payment Received | | | 2/4/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Pending Assignment by JCM | 2/4/2013 | | 2/4/2013 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 2/4/2013 | | PASS |
|
|
|
The 2nd plan intake was approved. CJW
|
Intake Approval | | | 1/25/2013 | | FAIL |
|
|
|
Please refer to the circled items on the plan intake checklist. Provide resolution to those items. CJW
|
Application received | | | 1/18/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 18 2013 12:13PM
|