DOC - Permit Finaled | | | 12/31/2015 | | DONE |
|
|
|
final passed 1-4-14
|
PubWorks Occupancy Approval | 6/2/2014 | 6/2/2014 | 6/2/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 1/3/2014 | 1/3/2014 | 1/4/2014 | P | PASS |
Tony Young
|
|
|
Todd Phone #: ###-####
|
BLD-Final | 12/31/2013 | 1/3/2014 | 1/3/2014 | A | PEND |
Tony Young
|
|
|
Todd Phone #: ###-####
|
BLD-Final | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | PART |
Tony Young
|
|
|
Todd; Phone #: ###-####,, items noted were made to meet code at this point of inspection.. bond in place for hillside.. doors are off to be painted,,, other trades are ok for occupancy,,, pool is on seperate permit
|
BLD-Conference | 12/30/2013 | 12/31/2013 | 12/31/2013 | A | PART |
Tony Young
|
|
|
Todd Phone #: ###-####,, walk through for the final,, fire seperation,, stair riser issues,, open risers,, address #s etc.
|
BLD-Energy code compliance | 10/8/2013 | 10/9/2013 | 10/9/2013 | A | PASS |
Tony Young
|
|
|
todd Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2013 | 10/2/2013 | 10/2/2013 | P | PASS |
Tony Young
|
|
|
Early afternoon - Todd Phone #: ###-####
|
BLD-Other | 9/17/2013 | 9/18/2013 | 9/18/2013 | A | PART |
Tony Young
|
|
|
todd Phone #: ###-####,, soffits work in progress,, ok
|
BLD-Conference | 9/16/2013 | 9/17/2013 | 9/17/2013 | A | PASS |
Tony Young
|
|
|
todd Phone #: ###-####,, frame walk through
|
BLD-Wall Bracing | 8/1/2013 | 8/1/2013 | 8/2/2013 | P | PASS |
Tony Young
|
|
|
Todd Phone #: ###-####,, ext. ok to cover
|
BLD-Other | 6/12/2013 | 6/13/2013 | 6/13/2013 | A | PASS |
Tom Arcoraci
|
|
|
bill will pour at 11 am Phone #: ###-####
|
BLD-Footing | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | PASS |
Tom Arcoraci
|
|
|
todd Phone #: ###-####
|
PubWorks Subgrade Approval | 6/6/2013 | 6/6/2013 | 6/6/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval for entire residence from geotechnical engieer (MTI). footing inspections can be scheduled with the building department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 4/30/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 4/25/2013 | | |
|
|
|
|
Plan assigned to (CDM) | 3/22/2013 | 3/22/2013 | 4/25/2013 | | PASS |
Carl D Madsen
|
|
|
Carl Madsen
|
Routing - PLAN CHECK | 4/25/2013 | | 4/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/25/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 4/25/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 4/19/2013 | | 4/19/2013 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - MECHANICAL | 4/19/2013 | | 4/19/2013 | | PASS |
Troy James
|
|
|
eplan
|
Routing - Erosion and Sediment | 4/9/2013 | | 4/10/2013 | | PASS |
Kimberly M. Johnson
|
|
|
approved per redline
|
1st review completed | | | 3/28/2013 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | | | 3/28/2013 | | FAIL |
Carl D Madsen
|
|
|
Carl Madsen
|
Routing - Addressing | | | 3/26/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Erosion and Sediment | 3/26/2013 | | 3/26/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
1. Update project description scope. Is this only for site development or is it meant to also cover verticle construction? Project schedule indicates a demo will have or has already occurred. This is not covered in the scope nor have any demo permits been issued for this address. 2. Amend project schedule to accurately reflect start date. 3. Update reporting requirements for spills. 4. Update potential pollutant list. 5. What temporary stabilization methods be used if portions become inactive? 6. Provide BMP installation details for washout, fiber rolls, storm drain inlet, check dam ect.
|
Routing - FIRE | 3/26/2013 | | 3/26/2013 | | PASS |
Scott Arellano
|
|
|
Approved with no comments.
|
Routing PW Grading-Hillside | 3/22/2013 | | 3/26/2013 | | PASS |
Jason C. Taylor
|
|
|
Grading Plans Approved. Subgrade approval is required before footing inspection can be scheduled. Jason Taylor ###-####
|
Route to Impact Fee Review | 3/22/2013 | 3/27/2013 | 3/25/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | | | 3/25/2013 | | PASS |
|
|
|
|
Payment Received | | | 3/22/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Routing - PUBLIC WORKS | | | 3/22/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 2/7/2013 | | FAIL |
Christina Prado
|
|
|
Needs CFH & building height called out
|
Application received | | | 1/30/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 30 2013 12:53PM
|