Case Summary (BLD) | | | 10/10/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/10/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/10/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/10/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/10/2016 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 4/29/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/17/2016 | | DONE |
|
|
|
|
BLD-Final | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | PASS |
Dave Hannah
|
|
|
scott please call before going out as he wants to be there Phone #: ###-####
|
DOC - Permit Finaled | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | PASS |
Dave Hannah
|
|
|
|
Plan assigned to (CDM) | 7/25/2013 | 7/25/2013 | 10/7/2013 | | PASS |
Carl D Madsen
|
|
|
res. plan mod; routed to hillside, planning, fire
|
Routing - PLAN CHECK | 10/7/2013 | | 10/7/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/7/2013 | | DONE |
Tisha Gallop
|
|
|
Per CDM permit should be ISS
|
PubWorks Occupancy Approval | 10/4/2013 | 10/4/2013 | 10/4/2013 | | DONE |
Jason C. Taylor
|
|
|
Project complete. Jason Taylor ###-####
|
Routing PW Grading-Hillside | 10/3/2013 | | 10/3/2013 | | PASS |
Jason C. Taylor
|
|
|
Plan modification approved. Grading plan recieved and is acceptable. Jason Taylor ###-####
|
Routing - FIRE | | | 8/6/2013 | | PASS |
Scott Arellano
|
|
|
|
Routing - PLAN CHECK | 7/12/2013 | | 8/6/2013 | | FAIL |
Carl D Madsen
|
|
|
Fail pending grading and drainage approval. CDM
|
BLD-Framing/Rough-in | 7/29/2013 | 7/29/2013 | 7/30/2013 | P | PASS |
Dave Hannah
|
|
|
Shear-Scott Phone #: ###-#### int sheetrock shear walls
|
Plan assigned to (AJS) | 7/12/2013 | 7/12/2013 | 7/25/2013 | | DEFR |
Carl D Madsen
|
|
|
res. plan mod; routed to hillside, planning, fire
|
Routing - PLANNING | | | 7/16/2013 | | PASS |
David Moser
|
|
|
|
BLD-Energy code compliance | 7/12/2013 | 7/15/2013 | 7/15/2013 | A | PASS |
Tom Arcoraci
|
|
|
Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 7/15/2013 | 7/15/2013 | 7/15/2013 | P | PASS |
Tom Arcoraci
|
|
|
Scott Phone #: ###-####
|
Routing PW Grading-Hillside | 7/12/2013 | | 7/15/2013 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan needs revised to add swales in sideyard for additional concrete. Jason Talyor ###-####.
|
Inspection Record Card- Bld | | | 7/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 7/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan Modification Accepted | | | 7/12/2013 | | DONE |
Tisha Gallop
|
|
|
added concrete pad for fire dept access; received three copies of plan sheets C1.0 & C1.1, C2.0; routed to public works-hillside, planning, fire, plan review.
|
BLD-Framing/Rough-in | 7/8/2013 | 7/9/2013 | 7/11/2013 | P | PART |
Dave Hannah
|
|
|
Scott Phone #: ###-#### ok to insulate c/n on site needs fire departments ok for no fire sprinklers
|
Meeting | | | 7/11/2013 | | DONE |
Scott Arellano
|
|
|
The revised Fire Access plan on sheet C1.1 appears to be sufficient to meet the Fire Code requirements. This driveway modification will be sufficient to remove the previous fire sprinkler requirement. I have updated the permit case language to reflect this change. Please Note that these revised plan sheets will need to be approved by the residential plan reviewer and re-issued for the final approved set.
|
Plan resubmittals received | | | 6/28/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 6/28/2013 | | 6/28/2013 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Wall Bracing | 6/24/2013 | 6/25/2013 | 6/25/2013 | A | PASS |
Dave Hannah
|
|
|
scott Phone #: ###-####
|
BLD-Wall Bracing | 6/19/2013 | 6/19/2013 | 6/20/2013 | P | FAIL |
Dave Hannah
|
|
|
Scott-Shear nail Phone #: ###-####
|
BLD-Wall Bracing | 6/18/2013 | 6/19/2013 | 6/19/2013 | A | FAIL |
Dave Hannah
|
|
|
Scott-Shear nail Phone #: ###-####
|
Telephone call | | | 6/13/2013 | | DONE |
|
|
|
Telephnoe Call with Don Flynn of Shadow Mountain Homes.
Per our discussion, the proposed single family dwelling located at 289 North Alto Via Court does not currently meet the requirements of the Fire Code in regards to Fire Department vehicle access. As measured from the public roadway (North Alto Via Court) the distance around the structure to the furthest exterior portion of the home is 200 lineal feet. To be in compliance with the Fire Code, the furthest exterior portion of the structure must be within 150 feet of an approved fire department roadway, unless an approved alternative is accepted by the Fire Code official.
Acceptable alternatives are:
1) Installation of fire sprinklers in accordance with NFPA 13D; or
2) Provide additional fire department vehicle access roadways capable of supporting the weight of fire department apparatus weighing 75,000 lbs per axle, with a grade not exceeding 10%, and roadway width acceptable to the Fire Code Official.
Please submit your alternate approval request in writing and/or proposed plan to the Boise City Fire Marshal, Deputy Chief Romeo Gervais at rgervais@cityofboise.org; or deliver to Boise Fire Department at 333 N. Mark Stall Place, Boise, ID.
|
BLD-Foundation | 4/26/2013 | 4/26/2013 | 4/26/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 4/24/2013 | 4/25/2013 | 4/26/2013 | P | NR |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 4/19/2013 | 4/23/2013 | 4/24/2013 | P | CANC |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 4/19/2013 | 4/22/2013 | 4/24/2013 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
PubWorks Subgrade Approval | 4/24/2013 | 4/24/2013 | 4/24/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer. Footing inspection can be scheduled with building department. Jason Taylor ###-####
|
BLD-Foundation | 4/18/2013 | 4/22/2013 | 4/19/2013 | P | CANC |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Inspection cancelled via mobile web on Friday, April 19, 2013.
|
BLD-Footing | 4/18/2013 | 4/19/2013 | 4/19/2013 | P | NR |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 3/22/2013 | 3/27/2013 | 3/27/2013 | P | PART |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron basement walls ok
|
BLD-Footing | 3/22/2013 | 3/25/2013 | 3/25/2013 | P | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
PubWorks Subgrade Approval | 3/20/2013 | 3/20/2013 | 3/20/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval (basement only) from geotechnical engineer. Footing inspection can be scheduled with building department. Jason Taylor ###-####
|
Issue PAID IN FULL permit | | | 3/13/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 3/12/2013 | | |
|
|
|
|
Plan assigned to (CDM) | 2/6/2013 | 2/6/2013 | 3/12/2013 | | PASS |
Carl D Madsen
|
|
|
|
Telephone call | | | 3/12/2013 | | DONE |
Tisha Gallop
|
|
|
called Shadow Mtn Const and left vm permit is ready and fee.
|
Routing - FIRE | | | 3/12/2013 | | PASS |
|
|
|
With conditions
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/12/2013 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 3/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 3/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 3/8/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/7/2013 | | 3/7/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 3/5/2013 | | 3/5/2013 | | PASS |
David Moser
|
|
|
|
Routing PW Grading-Hillside | 3/4/2013 | | 3/4/2013 | | PASS |
Jason C. Taylor
|
|
|
Grading and Drainage plans approved. Jason Taylor ###-####
|
Plan resubmittals received | | | 3/1/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets A2-1 (elevations), A2-2 (elevations), A3-3 (lower floor plan), A4-1 (building sections), A4-2 (building sections); taken to Carl Madsen.
|
1st review completed | | | 2/27/2013 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | | | 2/27/2013 | | FAIL |
Carl D Madsen
|
|
|
Failed pending the resubmittal adressing WUI, basement emergency escape, new elevations sheets and truss engineering. Sent E-Mail to Don with Shadow Mountain 2-27-13 CDM
|
Routing - FIRE | 2/15/2013 | | 2/19/2013 | | FAIL |
Tim Frost
|
|
|
The home does not comply with 503.1.1. If the home was to have fire sprinklers it would be acceptable under exception1.
|
Routing - Erosion and Sediment | 2/13/2013 | | 2/15/2013 | | PASS |
Kimberly M. Johnson
|
|
|
approved with redlines
|
Routing - MECHANICAL | 2/12/2013 | | 2/13/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | | | 2/12/2013 | | FAIL |
Colleen T Carroll
|
|
|
Failed, as per PW grading Comments the building needs a CAT 1 staff level hillside application. Called applicant about the application.
|
Routing - PUBLIC WORKS | 2/12/2013 | | 2/12/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | 2/12/2013 | | 2/12/2013 | | FAIL |
Jason C. Taylor
|
|
|
Revised grading plans were not accepted (walls over 4 ft) . Civil Engineer will re-submit new grading plans and builder will file for a category 1 permit.
|
Plan resubmittals received | | | 2/12/2013 | | |
|
|
|
Received cover letter dated 2-12-13 to Jason Taylor from Carl Geiger, 3 copies of sheets C1.0, C2.0 attached to plans in mechanical office
|
Route to Impact Fee Review | 2/6/2013 | 2/11/2013 | 2/8/2013 | | PASS |
James McMahon
|
|
|
|
Routing PW Grading-Hillside | 2/8/2013 | | 2/8/2013 | | FAIL |
Jason C. Taylor
|
|
|
This project needs a zoning application (Category 1 Hillside Project). Grading Plans were not signed by the design engineer and missing 3rd set for PW. Jason Taylor ###-####
|
Plan resubmittals received | | | 2/8/2013 | | DONE |
Tisha Gallop
|
|
|
Received response letter to Jason Taylor, one copy of Retaning Wall Calcs, three copies of plan sheets C1.0 and C2.0; received response letter to Kim Johnson, two copies of Narrative and plan sheet ESC1.0; put with plans at Public Works.
|
Routing - Addressing | 2/6/2013 | | 2/6/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 2/6/2013 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/6/2013 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | | 2/5/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 5 2013 10:36AM
|
Intake Approval | | | 2/5/2013 | | FAIL |
Darla L Downs
|
|
|
The applicant did not have the check off list filled out,as we were starting I noticed he didn't have the structural calcs, at that time the applicant said he would just take the plans, get the check off list filled out and bring it back for submittal another time. I did have Jason Taylor look at the plans and he said it would just be a normal hill side submittal. PLEASE note I did not get very far with the plan intake.
|