The Terraces of Boise - Main Building Wings A and B - To construct a new 50,285 square foot, four story, wood framed independent living apartment building. This is a wing of a larger building, with wings separated by two-hour fire walls. This building is being constructed on top of an underground parking garage. The parking garage is separated from the above apartment building by a three-hour horizontal separation. This building is fully fire sprinklered. The sprinklers are used for story increase. First Floor: 14,885 sq. ft. with 11 apartments. Second Floor: 14,785 sq. ft. with 11 apartments. Third Floor: 11,865 sq. ft. with 9 apartments. Fourth Floor: 8,750 sq. ft. with 7 apartments. All floors contain mechanical/electrical and housekeeping areas. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  8/24/2015 DONE
DetailsChristina Prado
Zoning Approval8/19/20158/19/20158/19/2015 PASS
DetailsJosh Wilson
Landscaping complete- ok for final.
BLD-Final7/8/20157/9/20157/9/2015PPASS
DetailsJim Storey
Kc Phone #: ###-####
Temporary Occupancy6/23/20159/21/20156/23/2015 DONE
DetailsChristina Prado
Zoning Approval Temp6/23/20156/23/20156/23/2015 DONE
DetailsJosh Wilson
BLD-Final6/12/20156/17/20156/17/2015APART
DetailsJim Storey
JC Phone #: ###-####
FIRE-Final Inspection6/12/20156/15/20156/15/2015APASS
DetailsThomas Walsh
Final FLS inspection of Wings A & B for TCO and final sign off.
NOTE: Both fire sprinklers and fire alarm systems have been singed off for this area.
Emergency lights and exit signs inspected - 90 minute test off of generator. All tested OK.
Fire extinguishers - OK
Fire lane sign installed.
Knox box installed and FD called to lock box with keys installed.
No other discrepancies pending - TCO approved by this office.

BLD-Final6/12/20156/15/20156/15/2015ACANC
DetailsJim Storey
Jesus Phone #: ###-####
BLD-Final6/12/20156/15/20156/15/2015ACANC
DetailsBob Archibald
JC// wing A & B Phone #: ###-####
BLD-Final6/11/20156/12/20156/12/2015PNR
DetailsTony Young
JC// wing A & B Phone #: ###-####,, conference only,, need trades 1st,, walk through only
BLD-Final6/9/20156/10/20156/10/2015PNR
DetailsJim Storey
John Phone #: ###-####
BLD-Final6/4/20156/4/20156/5/2015PPART
DetailsJim Storey
A, B, C Wings, mechanical support stairwell doors - JC Phone #: ###-#### smoke seals installed
BLD-Final6/2/20156/3/20156/3/2015APART
DetailsJim Storey
JC Phone #: ###-#### room doors all ok
BLD-Other5/19/20155/20/20155/20/2015APART
DetailsJim Storey
Fire collar // Phone #: ###-#### missing one 3 inch in ele rm west/ fire treat at overheaddoors
FIRE-Conference5/18/20155/19/20155/19/2015ADONE
DetailsThomas Walsh
Meeting to discuss upcoming fire alarm testing and subsequent occupancy (TCO) of wings A thru D.
BLD-Ceiling Grid Inspection4/22/20154/23/20154/23/2015APASS
DetailsJim Storey
1st and 2nd floor wind a b and c // JC Phone #: ###-####
BLD-Ceiling Grid Inspection3/24/20153/25/20153/25/2015APASS
DetailsJim Storey
3rd and 4th A,B, C possibly D // JC Phone #: ###-####
BLD-Ceiling Grid Inspection3/3/20153/3/20153/3/2015PPASS
DetailsJim Storey
JC Phone #: ###-#### 2nd floor corridor ceilling hard lid ok
BLD-Ceiling Grid Inspection2/26/20152/27/20152/27/2015APART
DetailsJim Storey
JC-2nd floor corridor ceiling for cover Phone #: ###-####west end ok to cover hard lids// east end remove ceilling duct in corridor wall needs isolated out/ fire tape / firespk out of lid/ firestop all ceilling penatrations.
BLD-Ceiling Grid Inspection1/20/20151/20/20151/20/2015PPART
DetailsJim Storey
JC-fire caulking for cover 4th floor wing B Phone #: ###-#### elavator rm storage rm no cover all rest ok to cover.
BLD-Ceiling Grid Inspection1/14/20151/15/20151/15/2015APASS
DetailsJim Storey
JC-shaft liner ceiling 4th floor stairwell B1 Phone #: ###-####
BLD-Other12/29/201412/29/201412/29/2014PPASS
DetailsJim Storey
JC-fire caulking soffits-1st floor wings B & A Phone #: ###-####
BLD-Other12/23/201412/24/201412/24/2014ANR
DetailsJim Storey
fire colcking first floor wing a // Jc Phone #: ###-####
BLD-Framing/Rough-in12/12/201412/15/201412/15/2014APASS
DetailsJim Storey
Gary Phone #: ###-#### 2nd floor a bld drops ok to cover
BLD-Energy code compliance12/9/201412/9/201412/9/2014PPASS
DetailsJim Storey
insulation third floor wing C and D// JC Phone #: ###-####coridor
BLD-Ceiling Grid Inspection12/9/201412/9/201412/9/2014PPASS
DetailsJim Storey
second floor wing D// JC Phone #: ###-####
BLD-Other11/28/201412/1/201412/1/2014AFAIL
DetailsJim Storey
closer to noon. fire colt. blockin// JC Phone #: ###-####
BLD-Ceiling Grid Inspection11/28/201411/28/201411/28/2014ANR
DetailsJim Storey
brett - ###-#### - first floor wing b
BLD-Ceiling Grid Inspection11/18/201411/19/201411/19/2014APART
DetailsJim Storey
jc Phone #: ###-####
BLD-Energy code compliance11/12/201411/13/201411/13/2014APASS
DetailsJim Storey
JC Phone #: ###-#### ok to insulate ceilling foamseal ok
BLD-Ceiling Grid Inspection11/7/201411/10/201411/10/2014PPASS
DetailsJim Storey
JC// 4th floor soffits Phone #: ###-####
BLD-Ceiling Grid Inspection11/5/201411/6/201411/6/2014APASS
DetailsJim Storey
JC-2 nd floor Phone #: ###-#### insulation and rc ok to cover 2nd floor/ sheer 1 st floor ok to cover a and b wing
BLD-Ceiling Grid Inspection11/4/201411/4/201411/4/2014PNR
DetailsJim Storey
JC Phone #: ###-####
BLD-Wall Bracing11/4/201411/4/201411/4/2014PPASS
DetailsJim Storey
JC Phone #: ###-####2nd floor interior ok
BLD-Wall cover10/30/201410/31/201410/31/2014APASS
DetailsJim Storey
JC Phone #: ###-####sheer nail pick up interior. 2nd and 3hird floor sheer ok
BLD-Energy code compliance10/30/201410/31/201410/31/2014ACANC
DetailsJim Storey
2nd floorJC Phone #: ###-####walls ok
BLD-Energy code compliance10/29/201410/30/201410/30/2014APART
DetailsJim Storey
JC Phone #: ###-####
BLD-Wall cover10/29/201410/30/201410/30/2014APART
DetailsJim Storey
JC Phone #: ###-####
BLD-Wall Bracing10/23/201410/24/201410/24/2014APASS
DetailsJim Storey
JC Phone #: ###-#### sheer wall osb ok 2nd floor
BLD-Energy code compliance10/16/201410/17/201410/17/2014APART
DetailsJim Storey
2nd fl B wing - Gary Phone #: ###-#### air seal for iecc exterior wall and floor ok.
BLD-Energy code compliance10/14/201410/15/201410/15/2014APASS
DetailsJim Storey
JC Phone #: ###-#### 3rd and fouth ok to cover/ ec insulation ok
BLD-Framing/Rough-in10/10/201410/13/201410/13/2014APART
DetailsJim Storey
Gary Phone #: ###-#### fourth floor tennent wall gyp need nailling tighter/ missing gyp at trusses.
BLD-Framing/Rough-in10/1/201410/2/201410/2/2014APASS
DetailsDave Hannah
Gary-3 fl corrider Phone #: ###-#### ok to cover upper 3rd
BLD-Framing/Rough-in9/22/20149/23/20149/23/2014APART
DetailsDave Hannah
4th floor B Wing corrider framing for cover // JC Phone #: ###-#### ok to sheetrock lids
BLD-Framing/Rough-in9/3/20149/4/20149/4/2014APART
DetailsJim Storey
J.C. Phone #: ###-#### exterior ok to cover/ truss repair/ pony wall for interior bearing/ starp mlb header to top plate/ strap post to beam roof popout.
BLD-Wall Bracing8/21/20148/21/20148/21/2014PPASS
DetailsJim Storey
Jason Phone #: ###-#### exterior ok/ interior ok/ ok to gyp coridor ceilling.
BLD-Other7/21/20147/21/20147/21/2014PPART
DetailsJim Storey
JC-fire blanket Phone #: ###-#### 1st floor ok
BLD-Wall Bracing7/21/20147/21/20147/21/2014PPASS
DetailsJim Storey
JC Phone #: ###-#### exterior ok for cover
Print Occupancy Form  2/21/2014 DONE
DetailsChristina Prado
Permit Ready to Issue  2/21/2014 DONE
Issue PAID IN FULL permit  2/21/2014 DONE
DetailsTisha Gallop
Routing - PLAN CHECK11/1/2013 2/20/2014 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  2/20/2014 DONE
DetailsJohn Menard
Plan assigned to (JCM)2/6/2013 2/20/2014 PASS
DetailsJohn Menard
1st Review Complete 5/10/2013
Routing - MECHANICAL  2/19/2014 PASS
DetailsTroy James
Routing PW Drainage2/15/2013 2/12/2014 PASS
DetailsBrian Murphy
Plan resubmittals received  1/23/2014 DONE
DetailsTisha Gallop
received two copies of resonse and plan sheets AA210, AA211, AA220, AA212, AA213, AA401, AA604, AA702, AA503, AA601, AS201, AS601, AS221, AS300, AS700, AC604, AC211, AC213, AC603, AT100, AT101, AI210, AI516, AI611, AI211, AI212, AI213, AI214, AI217, AI221, AI227, PS201, ES211, ET100, EA301, EA302, EA303, ET100, EI200, EI210, EI300, MI211, MI212, MI213, MI222, MI224, MI225, MI228, MI223, MI226, MI229, MI231, MC211, C400, G003, G201, G211, G220; inserted by Ron Hill.
Plan resubmittals requested  12/13/2013 DONE
DetailsJohn Menard
E-mailed the architect a copy of the second plan review requesting revisions. JCM
Routing - Erosion and Sediment10/29/2013 11/1/2013 PASS
DetailsEvan Jenkins
Routing - PLUMBING2/15/2013 10/31/2013 PASS
DetailsDaryl Spivey
Routing PW Drainage10/29/2013 10/30/2013 PASS
DetailsBrian Murphy
Routing PW Solid Waste10/29/2013 10/29/2013 PASS
DetailsPeter J. McCullough
Routing PW Environmental10/29/2013 10/29/2013 PASS
DetailsWalt Baumgartner
Routing PW Sewer Design10/29/2013 10/29/2013 PASS
DetailsKyle S. Rosenmeyer
Routing - PUBLIC WORKS10/29/2013 10/29/2013 PASS
DetailsConnie Baumgartner
Routing PW Sewer Rating10/29/2013 10/29/2013 PASS
DetailsConnie Baumgartner
Routing PW Street Lights10/29/2013 10/29/2013 PASS
DetailsMike D Hedge
Plan resubmittals received  10/25/2013  
Complete plan set of resubmittals received
Routing Off Site - STRUCTURAL8/21/2013 9/30/2013 PASS
DetailsRon Hill
Plan resubmittals received  9/18/2013  
Rec'd response letter, calcs and sheets SI200; 201; 202; 203; 210; 211; 212; 213; 214; 215; 220; 221; 222; 223; 224; 230; 231; 232; 233; 234; 235; 600; 610; 620; 630; 700; SC211; 212; ST001; 002; 101; 102; 103; 201; 202; 203; 301; 302; 303; 401; 402; 403; 501; 301; SS210; 211 - taken to JCM
Plan resubmittals received  8/20/2013  
8-20-13 received 3 structural design calcs, 3 copies if sheets s1210,s1211,s1212,s1213,s1214,s1215,s1220,s1221,s1222,s1223,s1224,s1230,s1231,s1232,s1233,s1234,s1235,sc211,sc212,s1600,s1610,s1620,s1630,s1700,st001,st002. sent to CHM2HILL outside engineering per Ron Hill///dld
Plan resubmittals requested  5/17/2013 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK5/7/2013 5/10/2013 FAIL
DetailsJohn Menard
1st review completed  5/7/2013 FAIL
Failed PW & ESC.
Routing - FIRE5/1/2013 5/7/2013 PASS
DetailsScott Arellano
Attached review comments to plans.
Routing Off Site - STRUCTURAL4/3/2013 4/18/2013 FAIL
DetailsRon Hill
Route to Impact Fee Review2/6/20132/11/20134/9/2013 PASS
DetailsCindy M. Gould
Impact fees applied to BLD13-00179
Routing - PLAN CHECK2/28/2013 4/3/2013  
DetailsJohn Menard
John Menard
Plan resubmittals received  4/3/2013 DONE
DetailsTisha Gallop
received three copies of Structural Calcs and plan sheets ST001, ST002, SI210, SI211, SI212, SI213, SI214, SI215, SI220, SI221, SI222, SI223, SI224, SI230, SI231, SI232, SI233, SI234, SI235, SI600, SI620, SI700, ST101, ST102, ST103, ST201, ST202, ST301, ST302, ST401, ST402, ST501, ST601; Ron Hill took two copies and one copy routed to off site structural.
Telephone call  4/3/2013 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Routing - PLANNING2/27/2013 2/28/2013 PASS
DetailsJosh Wilson
DRH12-00250 Josh Wilson
Routing - Erosion and Sediment2/13/2013 2/15/2013 FAIL
DetailsKimberly M. Johnson
Need more information on non-stormwater discharges. Where will these discharges be directed to. Need phasing plan for clearing and grubbing and permanent stabilization. Ref ESC13-0069 for Plan
Routing PW Solid Waste2/13/2013 2/14/2013 FAIL
DetailsJohn Menard
Routing PW Street Lights2/14/2013 2/14/2013 FAIL
DetailsMike D Hedge
Routing PW Environmental2/14/2013 2/14/2013 FAIL
DetailsWalt Baumgartner
Routing PW Sewer Rating2/13/2013 2/13/2013 PASS
DetailsConnie Baumgartner
Routing PW Sewer Design2/13/2013 2/13/2013 PASS
DetailsKyle S. Rosenmeyer
Existing main in Lysted 15", not 18". Sewer tap permit required and CCTV inspection of new manhole installation. Existing stub provided off lysted needs to be plugged at manhole, and the base re-channeled.
Routing - PUBLIC WORKS2/8/2013 2/13/2013 FAIL
DetailsConnie Baumgartner
Routing - PLANNING Land Div2/7/2013 2/8/2013 PASS
DetailsTodd Tucker
Routing - Addressing2/8/2013 2/8/2013 PASS
DetailsJason C. Taylor
Application received 2/6/20132/7/2013 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  2/6/2013 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  2/6/2013 DONE
DetailsTisha Gallop
First Notice 9/3/2015   
FIRE-Conference3/19/20143/19/2014 P 
DetailsForrest France