Permanent Occupancy | | | 1/14/2016 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/13/2016 | 1/13/2016 | 1/13/2016 | P | PASS |
Jim Storey
|
|
|
JC-final for perm c of o Phone #: ###-####
|
Temporary Occupancy | 12/7/2015 | 3/6/2016 | 12/7/2015 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval | 11/18/2015 | 11/18/2015 | 11/18/2015 | | PASS |
Josh Wilson
|
|
|
|
BLD-Conference | 11/16/2015 | 11/16/2015 | 11/16/2015 | P | PART |
Jim Storey
|
|
|
Gary Phone #: ###-#### temp ok
|
FIRE-Final Inspection | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PASS |
Jim Page
|
|
|
Attached FIR permit to this BLD permit for sprinklers finaled, attached FIR permit to this BLD permit for alarms finaled. Life fire safety passed.complete
|
BLD-Final | 11/5/2015 | 11/5/2015 | 11/5/2015 | P | PART |
Jim Storey
|
|
|
Gary-wings F & G Phone #: ###-#### c/n with gary //doors latch ok all floors
|
FIRE-Final Inspection | 10/27/2015 | 10/27/2015 | 10/27/2015 | P | CANC |
Thomas Walsh
|
|
|
Gary// Wings S and G Phone #: ###-####
|
BLD-Framing/Rough-in | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | PASS |
Jim Storey
|
|
|
fire rated soffits; Gary Phone #: ###-#### ceillings ok to cover all floors
|
BLD-Framing/Rough-in | 9/21/2015 | 9/22/2015 | 9/22/2015 | A | PASS |
Jim Storey
|
|
|
Gary-soffits-1st floor F corridors Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/10/2015 | 9/11/2015 | 9/11/2015 | A | PASS |
Jim Storey
|
|
|
Gary// 2nd floor F Phone #: ###-####4th 3rd and 2nd ok
|
BLD-Other | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PASS |
Jim Storey
|
|
|
T-grid soffits E 1st fl hallway - Jerry Phone #: ###-####2nd and third ok
|
BLD-Framing/Rough-in | 8/13/2015 | 8/14/2015 | 8/14/2015 | A | PASS |
Jim Storey
|
|
|
Gary-hallway G on 1 st floor- basement elevator- lobby Phone #: ###-####
|
BLD-Framing/Rough-in | 8/11/2015 | 8/12/2015 | 8/12/2015 | A | PASS |
Jim Storey
|
|
|
2nd floor; Gary Phone #: ###-#### hard lids ok
|
BLD-Framing/Rough-in | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | PASS |
Jim Storey
|
|
|
G-3rd floor (Hall); Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 7/31/2015 | 8/3/2015 | 8/3/2015 | A | PASS |
Jim Storey
|
|
|
F first fl hallway - Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 7/29/2015 | 7/29/2015 | 7/29/2015 | P | PASS |
Jim Storey
|
|
|
2nd fl F hallway, cover - Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 7/24/2015 | 7/27/2015 | 7/27/2015 | A | PASS |
Jim Storey
|
|
|
Mark-east 1st floor corridor Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | FAIL |
Jim Storey
|
|
|
Garry Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | NR |
Jim Storey
|
|
|
Garry Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/15/2015 | 7/16/2015 | 7/17/2015 | P | PASS |
Jim Storey
|
|
|
JC// F wing, 3rd floor Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/6/2015 | 7/7/2015 | 7/7/2015 | A | PASS |
Jim Storey
|
|
|
Gary// 4th floor, hallway F Phone #: ###-####
|
BLD-Framing/Rough-in | 6/26/2015 | 6/29/2015 | 6/29/2015 | A | PASS |
Jim Storey
|
|
|
G first floor sofet // Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | NR |
Jim Storey
|
|
|
G first floor sofet // Gary Phone #: ###-####
|
BLD-Energy code compliance | 6/8/2015 | 6/9/2015 | 6/9/2015 | P | PASS |
Jim Storey
|
|
|
Gary Phone #: ###-####
|
BLD-Wall cover | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | PASS |
Jim Storey
|
|
|
Bldg F, first floor//fire caulking, ok to cover - Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 6/3/2015 | 6/4/2015 | 6/4/2015 | A | DEFR |
Jim Storey
|
|
|
Bldg F, first floor//fire caulking, ok to cover - Gary Phone #: ###-####
|
BLD-Other | 5/27/2015 | 5/27/2015 | 5/27/2015 | P | PASS |
Jim Storey
|
|
|
Soffit; Gary Phone #: ###-####
|
BLD-Energy code compliance | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | PASS |
Jim Storey
|
|
|
Gary// F wing 1st and 2nd floor rooms 158 and 258 Phone #: ###-####
|
BLD-Energy code compliance | 5/14/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Jim Storey
|
|
|
F 2nd & 3rd floor - Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 5/7/2015 | 5/8/2015 | 5/8/2015 | P | PASS |
Jim Storey
|
|
|
Gary// 4th floor hallway F Phone #: ###-####
|
BLD-Other | 5/4/2015 | 5/5/2015 | 5/5/2015 | A | PASS |
Jim Storey
|
|
|
Gary// approval to cover soffits- 1st floor F Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | P | PASS |
Jim Storey
|
|
|
1st floor; Gary Phone #: ###-####
|
BLD-Framing/Rough-in | 4/28/2015 | 4/28/2015 | 4/28/2015 | P | PASS |
Jim Storey
|
|
|
Gary-2nd floor G wing Phone #: ###-####
|
BLD-Framing/Rough-in | 4/24/2015 | 4/24/2015 | 4/24/2015 | P | PASS |
Jim Storey
|
|
|
Gary-2nd floor soffits wing F Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/22/2015 | 4/22/2015 | 4/23/2015 | P | PASS |
Jim Storey
|
|
|
1st and 2nd floor wing G.. To cover // gary Phone #: ###-####
|
BLD-Wall cover | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Jim Storey
|
|
|
third floor // Gary Phone #: ###-####
|
BLD-Energy code compliance | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Jim Storey
|
|
|
3 and 4 F wing // Gary Phone #: ###-####
|
BLD-Other | 4/13/2015 | 4/13/2015 | 4/13/2015 | P | PASS |
Jim Storey
|
|
|
To cover // Gary Phone #: ###-#### 4th floor f ok to cover drops/ entry roof truss repairs ok to cover.
|
BLD-Energy code compliance | 4/2/2015 | 4/2/2015 | 4/2/2015 | P | PASS |
Jim Storey
|
|
|
Gary// 1st, 2nd, & 3rd floor bldg. G Phone #: ###-####
|
BLD-Energy code compliance | 3/30/2015 | 3/31/2015 | 3/31/2015 | A | PASS |
Jim Storey
|
|
|
Gary// 1st, 2nd, and 3rd floor wing G- air barrier insulation Phone #: ###-####
|
BLD-Energy code compliance | 3/27/2015 | 3/30/2015 | 3/30/2015 | A | PASS |
Jim Storey
|
|
|
Gary//1st floor F wing Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 | P | PASS |
Jim Storey
|
|
|
RCE... Second floor F // Dan Phone #: ###-####
|
BLD-Energy code compliance | 3/11/2015 | 3/11/2015 | 3/11/2015 | P | PASS |
Jim Storey
|
|
|
insulation // Gary Phone #: ###-####unit septration walls above ceilling/ corridor ok to pre gyp 3rd
|
BLD-Energy code compliance | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | PASS |
Jim Storey
|
|
|
3rd fl wing f - Gary Phone #: ###-#### ceilling ok to cover
|
BLD-Other | 2/26/2015 | 2/27/2015 | 2/27/2015 | P | PASS |
Jim Storey
|
|
|
Gary// F wing- 2nd and 3rd floors-demising walls Phone #: ###-####
|
BLD-Wall Bracing | 2/19/2015 | 2/20/2015 | 2/20/2015 | A | PART |
Jim Storey
|
|
|
Gary-F wing 1,2,3,4,floor Phone #: ###-#### sheer naill ok pending rfi as to top plate or blk. top of sheathing.
|
BLD-Framing/Rough-in | 2/6/2015 | 2/9/2015 | 2/9/2015 | A | PASS |
Jim Storey
|
|
|
Garyf Bldg F Phone #: ###-#### coridor 4th floor ok
|
BLD-Other | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | PASS |
Jim Storey
|
|
|
Gary// F wing-3rd floor- hallway- approval to insulate Phone #: ###-####
|
BLD-Wall Bracing | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PASS |
Jim Storey
|
|
|
JC-exterior shear g wing Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/21/2014 | | DONE |
|
|
|
permit was in REV status, no plan mods or deferred subs were done?
|
Print Occupancy Form | | | 2/21/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 2/21/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 2/20/2014 | | |
|
|
|
|
Routing - PLAN CHECK | 10/30/2013 | | 2/20/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2014 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 2/6/2013 | | 2/20/2014 | | PASS |
John Menard
|
|
|
1st Review completed 5/11/2013
|
Routing - MECHANICAL | | | 2/19/2014 | | PASS |
Troy James
|
|
|
|
Routing PW Drainage | 2/15/2013 | | 2/12/2014 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 1/23/2014 | | DONE |
Tisha Gallop
|
|
|
received two copies of resonse and plan sheets AA210, AA211, AA220, AA212, AA213, AA401, AA604, AA702, AA503, AA601, AS201, AS601, AS221, AS300, AS700, AC604, AC211, AC213, AC603, AT100, AT101, AI210, AI516, AI611, AI211, AI212, AI213, AI214, AI217, AI221, AI227, PS201, ES211, ET100, EA301, EA302, EA303, ET100, EI200, EI210, EI300, MI211, MI212, MI213, MI222, MI224, MI225, MI228, MI223, MI226, MI229, MI231, MC211, C400, G003, G201, G211, G220; inserted by Ron Hill.
|
Plan resubmittals requested | | | 12/13/2013 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the second plan review requesting revisions. JCM
|
Routing - Erosion and Sediment | 10/29/2013 | | 11/1/2013 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLUMBING | 2/15/2013 | | 10/31/2013 | | PASS |
Daryl Spivey
|
|
|
|
Routing PW Drainage | 10/30/2013 | | 10/30/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 10/29/2013 | | 10/29/2013 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Sewer Design | 10/29/2013 | | 10/29/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Sewer Rating | 10/29/2013 | | 10/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 10/29/2013 | | 10/29/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 10/29/2013 | | 10/29/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 10/29/2013 | | 10/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLAN CHECK | 5/8/2013 | | 10/29/2013 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 10/25/2013 | | |
|
|
|
Complete plan set of resubmittals received
|
Routing Off Site - STRUCTURAL | 8/21/2013 | | 9/30/2013 | | PASS |
Ron Hill
|
|
|
|
Plan resubmittals received | | | 9/18/2013 | | DONE |
|
|
|
Rec'd response letter, calcs and sheets SI200; 201; 202; 203; 210; 211; 212; 213; 214; 215; 220; 221; 222; 223; 224; 230; 231; 232; 233; 234; 235; 600; 610; 620; 630; 700; SC211; 212; ST001; 002; 101; 102; 103; 201; 202; 203; 301; 302; 303; 401; 402; 403; 501; 301; SS210; 211 - taken to JCM
|
Plan resubmittals received | | | 8/20/2013 | | |
|
|
|
8-20-13 received 3 structural design calcs, 3 copies if sheets s1210,s1211,s1212,s1213,s1214,s1215,s1220,s1221,s1222,s1223,s1224,s1230,s1231,s1232,s1233,s1234,s1235,sc211,sc212,s1600,s1610,s1620,s1630,s1700,st001,st002. sent to CHM2HILL outside engineering per Ron Hill///dld
|
Plan resubmittals requested | | | 5/17/2013 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
1st review completed | | | 5/8/2013 | | FAIL |
|
|
|
Failed PW, ESC
|
Routing - FIRE | 5/8/2013 | | 5/8/2013 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Routing - PLAN CHECK | 2/28/2013 | | 5/8/2013 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/3/2013 | | 4/18/2013 | | FAIL |
Ron Hill
|
|
|
|
Route to Impact Fee Review | 2/6/2013 | 2/11/2013 | 4/9/2013 | | PASS |
Cindy M. Gould
|
|
|
Impact fees applied to BLD13-00179
|
Plan resubmittals received | | | 4/3/2013 | | DONE |
Tisha Gallop
|
|
|
received three copies of Structural Calcs and plan sheets ST001, ST002, SI210, SI211, SI212, SI213, SI214, SI215, SI220, SI221, SI222, SI223, SI224, SI230, SI231, SI232, SI233, SI234, SI235, SI600, SI620, SI700, ST101, ST102, ST103, ST201, ST202, ST301, ST302, ST401, ST402, ST501, ST601; Ron Hill took two copies and one copy routed to off site structural.
|
Telephone call | | | 4/3/2013 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Routing - PLANNING | 2/27/2013 | | 2/28/2013 | | PASS |
Josh Wilson
|
|
|
DRH12-00250 Josh Wilson
|
Routing - Erosion and Sediment | 2/13/2013 | | 2/15/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
Need more information on non-stormwater discharges. Where will these discharges be directed to. Need phasing plan for clearing and grubbing and permanent stabilization. Ref ESC13-0069 for Plan
|
Routing PW Solid Waste | 2/13/2013 | | 2/14/2013 | | FAIL |
|
|
|
|
Routing PW Street Lights | 2/14/2013 | | 2/14/2013 | | FAIL |
Mike D Hedge
|
|
|
|
Routing PW Environmental | 2/14/2013 | | 2/14/2013 | | FAIL |
Walt Baumgartner
|
|
|
SEE BLD 13 00179
|
Routing PW Sewer Rating | 2/13/2013 | | 2/13/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Design | 2/13/2013 | | 2/13/2013 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Existing main in Lysted 15", not 18". Sewer tap permit required and CCTV inspection of new manhole installation. Existing stub provided off lysted needs to be plugged at manhole, and the base re-channeled.
|
Routing - PUBLIC WORKS | 2/8/2013 | | 2/13/2013 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing - PLANNING Land Div | 2/7/2013 | | 2/8/2013 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 2/8/2013 | | 2/8/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 2/6/2013 | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/6/2013 | | DONE |
Tisha Gallop
|
|
|
|
First Notice | | 1/24/2016 | | | |
|
|
|
|