BLD-Final | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | PASS |
Jim Storey
|
|
|
Sean Phone #: ###-####
|
DOC - Permit Finaled | 5/6/2015 | 5/6/2015 | 5/6/2015 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 4/15/2015 | 4/16/2015 | 4/16/2015 | A | PART |
Jim Storey
|
|
|
Sean// inspection for Duplex #2 Phone #: ###-#### c/n
|
BLD-Energy code compliance | 9/24/2014 | 9/24/2014 | 9/25/2014 | P | PASS |
Dave Hannah
|
|
|
Sean Phone #: ###-####
|
BLD-Energy code compliance | 9/11/2014 | 9/12/2014 | 9/15/2014 | A | CANC |
Jim Storey
|
|
|
Sean Phone #: ###-#### air seal ok
|
BLD-Wall Bracing | 7/23/2014 | 7/25/2014 | 7/25/2014 | A | PASS |
Jim Storey
|
|
|
Please call ahead for access - shawn Phone #: ###-#### exterior ok to cover
|
Issue PAID IN FULL permit | | | 2/28/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 2/27/2014 | | |
|
|
|
|
Plan assigned to (CDM) | 2/6/2013 | 2/6/2013 | 2/27/2014 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 2/28/2013 | | 2/27/2014 | | PASS |
Carl D Madsen
|
|
|
|
Inspection Record Card- Bld | | | 2/27/2014 | | DONE |
Christina Prado
|
|
|
|
Case Summary (BLD) | | | 2/27/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2014 | | DONE |
|
|
|
|
Telephone call | | | 2/27/2014 | | DONE |
Christina Prado
|
|
|
called Eugene to advise permits are ready for pick up
|
Permit Ready to Issue | | | 2/27/2014 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 2/19/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked MH201 & MH211 as well as one transmittal sheet; Plans taken and inserted by Ron Hill
|
Routing - MECHANICAL | | | 2/19/2014 | | PASS |
Troy James
|
|
|
|
Routing PW Drainage | 2/15/2013 | | 2/12/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - Erosion and Sediment | 10/29/2013 | | 11/1/2013 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLUMBING | 10/31/2013 | | 10/31/2013 | | PASS |
Daryl Spivey
|
|
|
|
Routing - PUBLIC WORKS | 10/29/2013 | | 10/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 10/29/2013 | | 10/29/2013 | | PASS |
Peter J. McCullough
|
|
|
The duplexes located on the dead-end drive will need to bring their trash and recycling carts to the main drive-through street for collection or pay for premium carry-out service.
|
Routing PW Sewer Rating | 10/29/2013 | | 10/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Design | 10/29/2013 | | 10/29/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Environmental | 10/29/2013 | | 10/29/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Plan resubmittals received | | | 10/25/2013 | | |
|
|
|
Complete plan set of resubmittals received
|
Plan Reviewer's activity | | | 5/6/2013 | | DONE |
Scott Arellano
|
|
|
PDS/Fire to verify FD access roadway and FH water supply only.
|
Route to Impact Fee Review | 2/6/2013 | 2/11/2013 | 4/9/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals received | | | 3/13/2013 | | |
|
|
|
|
Routing - PLANNING | 2/27/2013 | | 2/28/2013 | | PASS |
Josh Wilson
|
|
|
DRH12-00250 Josh Wilson
|
Routing - PLAN CHECK | | | 2/25/2013 | | FAIL |
Carl D Madsen
|
|
|
Failed pending resubmittals for shear wall engineering, emergency escape and rescue openings for the front bedrooms and clarification on rated wall transected by girder trusses. Called and talked to Bill at AG Architecture. 2-25-13 CDM.
These plans will not meet the 1st review timeframes as they are being routed with the commercial submittal package.
|
1st review completed | | | 2/25/2013 | | FAIL |
|
|
|
Failed pending resubmittals for shear wall engineering, emergency escape and rescue openings for the front bedrooms and clarification on rated wall transected by girder trusses. Called and talked to Bill at AG Architecture. 2-25-13 CDM.
These plans will not meet the 1st review timeframes as they are being routed with the commercial submittal package.
|
Routing - Erosion and Sediment | 2/13/2013 | | 2/15/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
Need more information on non-stormwater discharges. Where will these discharges be directed to. Need phasing plan for clearing and grubbing and permanent stabilization. Ref ESC13-0069 for Plan
|
Routing PW Sewer Rating | 2/13/2013 | | 2/13/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | | | 2/13/2013 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 2/8/2013 | | 2/8/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 2/6/2013 | 2/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/6/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/6/2013 | | DONE |
Tisha Gallop
|
|
|
|