Letter of compliance/Occupancy | | | 6/3/2014 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 9/5/2013 | 9/6/2013 | 9/6/2013 | A | PASS |
Tom Arcoraci
|
|
|
clint Phone #: ###-####
|
DOC - Permit Finaled | 9/6/2013 | 9/6/2013 | 9/6/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 8/27/2013 | 8/28/2013 | 8/28/2013 | A | FAIL |
Jim Storey
|
|
|
clint Phone #: ###-#### massanary wall unsupported on sub floor provide engineering to justify load and design.
|
PubWorks Occupancy Approval | 8/28/2013 | 8/28/2013 | 8/28/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved civil engineers approval for sitew gading and drainage. Project is approved for occupancy. Jason Talyor ###-####.
|
BLD-Energy code compliance | 6/17/2013 | 6/18/2013 | 6/18/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 6/13/2013 | 6/14/2013 | 6/14/2013 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Other | 6/10/2013 | 6/10/2013 | 6/10/2013 | P | PASS |
Jim Storey
|
|
|
CLINT Phone #: ###-#### soffits ok to cover
|
BLD-Wall Bracing | 5/30/2013 | 5/30/2013 | 5/30/2013 | P | PASS |
Jim Storey
|
|
|
Joey Phone #: ###-####
|
BLD-Framing/Rough-in | 5/23/2013 | 5/23/2013 | 5/23/2013 | P | PART |
Jim Storey
|
|
|
Joey-Shear inspection Please Phone #: ###-#### 2nd floor ok
|
BLD-Foundation | 4/2/2013 | 4/2/2013 | 4/2/2013 | P | PASS |
Jim Storey
|
|
|
Alvaro Phone #: ###-####
|
BLD-Footing | 4/1/2013 | 4/1/2013 | 4/1/2013 | P | PASS |
Jim Storey
|
|
|
Alvaro Phone #: ###-####
|
BLD-Footing | 3/29/2013 | 3/29/2013 | 3/29/2013 | P | CANC |
Tom Arcoraci
|
|
|
ready at 4:30//Anton Phone #: ###-####
|
PubWorks Subgrade Approval | 3/22/2013 | 3/22/2013 | 3/22/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer. Building department can be scheduled for footing inspection. Jason Taylor ###-####.
|
OVERRIDE | | | 3/7/2013 | | |
|
|
|
|
Plan assigned to (CDM) | | 2/14/2013 | 3/7/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2013 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
advised permit is ready and gave fees due
|
Permit Ready to Issue | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/6/2013 | | DONE |
Christina Prado
|
|
|
received three sets of plans marked C2; taken to Carl for further review
|
Routing PW Grading-Hillside | 3/6/2013 | | 3/6/2013 | | PASS |
Jason C. Taylor
|
|
|
Prior to scheduling footing inspection, Geotechnical Engineer must approve footing subgrade. Jason Taylor ###-####
|
1st review completed | | | 2/28/2013 | | FAIL |
|
|
|
Failed pending grading and drainage 2-28-13 CDM
|
Case Summary (BLD) | | | 2/28/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 2/28/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - FIRE | 2/20/2013 | | 2/22/2013 | | PASS |
Tim Frost
|
|
|
|
Telephone call | | | 2/21/2013 | | DONE |
|
|
|
Called Romeo and told him I could not verify that the East Heartleaf Lane is not a dead end at this time. I am waiting on a call from Romeo if fire sprinklers should be required.
|
Routing - MECHANICAL | 2/19/2013 | | 2/20/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/15/2013 | | 2/19/2013 | | PASS |
David Moser
|
|
|
|
Route to Impact Fee Review | 2/13/2013 | 2/19/2013 | 2/15/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 2/14/2013 | | 2/15/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | | | 2/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 2/14/2013 | | 2/14/2013 | | PASS |
Christina Prado
|
|
|
Per Kim Johnson - No ESC review required for this project
|
Plans ACCEPTED BY PLAN TECH | | | 2/14/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/14/2013 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/14/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 2/13/2013 | | FAIL |
Christina Prado
|
|
|
grading sheet needs to be signed
|
Application received | | 2/13/2013 | | | |
|
|
|
|