DOC - Permit Finaled | | | 1/4/2016 | | DONE |
|
|
|
final passed 5-10-13
|
BLD-Final | 5/9/2013 | 5/10/2013 | 5/10/2013 | A | PASS |
Tom Arcoraci
|
|
|
BOB Phone #: ###-####
|
Zoning Approval | 5/8/2013 | 5/8/2013 | 5/8/2013 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 5/6/2013 | 5/7/2013 | 5/7/2013 | P | PASS |
Forrest France
|
|
|
|
BLD-Framing/Rough-in | 4/12/2013 | 4/15/2013 | 4/15/2013 | P | PART |
Dave Hannah
|
|
|
bob Phone #: ###-#### ok to cover roof
|
BLD-Other | 4/4/2013 | 4/5/2013 | 4/5/2013 | A | PART |
Dave Hannah
|
|
|
masonary rebar - Bob Phone #: ###-#### crews still working mti will be on site for rebar and grout inspection
|
BLD-Other | 3/29/2013 | 4/1/2013 | 4/1/2013 | A | PASS |
Dave Hannah
|
|
|
bob - 10:30 please Phone #: ###-#### concrete columns ok to place concrete.
|
BLD-Foundation | 3/27/2013 | 3/28/2013 | 3/28/2013 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Footing | 3/26/2013 | 3/27/2013 | 3/27/2013 | A | PASS |
Dave Hannah
|
|
|
Darren Gossett Phone #: ###-#### pump house
|
OVERRIDE | | | 3/26/2013 | | |
|
|
|
|
Print Occupancy Form | | | 3/26/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 3/26/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 3/26/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 3/25/2013 | | 3/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/25/2013 | | 3/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2013 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/28/2013 | | 3/25/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLUMBING | 2/28/2013 | | 3/25/2013 | | PASS |
Daryl Spivey
|
|
|
Signed of per Eplan review
|
Routing - Design Review | 2/28/2013 | | 3/18/2013 | | PASS |
Josh Wilson
|
|
|
Approved per DRH13-00040
|
Routing - PLAN CHECK | 2/28/2013 | | 3/13/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 2/28/2013 | | 3/13/2013 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 3/13/2013 | | FAIL |
|
|
|
|
Routing - FIRE | 2/28/2013 | | 3/12/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Flood Plain | 2/28/2013 | | 3/6/2013 | | PASS |
Jim Wyllie
|
|
|
|
Routing PW Sewer Rating | 2/28/2013 | | 3/4/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 2/28/2013 | | 3/1/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Permit approved with no ESC plan contingent on including this additional scope of work in the master SWPPP for ESC09-00352. No waiver fee required.
|
Route to Impact Fee Review | 2/28/2013 | 3/5/2013 | 2/28/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Design | 2/28/2013 | | 2/28/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Connecting to Existing Stub. No work in Public R/W Necessary
|
Routing - Addressing | 2/28/2013 | | 2/28/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 2/28/2013 | | 2/28/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 2/28/2013 | | PASS |
John Menard
|
|
|
|
Application received | | | 2/17/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 17 2013 4:17PM
|
Pending Assignment by JCM | 2/28/2013 | | | | |
John Menard
|
|
|
|