Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD13-00294
StatusFinaled
Name CULPAN & COMPANY
Site Address 2434 E SUNSHINE DR
Project NameLickley Residence
Customer Number 
ePlanReviewNo
Description
WUI ZONE A, Permit for the construction of a new 3,726 sq. ft., two story (first story 1,703 sq. ft., second story 1,350 sq. ft.) single family dwelling with a 673 sq. ft. finished basement, 300 sq ft of deck, 4.5 bedrooms, 3.5 bathrooms, and a 1,607 sq. ft. attached garage per the approved plans, plan review report, attached engineering, and any notations. R-1B zoning and setbacks per planning. A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/5/201311/6/201311/6/2013APASS
DetailsMike Jordan
Jared Phone #: ###-####
DOC - Permit Finaled11/6/201311/6/201311/6/2013PPASS
DetailsMike Jordan
PubWorks Occupancy Approval11/5/201311/5/201311/5/2013 DONE
DetailsJason C. Taylor
Project completed. Recieved engineers approval for site drainage and grading. Ok for occupancy by P.W. Jason Taylor ###-####
BLD-Final10/15/201310/16/201310/16/2013ANR
DetailsTom Arcoraci
Jarrod Phone #: ###-####
BLD-Energy code compliance7/2/20137/3/20137/3/2013APASS
DetailsDave Hannah
Jared Phone #: ###-####
BLD-Framing/Rough-in7/1/20137/2/20137/2/2013APASS
DetailsJim Sly
Patrick Phone #: ###-####
BLD-Framing/Rough-in6/27/20136/28/20136/28/2013AFAIL
DetailsTony Young
jared Phone #: ###-####,, correction posted,, do not insulate
BLD-Other6/6/20136/7/20136/7/2013APART
DetailsTony Young
fire rated soffits - Jarod Phone #: ###-####,, 1st layer ok
Plan resubmittals received  6/5/2013 DONE
new manual j
Routing - MECHANICAL6/5/2013 6/5/2013 PASS
DetailsTroy James
resubmitted manual j
BLD-Wall Bracing5/31/20136/3/20136/3/2013APASS
DetailsTom Arcoraci
JAROD Phone #: ###-####
BLD-Foundation4/23/20134/24/20134/26/2013PPASS
DetailsDave Hannah
hyrum Phone #: ###-####
BLD-Footing4/22/20134/23/20134/23/2013APART
DetailsDave Hannah
2nd footing - Hyrun Phone #: ###-#### upper level forms up and horz bar in waiting for engioneer on vert splacing ok to place concrete
PubWorks Subgrade Approval4/23/20134/23/20134/23/2013 DONE
DetailsJason C. Taylor
Recieved subgrade approval for column pads (4-southern & 2 eastern). Building department may be scheduled for inspections. Jason Taylor ###-####
PubWorks Subgrade Approval4/22/20134/22/20134/22/2013 DONE
DetailsJason C. Taylor
Recieved subgrade approval for footing locations to the north of the basement wall. Building department may be scheduled for inspections. Jason Taylor ###-####
BLD-Foundation4/11/20134/12/20134/15/2013APART
DetailsDave Hannah
hyrum Phone #: ###-#### basement walls
BLD-Footing4/8/20134/9/20134/10/2013PPART
DetailsDave Hannah
hyrum Phone #: ###-#### basement ftgs ok
PubWorks Subgrade Approval3/28/20133/28/20133/28/2013 DONE
DetailsJason C. Taylor
Subgrade approval recieved from geotechnical engineer for entire building footprint. Building department may be scheduled for footing inspections. Jason Taylor ###-####.
Issue PAID IN FULL permit  3/25/2013 DONE
DetailsBarbara Stitt
OVERRIDE  3/20/2013  
Plan assigned to (AJS)3/12/20133/12/20133/20/2013 DONE
DetailsAdele J Schaffeld-Griffin
Recieved resised plans 3/18/13. spoke with Jarrod 3/19/13. The revised sheets did not iclude the engineers stamp for the existing stamped sheets. He will get them re submitted or have the engineer come in and stamp them. 3/19/13 ajs
Routing - PLAN CHECK3/20/2013 3/20/2013 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  3/20/2013 DONE
Case Summary (BLD)  3/20/2013 DONE
DetailsAdele J Schaffeld-Griffin
Inspection Record Card- Bld  3/20/2013 DONE
DetailsTisha Gallop
Telephone call  3/20/2013 DONE
DetailsChristina Prado
called Jerrod to advise permit is ready pending Rp and gave fees due. ***plans in comm drawer under street***
Permit Ready to Issue  3/20/2013 DONE
DetailsChristina Prado
Plan resubmittals received  3/19/2013  
Received 2 copies of sheets 2, 3.1, 4, 5, 8.1, 10, 11 and taken to Adele's desk
Plan resubmittals received  3/18/2013  
Recieved 2 copies of cover transmittal, 2 copies of sheets 2, 3.1, 4, 5, 8.1, 10, 11 and taken to Adele's desk
Plan assigned to (CDM)2/20/20132/20/20133/12/2013 DEFR
DetailsCarl D Madsen
Deferred to Adele
1st review completed  3/12/2013 FAIL
DetailsAdele J Schaffeld-Griffin
emailed comments to Jarrod 3/12/13
Routing PW Grading-Hillside3/12/2013 3/12/2013 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Plan resubmittals received  3/12/2013  
Recieved 3 copies of sheets C1.0, C2.0, C3.0
Routing PW Grading-Hillside3/5/2013 3/6/2013 FAIL
DetailsJason C. Taylor
Grading plans need revised. Left message with civil engineer. Jason Taylor ###-####
Routing - PLANNING3/5/2013 3/6/2013 PASS
DetailsDavid Moser
Approved as redlined, reduce chimney height to 35 feet
Routing - MECHANICAL3/4/2013 3/4/2013 PASS
DetailsTroy James
Plan resubmittals received  3/4/2013 DONE
DetailsTisha Gallop
received two new sets of plans (sheets , 2, 3, 3.1, 4, 5, 6, 6.1, 7, 8, 8.1, 9, 10, 11, 12) and three sets of civils (sheets C1.0, C2.0, C3.0); taken to Carl Madsen.
Routing - FIRE3/1/2013 3/4/2013 PASS
DetailsScott Arellano
No comments.
Routing - MECHANICAL2/28/2013 3/1/2013 FAIL
DetailsTroy James
emailed correction to Teds Heating
Routing - Erosion and Sediment3/1/2013 3/1/2013 PASS
DetailsKimberly M. Johnson
Routing - PLANNING2/28/2013 2/28/2013 FAIL
DetailsDavid Moser
The building encrouches into both side yards setbacks. call applicant on 2-28-13 and let him know about the setbacks.
Routing - Addressing2/20/2013 2/28/2013 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS2/28/2013 2/28/2013 PASS
DetailsConnie Baumgartner
Routing PW Grading-Hillside2/20/2013 2/28/2013 FAIL
DetailsJason C. Taylor
Grading plan needs revised, or project needs a Category 1 (old) permit. Jason Talyor ###-####
Route to Impact Fee Review2/20/20132/25/20132/26/2013 PASS
DetailsCindy M. Gould
Intake Approval  2/20/2013 PASS
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  2/20/2013 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  2/20/2013 DONE
DetailsTisha Gallop
Intake Approval  2/19/2013 FAIL
DetailsTisha Gallop
need full size sheets ESC (x2) & Civils (x3)
Application received  2/18/2013 DONE
Application submitted via PDS Online on Feb 18 2013 4:03PM
Routing - PLAN CHECK3/4/2013   FAIL
DetailsAdele J Schaffeld-Griffin
plan check comments emailed to Jarroed 3/12/13