BLD-Final | 8/8/2013 | 8/9/2013 | 8/9/2013 | P | PASS |
Mike Jordan
|
|
|
Please call 1/2 hour prior thanks Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 8/9/2013 | 8/9/2013 | 8/9/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Wall cover | 6/5/2013 | 6/6/2013 | 6/6/2013 | A | PASS |
Mike Jordan
|
|
|
Interior drywall nailing Phone #: ###-#### >> Inspection requested via web by James Larkin. attacment of 5/8 typex rock for interior side of 1hr. wall.
|
BLD-Energy code compliance | 6/3/2013 | 6/3/2013 | 6/3/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 5/31/2013 | 5/31/2013 | 5/31/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/31/2013 | 5/31/2013 | 5/31/2013 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/28/2013 | 5/29/2013 | 5/29/2013 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin. Strap top plate at interior bearing wall were DWV and hot water line penetrate by stairs. Provide membrane penetration protection at water spicket at 1hr, firewall. Ok to insulate, correction notice posted.
|
BLD-Framing/Rough-in | 5/28/2013 | 5/29/2013 | 5/29/2013 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall cover | 5/14/2013 | 5/14/2013 | 5/14/2013 | A | PASS |
Mike Jordan
|
|
|
Firewall attachment Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 5/2/2013 | 5/2/2013 | 5/2/2013 | P | PASS |
Mike Jordan
|
|
|
Remaining wall bracing 2nd. story ok.
|
BLD-Wall Bracing | 5/2/2013 | 5/2/2013 | 5/2/2013 | A | PART |
Mike Jordan
|
|
|
1st story walls, east and west 2nd. story walls ok.
|
BLD-Wall Bracing | 5/1/2013 | 5/1/2013 | 5/1/2013 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 5/1/2013 | 5/1/2013 | 5/1/2013 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 4/30/2013 | 4/30/2013 | 4/30/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Wall Bracing | 4/10/2013 | 4/10/2013 | 4/10/2013 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Footing | 4/1/2013 | 4/1/2013 | 4/1/2013 | P | PASS |
Mike Jordan
|
|
|
greg Phone #: ###-####
|
BLD-Energy code compliance | 3/22/2013 | 3/25/2013 | 3/25/2013 | A | PASS |
Mike Jordan
|
|
|
steve Phone #: ###-#### Rigid foam insulation in interior side of stem wall.
|
BLD-Foundation | 3/18/2013 | 3/20/2013 | 3/20/2013 | P | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 3/18/2013 | 3/19/2013 | 3/19/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 3/13/2013 | | |
Christina Prado
|
|
|
|
OVERRIDE | | | 3/7/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 3/5/2013 | 3/5/2013 | 3/7/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/7/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 3/7/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | | | 3/7/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl Madsen
|
Telephone call | | | 3/7/2013 | | DONE |
Barbara Stitt
|
|
|
Left voice message for Jim that permit is ready with fees due on 3-7-13 @ 11:15am///BAS
|
Plan assigned to (AJS) | 3/5/2013 | 3/5/2013 | 3/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (CDM) | 2/21/2013 | 2/21/2013 | 3/5/2013 | | DEFR |
Carl D Madsen
|
|
|
Assigned to Adele
|
1st review completed | | | 3/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 3/1/2013 | | 3/1/2013 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 2/27/2013 | | 2/28/2013 | | FAIL |
Troy James
|
|
|
emailed correction to dustin mori
|
Routing - PLANNING | 2/22/2013 | | 2/27/2013 | | PASS |
Sue Cummings
|
|
|
|
Route to Impact Fee Review | 2/20/2013 | 2/25/2013 | 2/26/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 2/21/2013 | | 2/22/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | | | 2/22/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 2/20/2013 | 2/20/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/20/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 2/20/2013 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/20/2013 | | DONE |
Barbara Stitt
|
|
|
|