Agreement of Future work | 4/11/2013 | 3/1/2016 | 5/7/2016 | | DONE |
Tim L. Woodard
|
|
|
Phased Upgrade Agreement attached to case.
Phase 1 - March 2013 - May 2013
Phase 2 - April 2013 - July 2013
Phase 3 - July 2013 - July 2015
Phasse 4 - July 2015 - March 2016
5/7/16 All work has been completed under permits BLD14-02855, FIR14-00867, FIR14-00810, ELE13-00432, ELE13-00807, ELE14-03043. Terms of Upgrade Agreement fullfilled. Notice of Compliance filed and attached to case.
|
Third Notice | | 10/5/2013 | 10/29/2013 | | DONE |
|
|
|
|
Print Statement | | | 10/29/2013 | | DONE |
Tisha Gallop
|
|
|
e-mailed to Virna McEntee/St Lukes
|
Third Notice | | 9/4/2013 | 9/30/2013 | | DONE |
|
|
|
e-mailed to Curtis
|
Third Notice | | 8/10/2013 | 8/30/2013 | | DONE |
|
|
|
e-mailed to Curtis Weedop
|
Second Notice | | 7/12/2013 | 8/5/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/5/2013 | | DONE |
|
|
|
|
First Notice | | 6/23/2013 | 7/2/2013 | | DONE |
Barbara Stitt
|
|
|
Faxed 7-2-13
|
Permanent Occupancy | | | 6/13/2013 | | DONE |
|
|
|
|
BLD-Final | 5/22/2013 | 5/22/2013 | 5/22/2013 | P | PASS |
Dave Hannah
|
|
|
Jay Phone #: ###-####
|
FIRE-Final Inspection | 5/21/2013 | 5/22/2013 | 5/22/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed after repairs made while on site including three EM lights, one exit sign, reverse door hardware at the first floor office to allow free egress. Need to post signage at the door to the FACP room. NOTE* tenant has occupied the building prior to final approvals and issuance of a certificate of occupancy.
|
Plan Reviewer's activity | | | 5/14/2013 | | DONE |
|
|
|
Per Boise Fire Marshal, the request for TCO has been denied until the fire alarm permit is re-issued and the fire alarm work performed has been inspected and tested.
|
CHANGE STATUS TO (ISS) | | | 5/14/2013 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/10/2013 | 5/13/2013 | 5/13/2013 | A | NR |
Forrest France
|
|
|
Jay-Please call prior to inspection Phone #: ###-####
|
FIRE-Final Inspection | 5/6/2013 | 5/7/2013 | 5/7/2013 | A | NR |
Forrest France
|
|
|
Pending project related FIR trade permit work.
|
BLD-Conference | 5/2/2013 | 5/2/2013 | 5/3/2013 | P | PASS |
Dave Hannah
|
|
|
jay Phone #: ###-####
|
BLD-Framing/Rough-in | 4/4/2013 | 4/5/2013 | 4/5/2013 | A | PASS |
Dave Hannah
|
|
|
jay Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/4/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 2/25/2013 | | 4/3/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/3/2013 | | 4/3/2013 | | PASS |
Tim L. Woodard
|
|
|
Approved with Upgrade agreement. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 4/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/3/2013 | | DONE |
Christina Prado
|
|
|
left message with construction office givng fees due
|
Permit Ready to Issue | | | 4/3/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 3/27/2013 | | DONE |
Christina Prado
|
|
|
received one copy of upgrade agreement addressed to Jason Blais; Letter placed in Jason's office for review
|
1st review completed | | | 3/11/2013 | | FAIL |
Tim L. Woodard
|
|
|
Failed Plan Review. TLW
|
Routing - PLAN CHECK | 3/26/2013 | | 3/11/2013 | | FAIL |
Tim L. Woodard
|
|
|
Upgrade agreement submitted. Awaiting on approvals from Building Official and Fire Marshall prior to issuance. TLW
|
Routing PW Flood Plain | 2/26/2013 | | 3/11/2013 | | PASS |
Jim Wyllie
|
|
|
Approved on routing slip. TLW
|
Plan resubmittals received | | | 2/28/2013 | | DONE |
Tisha Gallop
|
|
|
received upgrade agreement; taken to Jason Blais.
|
Routing - PUBLIC WORKS | 2/25/2013 | | 2/26/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 2/26/2013 | | 2/26/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 2/25/2013 | 2/25/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/25/2013 | | DONE |
|
|
|
|
Routing - Addressing | 2/25/2013 | | 2/25/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 2/25/2013 | | | |
|
|
|
|