Permit Information
Permit NumberBLD13-00395
StatusFinaled
Name RADIX CONSTRUCTION INC
Site Address 1700 W STATE ST
Project NameCarl's Jr
Customer Number 
ePlanReviewNo
Description
(CARL'S JR) *** 11-13-13 PLAN MODIFICATION TO INCLUDE: A NEW EXTERIOR ACCESSIBLE RAMP WITH HANDRAILS ADDED TO THE SOUTHEAST CORNER AND A NEW EXTERIOR STAIRS W/ HANDRAILS ADDED TO THE SOUTH SIDE OF THE BUILDING. SRZ** Interior and exterior remodel of an existing 3,930 square foot drive-in restaurant building previously occupied by Burger King for a new 2,395 square foot tenant per approved plans. Work to include: demolition work per plans; construct a new interior 2-hr fire barrier wall to separate this building into two separate tenant spaces; construct a new 72 square foot vestibule addition at the South West exterior wall location; construct new exterior parapet walls; new storefront doors and windows; construct new interior walls to create two new accessible restrooms, new dining room, kitchen, scullery/storage room, and a new office room; related interior finishes in compliance with chapter 8 of the 2009 IBC; Installation of a new suspended ceiling system; install new HVAC roof top units; plumbing, mechanical, and electrical work; exterior site improvements; and all other work per the approved plans, attached plan review report, and other reviewing agencies approvals. A new Certificate of Occupancy with the new occupant load total is required to be obtained after all work has been inspected and approved and prior to tenant occupying this space. A separate Tenant Improvement permit is required to occupy the adjacent new 1,607 square foot space. This building is NOT fire sprinklered. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/15/20145/23/2014 DONE
DetailsChristina Prado
complete 5-23-14
Print Statement  5/23/2014 DONE
DetailsChristina Prado
First Notice 4/6/20145/5/2014 DONE
Permanent Occupancy  3/27/2014 DONE
DetailsChristina Prado
BLD-Final3/20/20143/21/20143/21/2014PPASS
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson
Zoning Approval3/21/20143/21/20143/21/2014 DONE
DetailsAndrea Tuning
Print Occupancy Form  3/21/2014 DONE
DetailsTisha Gallop
BLD-Final3/19/20143/21/20143/20/2014ACANC
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Inspection cancelled from web by: Scott Stimpson
FIRE-Final Inspection3/18/20143/20/20143/20/2014APASS
DetailsForrest France
Fire life safety inspection completed satisfactory.
BLD-Final3/18/20143/20/20143/19/2014PCANC
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson Inspection cancelled from web by: Scott Stimpson
BLD-Other3/4/20143/5/20143/5/2014APASS
DetailsTony Young
Fire caulking inspection at 2 hr wall tenant side. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson,, east side ok above ceiling
BLD-Ceiling Grid Inspection2/28/20142/28/20142/28/2014PPEND
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson,, ok pending trades
BLD-Other2/18/20142/19/20142/19/2014APART
DetailsTony Young
2 hr wall Sheetrock in progress. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson...work in progress,, ok so far
BLD-Other2/17/20142/18/20142/18/2014APART
DetailsTony Young
This is for 2hr wall fire caulking. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson,, west side firewall caulking ok
BLD-Energy code compliance2/3/20142/4/20142/4/2014APASS
DetailsJim Storey
Interior sound batt insulation. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson insulation ok
Telephone call  2/4/2014 DONE
DetailsSam Zahorka
I spoke with the architect about the fire barrier penetrations. Requested he provide the contractor with directions on how to wrap the penetrations with the assembly, provide blocking, and fire caulking to the roof decking. He said he would email me this information also so I could attach to the permit for the inspectors information during inspection.
Plan Reviewer's activity  2/4/2014 DONE
DetailsSam Zahorka
Recieved detail from the architect for penetrations and continuity of the 2-hour fire barrier. Attached this to this case under documents. Called Tony Young the Structural Inspector and let him know.
BLD-Other2/3/20142/3/20142/3/2014PPART
DetailsJim Storey
This is a 2 hr wall Sheetrocking in progress inspection. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson gyp ok to progress/ need arch to address fire barrior thrur penatrations of roof framing members/ frame to exterior wall at 2 hr on south end.
BLD-Framing/Rough-in1/31/20141/31/20141/31/2014PPART
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson
Partial framing insp. All walls OK up to 9' level. Structural Engineer to provide a final letter of approval for all Framing. OK to insulate Ext. walls. Fireblock all interior walls at ceiling line......insulation...OK.
BLD-Energy code compliance1/24/20141/27/20141/27/2014PPART
DetailsTony Young
This is for exterior wall rigid insulation prior to Sheetrock. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson,, ok to cover block walls where no trades are behind coolers
BLD-Framing/Rough-in1/24/20141/24/20141/24/2014APART
DetailsTom Arcoraci
Partial wall cover at exterior wall furr out over CMU. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson ok to cover ext cmu walls
BLD-Other1/12/20141/13/20141/13/2014APASS
DetailsTony Young
This is for masonry wall infill rebar inspection. Phone #: ###-#### >> Inspection requested via web by Scott Stimpson,, per plan
BLD-Conference1/8/20141/9/20141/9/2014APART
DetailsTony Young
Chris IVes-Please call prior to inspection Phone #: ###-####,, walk through with Radix owner,, seeing job status
OVERRIDE  11/25/2013  
Plan assigned to (SRZ)11/13/201311/13/201311/25/2013 PASS
DetailsSam Zahorka
Plan mod. pending Design Review to PASS. (Carls Junior)
Routing - PLAN CHECK11/14/2013 11/25/2013 PASS
DetailsSam Zahorka
Re-routed to Planning and Zoning
Routing - PLANNING11/25/2013 11/25/2013 PASS
DetailsAndrea Tuning
Print Occupancy Form  11/25/2013 DONE
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  11/25/2013 DONE
DetailsTisha Gallop
Permit Ready to Issue  11/25/2013 DONE
DetailsBarbara Stitt
Telephone call  11/25/2013 DONE
DetailsBarbara Stitt
Called Jason Smith and told him plan mod is ready for pick & fees due on 11-25-13 @ 11:45am//BAS
CHANGE STATUS TO (ISS)  11/25/2013 DONE
DetailsBarbara Stitt
(F) Reprint permit  11/25/2013 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK11/13/2013 11/14/2013 PASS
DetailsSam Zahorka
Routing - Design Review11/14/2013 11/14/2013 FAIL
DetailsAndrea Tuning
The applicant has submitted a DR application for the changes. The DR application is not yet reviewed.
Case Summary (BLD)  11/14/2013 DONE
DetailsSam Zahorka
Plan Modification Accepted  11/13/2013 DONE
DetailsTisha Gallop
Plan Modification accepted for Bld13-00395 (Carl's Jr.) because during construction it was discovered that the finished floor elevation of the existing building is higher than was anticipated. As a result the proposed connection from the new entrances on the south side of the building to the existing sidewalk on State Street exceed code maximums for an accessible route. A new accessible ramp with handrails has been added at the southeast corner of the building alon with stairs on the south side to connect to the existing sidewalks on State and 17th. Submitted on plan sheets A-1 & A-2; Ref DRH13-00374; routed to Sam Zahorka.
Issue PAID IN FULL permit  8/22/2013 DONE
DetailsBarbara Stitt
Expiration Notice8/8/20138/29/20138/8/2013 DONE
DetailsChristina Prado
Plan assigned to (SRZ)5/29/20135/29/20136/3/2013 PASS
DetailsSam Zahorka
Minor changes resubmitted by architect prior to issuance. Routed to Mechanical, Planning, and Plumbing.
Routing - PLAN CHECK5/31/2013 6/3/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  6/3/2013 DONE
DetailsSam Zahorka
CHANGE STATUS TO (RDY)  6/3/2013  
Routing - MECHANICAL5/29/2013 5/31/2013 PASS
DetailsTroy James
Routing - PLUMBING5/31/2013 5/31/2013 PASS
DetailsBill VanDegrift
resubmittals- misc. pipe routing changes ok
CHANGE STATUS TO (REV)  5/29/2013  
5-29-13 per Sam Z put back in the review status as Andrew Erstad need to make some changes on the plans.
Routing - Design Review5/29/2013 5/29/2013 PASS
DetailsAndrea Tuning
Minor changes resubmitted prior to issuance. See architects transmittal letter for explanation.
OVERRIDE  3/26/2013  
Plan assigned to (SRZ)3/4/20133/4/20133/26/2013 PASS
DetailsSam Zahorka
Carl's Jr.
1st review completed.
Routing - PLAN CHECK3/15/2013 3/26/2013 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  3/26/2013 DONE
DetailsSam Zahorka
Case Summary (BLD)  3/26/2013 DONE
DetailsSam Zahorka
Print Occupancy Form  3/26/2013 DONE
DetailsChristina Prado
Telephone call  3/26/2013 DONE
DetailsTisha Gallop
called Jason and told him permit is ready, fee, need ACHD, RP, RCE/GC
Permit Ready to Issue  3/26/2013 DONE
DetailsTisha Gallop
Plan resubmittals received  3/22/2013 DONE
DetailsTisha Gallop
received response letter from architect and two copies of plan sheet A3.1; taken to Sam Zahorka.
1st review completed  3/15/2013 FAIL
Failed - Plan Check
Routing - FIRE3/13/2013 3/15/2013 PASS
DetailsScott Arellano
Routing - PLAN CHECK3/8/2013 3/13/2013 FAIL
DetailsSam Zahorka
Routing - Design Review3/8/2013 3/8/2013 PASS
DetailsAndrea Tuning
Andrea Tuning - DRH12-00345
Routing - PLUMBING3/7/2013 3/8/2013 PASS
DetailsBill VanDegrift
1. BFP-2 shows a Wilkens mod. #740 dual check. This is not a testable device and is not approved. all backflow devices must be a testable device in Idaho.
2. Public lavs shall have tempered water or a tempering device. Maximum temp. 120 degrees.
3. May require additional backflow protection.
Routing - Erosion and Sediment3/6/2013 3/7/2013 PASS
DetailsKimberly M. Johnson
plan approved with minor redlines
Routing - PUBLIC WORKS3/5/2013 3/6/2013 PASS
DetailsConnie Baumgartner
Routing - Addressing3/4/2013 3/5/2013 PASS
DetailsJason C. Taylor
Routing PW Environmental3/5/2013 3/5/2013 PASS
DetailsWalt Baumgartner
Submitted plans approved as drawn with grease waste line connecting to existing grease interceptor.
Routing PW Sewer Rating3/5/2013 3/5/2013 PASS
DetailsConnie Baumgartner
Application received 3/1/20133/4/2013 DONE
Pending Assignment by JCB3/1/2013 3/4/2013 DONE
DetailsJason Blais
Intake Approval  3/1/2013 PASS
Plan intake review approved.
Plans ACCEPTED BY PLAN TECH  3/1/2013 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  3/1/2013 DONE
DetailsChristina Prado