DOC - Permit Finaled | | | 12/23/2015 | | DONE |
|
|
|
|
BLD-Final | 7/23/2013 | 7/23/2013 | 7/23/2013 | P | PASS |
Mike Jordan
|
|
|
marcos Phone #: ###-####
|
Zoning Approval | 7/19/2013 | 7/19/2013 | 7/19/2013 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Wall Bracing | 6/12/2013 | 6/13/2013 | 6/13/2013 | A | PASS |
Mike Jordan
|
|
|
Marcos Phone #: ###-####. Exterior sheating attachment at north and west enterances ok.
|
BLD-Framing/Rough-in | 6/3/2013 | 6/4/2013 | 6/4/2013 | A | PASS |
Mike Jordan
|
|
|
Marco Phone #: ###-####. Steel stud framing for new exterior facade, west enterance.
|
BLD-Framing/Rough-in | 5/30/2013 | 5/31/2013 | 5/31/2013 | A | PASS |
Mike Jordan
|
|
|
Shear inspection please-Marcos Phone #: ###-####. Exterior steel stud framing for new exterior facade on north side enterance. 3/4 inch plywood attachment ok.
|
BLD-Framing/Rough-in | 5/20/2013 | 5/21/2013 | 5/21/2013 | A | NR |
Mike Jordan
|
|
|
KEVIN Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/29/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 4/29/2013 | | DONE |
Christina Prado
|
|
|
|
Plan Reviewer's activity | | | 4/23/2013 | | DONE |
Sam Zahorka
|
|
|
Architect changed the concrete anchors from Hilti to Tapcon. Attached ESR special inspection info to case under documents and in ePlanReview.
|
OVERRIDE | | | 4/22/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 4/22/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 3/28/2013 | 3/28/2013 | 4/19/2013 | | PASS |
Sam Zahorka
|
|
|
ePlanReview - 1st Review complete. Corrections needed.
|
Routing - PLAN CHECK | 4/19/2013 | | 4/19/2013 | | PASS |
Sam Zahorka
|
|
|
|
Telephone call | | | 4/19/2013 | | DONE |
Sam Zahorka
|
|
|
Spoke with the applicant Carly Mathes. Sent her the Boise City Policy for Special Inspections and the approved Special inspection agencies. The Special Inspection firm is TBD by the Engineer of Record.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2013 | | DONE |
Sam Zahorka
|
|
|
|
Telephone call | | | 4/12/2013 | | DONE |
Sam Zahorka
|
|
|
Called the applicant to explain correction items. Left message.
|
1st review completed | | | 4/12/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 3/28/2013 | | 4/12/2013 | | FAIL |
Sam Zahorka
|
|
|
ePlanReview. See change mark for combustible plywood in a Type IIb building.
|
Routing - FIRE | 3/28/2013 | | 4/4/2013 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - Addressing | 3/28/2013 | | 3/29/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2013 | | 3/29/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 3/28/2013 | | 3/29/2013 | | PASS |
Kimberly M. Johnson
|
|
|
waiver approved
|
Routing - Design Review | 3/28/2013 | | 3/29/2013 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH13-00007
|
Payment Received | | | 3/28/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 3/28/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed and plan review fees paid.
|
Pending Assignment by JCB | 3/28/2013 | | 3/28/2013 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 3/7/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 7 2013 8:07AM
|