Second Notice | | 12/9/2013 | 12/4/2013 | | DONE |
Christina Prado
|
|
|
completed 12-4-13
|
First Notice | 9/30/2013 | 9/30/2013 | 11/29/2013 | | DONE |
Tom Arcoraci
|
|
|
mailed 12-2-13
|
BLD-Final | 9/30/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Tom Arcoraci
|
|
|
Tom, just call me when you are close to the jail. I can be there within minutes. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
DOC - Permit Finaled | 9/30/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 9/19/2013 | 9/20/2013 | 9/20/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed acceptable.
|
FIRE-Alarm Testing | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | NR |
Troy Cobbley
|
|
|
Fire life safety not ready pending the fire alarm permit
|
BLD-Ceiling Grid Inspection | 8/19/2013 | 8/20/2013 | 8/20/2013 | P | PASS |
Tom Arcoraci
|
|
|
Tom, just want you to come by to see if you have any issues with new grid in the kitchen. Thanks Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Final | 7/18/2013 | 7/19/2013 | 7/19/2013 | A | PART |
Tom Arcoraci
|
|
|
Tom, I have one room I need you to final. Troy has looked at it and is waiting to see approved plans. He will have them yet today. Thurs. Phone #: ###-#### >> Inspection requested via web by ary Simon wip ok ok for part occ
|
FIRE-Final Inspection | 7/18/2013 | 7/18/2013 | 7/18/2013 | P | PART |
Troy Cobbley
|
|
|
Life safety for the Dry Storage room is passed.
|
BLD-Ceiling Grid Inspection | 7/2/2013 | 7/2/2013 | 7/3/2013 | P | CANC |
Jim Sly
|
|
|
Tom, I have a ceiling for you to inspect. You will need to come to the security gate at the west end and push the button and tell them you are inspecting the kitchen remodel. proceed through the gate and stay left. You will see my truck.
Phone #: ###-#### >> Inspection requested via web by Gary Simon Hard lid..... OK
|
Case Summary (BLD) | | | 5/30/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/29/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 5/29/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/29/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | 4/12/2013 | 4/12/2013 | 4/15/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
eplan change to recess small walk in cooler instad of installing ramp
|
Routing - PLAN CHECK | 4/15/2013 | | 4/15/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
plan modifications in e plan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2013 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 4/12/2013 | | DONE |
|
|
|
started workflow per AJS
|
Routing - PLAN CHECK | 4/3/2013 | | 4/3/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (AJS) | 3/19/2013 | | 4/3/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 3/27/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see notes in e plan review
|
Routing PW Sewer Rating | 3/15/2013 | | 3/27/2013 | | PASS |
Connie Baumgartner
|
|
|
see approval in e plan review
|
Routing PW Environmental | 3/15/2013 | | 3/27/2013 | | PASS |
Walt Baumgartner
|
|
|
see approval in e plan review
|
Routing - PLAN CHECK | 3/15/2013 | | 3/27/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see comments in e plan review
|
Routing Off Site - C.D.H | 3/15/2013 | | 3/27/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
submitted documents signed by Frank
|
Routing - MECHANICAL | 3/15/2013 | | 3/20/2013 | | PASS |
Troy James
|
|
|
eplan
|
Routing - FIRE | 3/15/2013 | | 3/19/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Plan assigned to (TLW) | 3/15/2013 | | 3/19/2013 | | DEFR |
Tim L. Woodard
|
|
|
Defered review to Adele S. TLW
|
Intake Approval | | | 3/15/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 3/15/2013 | | 3/15/2013 | | PASS |
Daryl Spivey
|
|
|
Per plans and ISPC.
|
Routing - Addressing | 3/15/2013 | | 3/15/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/15/2013 | | 3/15/2013 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 3/8/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 8 2013 2:34PM
|