BLD-Final | 3/26/2014 | 3/26/2014 | 3/26/2014 | P | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 3/26/2014 | 3/26/2014 | 3/26/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 3/25/2014 | 3/25/2014 | 3/26/2014 | P | PASS |
Dave Hannah
|
|
|
rob Phone #: ###-####
|
PubWorks Occupancy Approval | 3/25/2014 | 3/25/2014 | 3/25/2014 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading & drainage, re-vegetation, and driveway has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | PASS |
Dave Hannah
|
|
|
rob Phone #: ###-####
|
BLD-Framing/Rough-in | 10/9/2013 | 10/10/2013 | 10/10/2013 | A | PASS |
Dave Hannah
|
|
|
rob Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | A | FAIL |
Mike Jordan
|
|
|
rob Phone #: ###-#### LATE PLEASE. Strap 4x4 to beam above at bottom of stairs, draftstop all furdowns and at fireplace, seal penetrations at draftstop on open web joist. Correction notice posted. Ok to insulate.
|
BLD-Other | 9/23/2013 | 9/27/2013 | 9/27/2013 | A | PASS |
Mike Jordan
|
|
|
Rob ... soffit and facia insp for WUI Phone #: ###-#### LATE PM IF POSSIBLE
|
BLD-Framing/Rough-in | 9/23/2013 | 9/23/2013 | 9/24/2013 | P | PART |
Dave Hannah
|
|
|
Late afternoon - Robert Phone #: ###-#### shear ok to cover ext walls.
|
BLD-Framing/Rough-in | 9/12/2013 | 9/13/2013 | 9/17/2013 | A | PART |
Dave Hannah
|
|
|
Rob Phone #: ###-#### shear needs to check stapel patterns
|
PubWorks Subgrade Approval | 7/19/2013 | 7/19/2013 | 7/19/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved geotechnical engineers approval for pool subgrade. Building department may be scheduled for inspections. Jason Taylor ###-####
|
BLD-Other | 7/10/2013 | 7/11/2013 | 7/11/2013 | P | PASS |
Dave Hannah
|
|
|
flatwork//rob Phone #: ###-####
|
PubWorks Subgrade Approval | 7/10/2013 | 7/10/2013 | 7/10/2013 | | DONE |
Jason C. Taylor
|
|
|
Received compaction testing for fill under the slab on grade floors. Geotechnical engineer has approved subgrade, builidng department may be scheduled for inspections. Jason Taylor ###-####.
|
BLD-Foundation | 6/17/2013 | 6/18/2013 | 6/19/2013 | P | PART |
Dave Hannah
|
|
|
early - shawn Phone #: ###-#### rebar ok cerw is still setting forms
|
BLD-Footing | 6/17/2013 | 6/17/2013 | 6/17/2013 | P | PASS |
Dave Hannah
|
|
|
request early pm//Shawn Phone #: ###-####
|
PubWorks Subgrade Approval | 6/17/2013 | 6/17/2013 | 6/17/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval letter from Bob Arnold for entire building footprint. Footing inspection can be scheduled with the building department. Jason Taylor ###-####.
|
OVERRIDE | | | 5/24/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/24/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/24/2013 | | DONE |
Tisha Gallop
|
|
|
no fee for plan mod per CDM
|
Plan assigned to (CDM) | 5/16/2013 | 5/16/2013 | 5/23/2013 | | PASS |
Carl D Madsen
|
|
|
Project Dox - Plan modification
|
Routing - PLAN CHECK | 5/17/2013 | | 5/23/2013 | | PASS |
Carl D Madsen
|
|
|
ePlan review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2013 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 5/22/2013 | | 5/22/2013 | | PASS |
Jason C. Taylor
|
|
|
New grading plan approved.
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLANNING | 5/17/2013 | | 5/17/2013 | | PASS |
Colleen T Carroll
|
|
|
|
Plan Modification Accepted | | | 5/16/2013 | | DONE |
Tisha Gallop
|
|
|
started plan mod in pjd, moved house on lot.
|
OVERRIDE | | | 5/3/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/3/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/3/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 4/1/2013 | 4/1/2013 | 5/2/2013 | | PASS |
Carl D Madsen
|
|
|
eplan
|
Routing - PLAN CHECK | 5/2/2013 | | 5/2/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/2/2013 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 5/1/2013 | | 5/1/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 4/30/2013 | | 4/30/2013 | | PASS |
Troy James
|
|
|
eplan
|
1st review completed | | | 4/16/2013 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | | | 4/16/2013 | | FAIL |
Carl D Madsen
|
|
|
Carl Madsen
|
Routing - FIRE | 4/16/2013 | | 4/16/2013 | | PASS |
Scott Arellano
|
|
|
No Fire Sprinklers Required
|
Routing - MECHANICAL | | | 4/3/2013 | | FAIL |
Troy James
|
|
|
eplan
|
Routing PW Grading-Hillside | 4/2/2013 | | 4/3/2013 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan needs revised, spoke with Civil about corrections/revisions. Applicant will need to re-submit grading plan when new plan is recieved. Jason Taylor ###-####.
|
Route to Impact Fee Review | 4/1/2013 | 4/4/2013 | 4/2/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | | | 4/2/2013 | | PASS |
|
|
|
|
Routing - Addressing | | | 4/2/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 4/2/2013 | | 4/2/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 4/1/2013 | | 4/2/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Intake Approval | | | 4/1/2013 | | PASS |
Barbara Stitt
|
|
|
|
Application received | | | 3/9/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 9 2013 1:53PM
|