Third Notice | | 9/3/2014 | 10/9/2014 | | DONE |
|
|
|
This permit finaled on the web by Adam Johnson
|
Third Notice | | 6/14/2014 | 8/29/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
Third Notice | | 5/10/2014 | 6/9/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
Third Notice | | 4/5/2014 | 5/5/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
Second Notice | | 3/16/2014 | 3/31/2014 | | DONE |
|
|
|
|
First Notice | | 2/3/2014 | 3/6/2014 | | DONE |
|
|
|
|
BLD-Final | 1/24/2014 | 1/24/2014 | 1/24/2014 | P | PASS |
Dave Hannah
|
|
|
Final inspection of 12th floor TI and corridor, DB Fitzpatrick. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
Permanent Occupancy | | | 1/24/2014 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | NR |
Dave Hannah
|
|
|
Request for Building Final, DB Fitzpatrick, 12th Floor. Thanks. Adam. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
FIRE-Final Inspection | 1/21/2014 | 1/21/2014 | 1/21/2014 | P | PASS |
Craig D. Hanson
|
|
|
life safety pass
|
BLD-Ceiling Grid Inspection | 1/20/2014 | 1/21/2014 | 1/21/2014 | P | PASS |
Jim Sly
|
|
|
Ceiling grid inspection of added corridor extension, DB Fitz, 12th floor, requested by Bob L. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson Grid OK.
|
Print Occupancy Form | | | 1/8/2014 | | DONE |
|
|
|
|
BLD-Conference | 10/3/2013 | 10/4/2013 | 10/7/2013 | A | PASS |
Dave Hannah
|
|
|
Conformation of FP at perimeter columns, follow up from yesterday. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/2/2013 | 10/3/2013 | 10/7/2013 | A | PASS |
Dave Hannah
|
|
|
Framing Inspection. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/1/2013 | 10/1/2013 | 10/7/2013 | P | PASS |
Dave Hannah
|
|
|
DB Fitzpatrick, 12th Floor Framing. Thanks, Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 10/1/2013 | 10/1/2013 | 10/1/2013 | P | CANC |
Dave Hannah
|
|
|
DB Fitzpatrick, 12th Floor Framing. Thanks, Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson Inspection cancelled from web by: Adam Johnson
|
Issue PAID IN FULL permit | | | 8/8/2013 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 8/7/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 8/7/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 5/1/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/1/2013 | | 5/1/2013 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 3/22/2013 | | 5/1/2013 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed
|
Routing - PLAN CHECK | 3/22/2013 | | 4/9/2013 | | FAIL |
Tim L. Woodard
|
|
|
Refer to E-Plan Review Change Marks. TLW
|
1st review completed | | | 4/9/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 3/22/2013 | | 3/26/2013 | | PASS |
Bill VanDegrift
|
|
|
Per plan and 2009 ISPC.
|
Routing - FIRE | 3/22/2013 | | 3/26/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Sewer Rating | 3/22/2013 | | 3/25/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 3/22/2013 | | PASS |
Jason Blais
|
|
|
Intake approved on 3/20/13. Plan Review Fees paid on 3/22/13.
|
Pending Assignment by JCB | 3/22/2013 | | 3/22/2013 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 3/22/2013 | | 3/22/2013 | | PASS |
Jason C. Taylor
|
|
|
Suite number corrected. Jason Taylor ###-####
|
Routing - PUBLIC WORKS | 3/22/2013 | | 3/22/2013 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 3/15/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 15 2013 1:34PM
|