Third Notice | | 7/3/2013 | 7/8/2013 | | DONE |
|
|
|
|
Second Notice | | 6/14/2013 | 6/28/2013 | | DONE |
|
|
|
mailed 7-1-13
|
First Notice | | 5/17/2013 | 6/4/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 5/7/2013 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 5/2/2013 | 5/3/2013 | 5/3/2013 | A | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
BLD-Final | 5/2/2013 | 5/3/2013 | 5/3/2013 | P | PASS |
Tom Arcoraci
|
|
|
Chris Wyatt-PLease call at least 20 mins prior to insepction Phone #: ###-####
|
Routing - PLUMBING | 4/19/2013 | | 4/19/2013 | | PASS |
Daryl Spivey
|
|
|
Add 2 inch drain as marked on plans for walk in cooler condensate drain.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Print Occupancy Form | | | 4/19/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 4/19/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 4/19/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 4/19/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 4/19/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 4/2/2013 | | 4/19/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1ST REVIEW COMPLETED
|
Routing - PLAN CHECK | 4/18/2013 | | 4/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Recieved document from owner on removal of toilet.
|
Routing Off Site - C.D.H | 4/18/2013 | | 4/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
signed off in e plan with notes
|
Routing - PLUMBING | 4/17/2013 | | 4/17/2013 | | FAIL |
Daryl Spivey
|
|
|
Provide engineered set of plumbing plans.
|
Routing - MECHANICAL | 4/16/2013 | | 4/16/2013 | | PASS |
Troy James
|
|
|
|
Routing PW Solid Waste | 4/3/2013 | | 4/10/2013 | | PASS |
Peter J. McCullough
|
|
|
approved in e plan review by Peter McCullough, no site improvements proposed, interior only
|
Routing PW Environmental | 4/3/2013 | | 4/10/2013 | | PASS |
Walt Baumgartner
|
|
|
approved, sewere pretreatment jurisdiction bench sewer district ###-#### comments per Walt Bumgartner in e plan review
|
Routing PW Drainage | 4/3/2013 | | 4/10/2013 | | PASS |
Brian Murphy
|
|
|
no review needed as per Brian Murphy in e plan review
|
1st review completed | | | 4/10/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 4/2/2013 | | 4/8/2013 | | FAIL |
Troy James
|
|
|
Look at bread ovens. TLW
Eplan
|
Routing - PLUMBING | 4/2/2013 | | 4/3/2013 | | FAIL |
Bill VanDegrift
|
|
|
Changing plumbing out to new, OK per Bill no plumbing plan. TLW
This project is more that a fixture change out. The plans must address the following items.
1) move floor sink out of restroom into wash area.
2) vent floor sink trap.
3)show water system.
4)food prep sink waste may not be connected to other wastes.
5)include any grease abatement required by public works pretreatment on resubmittal.
6)include any additional requirements by the health department on resubmittal.
|
Routing - Addressing | 4/2/2013 | | 4/3/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 4/2/2013 | | 4/3/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 4/3/2013 | | 4/3/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Payment Received | | | 4/2/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 4/2/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - Design Review | 4/2/2013 | | 4/2/2013 | | PASS |
Andrea Tuning
|
|
|
|
Application received | | | 3/21/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 21 2013 11:30AM
|
Case Summary (BLD) | | | 3/21/2013 | | DONE |
|
|
|
|
Routing Off Site - C.D.H | 4/2/2013 | | | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Walk-in refrigerator must drain indirectly outside of walk-in 2. Existing shower to be converted to mop sink with vacuum breaker faucet 3. Place barrier on both sides of food prep sink 4. Close off door to complete wall with FRP behind hand wash and food prep sinks
comments from e plan review
|
Routing - PLAN CHECK | 4/2/2013 | | | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Building Plan Reviewer AMARU - FLOOR PLAN REVISED a3.pdf Building Plan Review Changemarks note #01 Toilet rooms shall not open directly into a room used for preparation of food for service to the public. IBC section 1210.5 No
1 Building Plan Reviewer AMARU - SITE a1.pdf Building Plan Review Changemarks note #02 IBC section 306.2 specifically identifies bakeries as an F1 occupancy. Please revise code analysis. No
1 Building Plan Reviewer AMARU - SITE a1.pdf Building Plan Review Changemarks note #03 The current edition of ANSI-A117.1 is the 2003 edition, please revise code analysis. No
1 Building Plan Reviewer AMARU - SITE a1.pdf Building Plan Review Changemarks note #04 Please have the architect provide a statement on these plans that references building permit BLD04-02894, George McClean was the architect of record for this project. One of the existing bathrooms and access thereto from fully accessibility compliance for use by the coffee shop and office personnel.
|