Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-00645
StatusFinaled
Name HC COMPANY INC
Site Address 9976 W EMERALD ST
Project NameEmergency Responders Health Ce
Customer Number 
ePlanReviewYes
Description
Emergency Responders Health Center - To construct a new 4,785 square foot, one story, wood framed medical office building and related site improvements. This building is not fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  10/23/2015 DONE
Ok per Bob
BLD-Final5/8/20145/9/20145/9/2014APASS
DetailsMike Jordan
Jason Phone #: ###-####. Ok for perm occ.
Zoning Approval2/24/20142/24/20142/24/2014 PASS
DetailsJosh Wilson
Striping complete.
PubWorks Occupancy Approval12/23/201312/23/201312/23/2013 DONE
DetailsTiffany Lowery
BLD-Final12/20/201312/20/201312/20/2013PPART
DetailsMike Jordan
jason Phone #: ###-####. Needs public works sign off, then ok for temp occ. Front counter not installed, Need final lettter from special inspection agency.
FIRE-Final Inspection12/19/201312/19/201312/19/2013PPASS
DetailsTroy Cobbley
life safety passed
BLD-Ceiling Grid Inspection12/4/201312/5/201312/5/2013APASS
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Conference11/22/201311/25/201311/25/2013ADONE
DetailsMike Jordan
Requesting Building Conference to discuss final sign-off. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Energy code compliance11/1/201311/4/201311/4/2013PPASS
DetailsMike Jordan
Requesting Energy Code Inspection for exterior insulation systems on the South Half of the building. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Conference10/27/201310/28/201310/28/2013APASS
DetailsMike Jordan
Scheduling a building inspection conference at the request of Mike Jordan to review interior walls prior to closing. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Energy code compliance10/28/201310/28/201310/28/2013APASS
DetailsMike Jordan
Scheduling a building inspection conference at the request of Mike Jordan to review interior walls prior to closing. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. North half ok to cover.
BLD-Energy code compliance10/17/201310/18/201310/18/2013APART
DetailsMike Jordan
Requesting Air Seal Inspection for the South half of the building and the final framing and shear nailing inspection on interior walls. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. ok to insulate south half og building. Pending electrical and mechanical rough in inspections.
BLD-Framing/Rough-in10/11/201310/14/201310/14/2013APART
DetailsMike Jordan
Requesting exterior wall air-seal inspection and framing inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Ok to insulate north half gridlines 1 to 6. Neesd to complete nailing on interior shearwalls, complete gussett repairs on trusses T9 and foam all top plate penetrations o n interior walls.
FIRE-Conference10/10/201310/11/201310/11/2013ADONE
DetailsTroy Cobbley
Greg Baisch and I discussed the placement of the exit signs that may be blocked by ducting and the need for the fire hydrant to be rotated so that the 5" barrel does not face a parking space.
Plan assigned to (JCM)10/3/201310/3/201310/7/2013 PASS
DetailsJohn Menard
Routing - PLAN CHECK10/3/2013 10/7/2013 PASS
DetailsJohn Menard
Routing - PLAN CHECK10/3/2013 10/7/2013 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  10/7/2013 DONE
DetailsJohn Menard
CHANGE STATUS TO (ISS)  10/7/2013 DONE
DetailsTisha Gallop
plan mod approved and batch stamped, per JCM no additional fees due.
Routing PW Drainage10/3/2013 10/4/2013 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS10/3/2013 10/3/2013 PASS
DetailsConnie Baumgartner
Plan Modification Accepted  10/3/2013 DONE
DetailsChristina Prado
received notice to start plan mod workflow for changes to storm drainage system.
BLD-Framing/Rough-in9/26/20139/27/20139/27/2013PPASS
DetailsJim Storey
Requesting Roof Nailing Inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch drag nailling ok straps ok all deck sheathing ok to cover.
BLD-Framing/Rough-in9/23/20139/23/20139/23/2013PPASS
DetailsMike Jordan
Requesting a shear nailing inspection for the exterior walls Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Exterior shearnailing ok. Ok to cover.
BLD-Framing/Rough-in9/19/20139/20/20139/20/2013APART
DetailsMike Jordan
Requesting a shear nailing inspection for exterior walls. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Exterior shear nailing, south east corner of biulding only ok to cover. Needs to hit missed areas and provide the double nailing in the sole plate as per approved plans or provide RFI from engineer of record. Area approved for cover has the double nailing into sole plates and top lates S required.
BLD-Concrete8/6/20138/8/20138/8/2013PPASS
DetailsMike Jordan
Request inspection of wire mesh for slab-on-grade. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Slab on grade and interior footings, north half.
BLD-Concrete8/6/20138/7/20138/7/2013APART
DetailsMike Jordan
Requesting inspection of reinforcing steel for under-slab footings. Phone #: ###-#### >> Inspection requested via web by Greg Baisch. Interior footings. Work in progress, pend. special inspection.
BLD-Footing8/2/20138/5/20138/5/2013ANR
DetailsMike Jordan
Rebar inspection for thickened slab areas. Requesting Noon inspection. Phone #: ###-#### >> Inspection requested via web by Greg Baisch
BLD-Other7/16/20137/16/20137/16/2013PPART
DetailsJim Sly
reinforcing steel for walls-Greg Phone #: ###-####
Approved plans on site.....Foundation walls appear to be OK. Pending MTI special inspection, tests and approvals.
BLD-Footing7/10/20137/11/20137/11/2013APART
DetailsMike Jordan
mid morning rebar - greg Phone #: ###-####. Work in progress onplacing vertical reinforcement at perimeter footings and column pad footings to the S.E. Will have special inspection.
OVERRIDE  6/28/2013  
Issue PAID IN FULL permit  6/28/2013 DONE
DetailsChristina Prado
Print Occupancy Form  6/28/2013 DONE
DetailsChristina Prado
Permit Ready to Issue  6/28/2013 DONE
DetailsChristina Prado
Plan assigned to (JCM)5/9/2013 5/13/2013 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  5/13/2013 DONE
DetailsJohn Menard
Plan resubmittals received  5/10/2013 DONE
DetailsJohn Menard
Received revised plans sheet A3.4 and A11.1. JCM
Plan assigned to (JCM)3/27/2013 5/9/2013 PASS
DetailsJohn Menard
1st Review completed 4/13/2013. JCM
PLANS/APPL TAKEN TO FRONT DESK  5/8/2013 DONE
DetailsJohn Menard
Routing Off Site - STRUCTURAL5/1/2013 5/7/2013 PASS
DetailsJohn Menard
Routing PW Drainage5/1/2013 5/6/2013 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS5/1/2013 5/3/2013 PASS
DetailsConnie Baumgartner
Routing PW Street Lights5/1/2013 5/2/2013 PASS
DetailsMike D Hedge
Routing - Erosion and Sediment5/1/2013 5/1/2013 PASS
DetailsKimberly M. Johnson
approved
Plan Reviewer's activity  5/1/2013 PASS
DetailsJohn Menard
Reviewed and approved submitted revisions. JCM
Routing - PLAN CHECK5/1/2013 5/1/2013 PASS
DetailsJohn Menard
Routing PW Sewer Design3/27/2013 4/16/2013 PASS
DetailsKyle S. Rosenmeyer
1st review completed  4/16/2013 DONE
DetailsJohn Menard
Plan resubmittals requested  4/16/2013 DONE
DetailsJohn Menard
Resubmittals requested through ProjectDox. JCM
Routing - PLAN CHECK3/27/2013 4/13/2013 FAIL
DetailsJohn Menard
Routing PW Drainage3/27/2013 4/10/2013 FAIL
DetailsBrian Murphy
Routing Off Site - STRUCTURAL3/27/2013 4/9/2013 FAIL
DetailsJohn Menard
Routing - FIRE3/27/2013 4/2/2013 PASS
DetailsScott Arellano
Attached comments to plans.
Routing PW Solid Waste3/27/2013 4/1/2013 PASS
DetailsPeter J. McCullough
Routing - Design Review3/27/2013 3/29/2013 PASS
DetailsJosh Wilson
OK per DRH13-00024
Routing - Erosion and Sediment3/27/2013 3/28/2013 FAIL
DetailsKimberly M. Johnson
1) This project is subject to federal NPDES regulation; please include langauge in the plan specifiying that an NOI is required to be filed. Please note that this plan is not EPA compliant. For more information, review the CGP section 7 for SWPPP reqts. 2) Please provide the anticipated construction schedule and sequence of events. 3) Please provide BMPs for equipment fueling. 4) Provide a comprehensive list of potential pollutants that includes sediment. 5) Describe what BMPs will be used for both temporary stabilization and the timeframe stabilization measures are required 6) Describe what BMPs will be used for final stabilization. 7) Describe what waste disposal practices are required for paint, stucco, mortar, saw cutting slurry, and whatever other potential pollutants will be on site.
Pending Assignment by JCM3/27/2013 3/27/2013 DONE
DetailsJohn Menard
Routing - PLUMBING3/27/2013 3/27/2013 PASS
DetailsDaryl Spivey
Provide tempered water to lavs and shower.
Per plans and 2009 ISPC.
Routing - PLANNING Land Div3/27/2013 3/27/2013 PASS
DetailsDave Abo
Parcel 1 of ROS 3972. Property Line Adjustment. Verification of Legal Lot signed by Todd Tucker.
Routing - Addressing3/27/2013 3/27/2013 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS3/27/2013 3/27/2013 PASS
DetailsConnie Baumgartner
Routing PW Environmental3/27/2013 3/27/2013 PASS
DetailsWalt Baumgartner
Routing PW Sewer Rating3/27/2013 3/27/2013 PASS
DetailsConnie Baumgartner
Routing PW Street Lights3/27/2013 3/27/2013 FAIL
Details
Intake Approval  3/27/2013 PASS
DetailsJohn Menard
Application received  3/21/2013 DONE
Application submitted via PDS Online on Mar 21 2013 1:05PM
Zoning Approval Temp12/19/201312/19/2013   
60-day temp occ to allow for weather warm enough to paint striping in parking lot.