Permit Information
Permit NumberBLD13-00682
StatusFinaled
Name ESI
Site Address 800 W MAIN ST Unit: 1220
Project Name8th & Main Ste# 1220
Customer Number 
ePlanReviewYes
Description
(CLIFTON LARSON ALLEN – 8th & Main Building – Suite # 1220) This building is sprinklered to comply as a high-rise building. PLAN MODIFICATION 9-25-13: Modification is a complete redesign for a different tenant, including adding additional square footage and occupant load. TLW Permit is to build out for the first time a 4,610 square foot office space on the 11,250 square foot 12th floor (Shell and Core done under BLD12-01991). Work is to include: [construction of interior non-bearing walls to create; a waiting / reception room, a 231 square foot conference room, a 309 square foot conference room, 9 individual offices, an open office area, a IT room, a storage closet, a coat closet, and a break room], installation of a new lighting, installation of new plumbing, installation of new mechanical, and new interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/3/201410/9/2014 DONE
This permit finaled on the web by Adam Johnson
Third Notice 6/14/20148/29/2014 DONE
e-mailed to Adam Johnson
Third Notice 5/10/20146/9/2014 DONE
e-mailed to Adam Johnson
Third Notice 4/5/20145/5/2014 DONE
e-mailed to Adam Johnson
Second Notice 3/16/20143/31/2014 DONE
First Notice 2/3/20143/6/2014 DONE
BLD-Final1/24/20141/24/20141/24/2014PPASS
DetailsDave Hannah
Final inspection walk of TI and exit corridor. 12th Floor, Clifton Larson Allen. Thanks AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
Permanent Occupancy  1/24/2014 DONE
DetailsBarbara Stitt
FIRE-Final Inspection1/23/20141/23/20141/23/2014PPASS
DetailsCraig D. Hanson
F&LS Pass
FIRE-Final Inspection1/21/20141/21/20141/21/2014PNR
DetailsCraig D. Hanson
BLD-Conference1/20/20141/21/20141/21/2014PPASS
DetailsJim Sly
CLA Ceiling inspection request of 12th floor corridor extension on CLA space. Requested by Bob L. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam
Johnson
Grid OK.
BLD-Ceiling Grid Inspection1/15/20141/16/20141/16/2014APASS
DetailsJim Sly
Ceiling cover inspection requested by Bob L. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in11/14/201311/15/201311/15/2013APASS
DetailsDave Hannah
CLA Framing Inspection, 12th Floor. Contact Tyler for walk. Thanks Adam. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
Permit Ready to Issue  10/24/2013 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  10/24/2013 DONE
DetailsBarbara Stitt
Print Occupancy Form  10/24/2013  
DetailsBarbara Stitt
Extend Review Timeline  10/11/2013 DONE
DetailsChristina Prado
180day extension granted
Plan assigned to (TLW)9/3/2013 9/25/2013 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK9/3/2013 9/25/2013 PASS
DetailsTim L. Woodard
Routing - Addressing9/3/2013 9/5/2013 PASS
DetailsJason C. Taylor
Routing - FIRE9/3/2013 9/5/2013 PASS
DetailsScott Arellano
Attached comments to plans.
Plan Modification Accepted  9/3/2013 DONE
DetailsTim L. Woodard
Modification to expand space and alter interior layout. TLW
Routing - PLAN CHECK6/17/2013 6/24/2013 PASS
DetailsTim L. Woodard
Approved with modification from the B.O. allowing 107 ft common path of egress travel. TLW
PLANS/APPL TAKEN TO FRONT DESK  6/24/2013 DONE
DetailsTim L. Woodard
Plan assigned to (TLW)3/29/2013 6/24/2013 PASS
DetailsTim L. Woodard
1st Review Completed
Plan resubmittals received  6/17/2013 DONE
DetailsTim L. Woodard
1st review completed  4/16/2013 DONE
DetailsTim L. Woodard
Routing - PLAN CHECK3/29/2013 4/16/2013 FAIL
DetailsTim L. Woodard
Refer to change marks in E-plan review. TLW
Routing - FIRE3/29/2013 4/11/2013 PASS
DetailsScott Arellano
Attached comments to plans.
Routing - PLUMBING3/29/2013 4/1/2013 PASS
DetailsBill VanDegrift
Per plans and 2009 ISPC.
Routing PW Sewer Rating4/1/2013 4/1/2013 PASS
DetailsConnie Baumgartner
Routing - Addressing3/29/2013 4/1/2013 PASS
DetailsJason C. Taylor
Address should include "Suite 1220"
Routing - PUBLIC WORKS3/29/2013 4/1/2013 PASS
DetailsBeverly Mountain
Intake Approval  3/29/2013 PASS
DetailsJason Blais
Prescreen passed by John Menard on 3/27/13. Plan Review Fees paid on 3/29/13.
Pending Assignment by JCB3/29/2013 3/29/2013 DONE
DetailsJason Blais
Application received  3/26/2013 DONE
Application submitted via PDS Online on Mar 26 2013 12:44PM
Intake Approval  3/26/2013 FAIL
DetailsJohn Menard
Please submit a revised completed Certificate of Value, indicating values for the
Electrical, Plumbing, Mechanical, Fire Sprinkler and Alarm work.