BLD-Final | 1/27/2014 | 1/27/2014 | 1/27/2014 | P | PASS |
Jim Storey
|
|
|
Cameron Phone #: ###-####
|
DOC - Permit Finaled | 1/27/2014 | 1/27/2014 | 1/27/2014 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 12/20/2013 | 12/23/2013 | 12/23/2013 | A | NR |
Jim Storey
|
|
|
call for accesss - cameron Phone #: ###-#### no addrerss #/ no call back for accesss.
|
BLD-Framing/Rough-in | 6/4/2013 | 6/5/2013 | 6/5/2013 | P | PART |
Jim Sly
|
|
|
soffits & sheet rock also - Cameron Phone #: ###-#### Framing OK....Double rock at soffits.....West side only......OK.
|
BLD-Framing/Rough-in | 5/31/2013 | 6/2/2013 | 6/3/2013 | A | NR |
Jim Storey
|
|
|
Cameron Phone #: ###-####
|
BLD-Wall Bracing | 5/23/2013 | 5/24/2013 | 5/24/2013 | A | PASS |
Jim Storey
|
|
|
CAMERON Phone #: ###-####
|
BLD-Foundation | 4/26/2013 | 4/26/2013 | 4/29/2013 | P | PASS |
Jim Storey
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 4/23/2013 | 4/25/2013 | 4/25/2013 | P | PASS |
Jim Storey
|
|
|
BILL Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/22/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 4/12/2013 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/12/2013 | | DONE |
Christina Prado
|
|
|
called cameron to advise permit is ready for pick up and gave fees due
|
Permit Ready to Issue | | | 4/12/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | | 3/27/2013 | 4/11/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
1ST REVIEW COMPLETED
|
Routing - PLANNING | 4/10/2013 | | 4/11/2013 | | PASS |
Susan Riggs
|
|
|
|
Routing - PLAN CHECK | 4/11/2013 | | 4/11/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/11/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Plan resubmittals received | | | 4/10/2013 | | DONE |
Christina Prado
|
|
|
Received two sets of reduced site plan as well as full size site plan;Taken to Adele for review
|
1st review completed | | | 4/8/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
working with planning and zoning on moving on lot can not buidild over property line, rated construction required and no opeings with in 3 feet of property line.
|
Routing - PLAN CHECK | 4/4/2013 | | 4/8/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
working with planning and zoning on moving on lot can not buidild over property line, rated construction required and no opeings with in 3 feet of property line.
|
Routing - MECHANICAL | 3/29/2013 | | 4/4/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/27/2013 | 4/1/2013 | 4/1/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 3/28/2013 | | 3/29/2013 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Addressing | 3/27/2013 | | 3/28/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2013 | | 3/28/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/27/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/27/2013 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/27/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | 3/27/2013 | | | |
|
|
|
|