Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberBLD13-00729
StatusFinaled
Name ESI
Site Address 300 S CAPITOL BLVD
Project NameRETAIL 1
Customer Number 
ePlanReviewNo
Description
Retail 1 (Shell and Site Work Permit) - To construct a new 13,184 square foot, one story retail building and related site improvements. This building is constructed of masonry exterior walls and steel frame construction. This is a shell permit only and separate tenant improvement permit will be required to finish this building for occupancy. NOTE: This building is required to be fully fire sprinkled and with a fire alarm system. The sprinklers are used for area increase. All work shall comply with the approved drawings, the plan review report, and all applicable codes. DRH12-00319 & CUP12-00067 per Planning and Zoning. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Temp Occupancy Appr10/11/201310/11/201310/25/2013 DONE
DetailsMike D Hedge
*Temp Occupancy* - Waiting on street lights, Mike Hedge ###-####
Letter of compliance/Occupancy  10/25/2013 DONE
DetailsChristina Prado
DOC - Permit Finaled  10/25/2013 DONE
BLD-Final10/23/201310/24/201310/24/2013ADONE
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Final10/24/201310/24/201310/24/2013PPASS
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
FIRE-Final Inspection10/24/201310/24/201310/24/2013PPASS
DetailsTroy Cobbley
Life safety passed
BLD-Final10/21/201310/22/201310/23/2013PCANC
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
FIRE-Final Inspection10/21/201310/22/201310/23/2013PPART
DetailsForrest France
Final pending project related fire sprinkler permit items and finishes.
BLD-Final10/9/201310/10/201310/14/2013PNR
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Chris Palmer needs fire finals
Zoning Approval10/11/201310/11/201310/11/2013 DONE
DetailsSarah Schafer
FIRE-Final Inspection10/9/201310/10/201310/10/2013ANR
DetailsForrest France
Building shell permit fire life safety approval pending completion and final acceptance testing of trade related and project attatched fire sprinkler and fire alarm permit work in accordance with applicable standards (NFPA13, NFPA72, IFC). Refer to BLD13-00729 fire code plan review notes for specific details.
BLD-Conference10/8/201310/8/201310/9/2013PPASS
DetailsDave Hannah
Meet onsite for a pre-turnover/final inspection meeting. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Framing/Rough-in9/6/20139/6/20139/9/2013PPASS
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Chris Palmer insulation of ext walls ok
BLD-Framing/Rough-in8/26/20138/26/20138/28/2013PPASS
DetailsDave Hannah
Homer Phone #: ###-#### ext steel stud walls ok
Override - Parcel Holds8/26/20131/1/19008/26/2013  
this is for framining inspection
BLD-Framing/Rough-in8/21/20138/21/20138/21/2013PPART
DetailsMike Jordan
chris Phone #: ###-####. Work in progress on exterior steel stud walls for storefronts. All Cross bracing not yet installed, parapets ok.
Override - Parcel Holds8/21/20131/1/19008/21/2013  
bld framing
BLD-Foundation8/7/20138/7/20138/7/2013PCANC
DetailsDave Hannah
Footing and foundation waterproofing inspection. Phone #: ###-#### >> Inspection requested via web by Chris Palmer Inspection cancelled from web by: Chris Palmer
Telephone call  7/11/2013 DONE
DetailsSam Zahorka
Called the architect Megan with Erstad. Explained the slab insulation was red-lined on the plans and noted in the Final Plan Review Report (Item #8). I then emailed her the Final Plan Review Report. I offered a solution for a plan modification if the slab insulation was not wanted. I suggested she submit a new COMcheck envelope compliance with no slab insulation and I woould approve a plan modification for her. She stated she would check with the contractor and get back to me.
BLD-Footing7/8/20137/8/20137/8/2013APASS
DetailsDave Hannah
Footing at NW corner of property. Approx 5 yds. Pour at 1130 am. Please call with any questions. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Foundation6/28/20136/28/20137/2/2013PPASS
DetailsDave Hannah
Stem walls at Retail 1. Pour is scheduled for 1pm today. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
BLD-Energy code compliance7/1/20137/1/20137/1/2013AFAIL
DetailsDave Hannah
Foundation insulation inspection late morning. Please call with any questions. Phone #: ###-#### >> Inspection requested via web by Chris Palmer insulation stopped at bottom of slab
BLD-Footing6/19/20136/20/20136/20/2013APASS
DetailsDave Hannah
Footing inspection for Retail 1. Pour scheduled for 11am, inspection requested for 930am. Construction access is located on 6th. Please call with any questions. Thank You. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
Issue PAID IN FULL permit  5/7/2013 DONE
DetailsBarbara Stitt
OVERRIDE  4/23/2013  
Plan assigned to (SRZ)3/29/20133/29/20134/23/2013 PASS
DetailsSam Zahorka
2nd Review Completed.
Plan resubmittals received  4/23/2013 DONE
DetailsKimberly M. Johnson
ESC narrative
Routing - Erosion and Sediment4/23/2013 4/23/2013 PASS
DetailsKimberly M. Johnson
approved
PLANS/APPL TAKEN TO FRONT DESK  4/23/2013 DONE
DetailsSam Zahorka
Inspection Record Card- Bld  4/23/2013 DONE
DetailsTisha Gallop
Telephone call  4/23/2013 DONE
DetailsChristina Prado
called Andrew to advise permit is ready pending RP, GC & ACHD letter. Also gave fees due
Permit Ready to Issue  4/23/2013 DONE
DetailsChristina Prado
Routing PW Street Lights4/19/2013 4/19/2013 PASS
Details
Routing Off Site - STRUCTURAL4/18/2013 4/19/2013 PASS
DetailsAngela Brosious
Approved with no further comments. 4-18-13 called Action Couriers for pick up (exphedited review)
Routing - Erosion and Sediment4/19/2013 4/19/2013 FAIL
DetailsKimberly M. Johnson
Must address anticipated dewatering from sprinkler flushing and include BMPs for stabilization of lot (i.e. stabilized access routes, compaction, phasing, scheduling of paving and other hard surfaces, ect)
Routing - PUBLIC WORKS4/18/2013 4/19/2013 PASS
DetailsConnie Baumgartner
Resubmittals for Mike Hedge
Routing - PLUMBING4/18/2013 4/18/2013 PASS
DetailsDaryl Spivey
Modifications
Plan resubmittals received  4/18/2013  
4-17-13 received 6 response,4 document changes, landscape revisions, structural review comments ,revision-structural, revisions-mechanical, summary –plumbing, summary-fire protection, structural calcs & 2 national historic listings & 4 copies of sheets FS-1.00,FS-2.00,A0.01,C1.1,C1.2,C2.1,C3.1,C3.2,C4.0,C5.0,L1.0,L1.1,L1.2,L2.0,A1.11,A1.21,A1.23,A2.11,A2.41,A2.42,A2.43,A2.44,A2.45,A2.46,A3.11,A5.13,A6.12,S0.00,S1.01,S1.02,S1.03,S1.12,S2.11,S2.21,S3.02,S3.21,S3.22,M2.1M3.1,P2.1,P2.2,P2.3,P2.4,P3.1,E1.1,E2.1,E2.2,E2.3,E2.4,E3.1,E4.1
Routing - FIRE4/18/2013 4/18/2013 PASS
DetailsScott Arellano
Modifications to sheets FS-1.00 amd FS-2.00 regarding removal of fire sprinklers from non-combutsible canopies and notes for clarification.
Routing Off Site - STRUCTURAL3/29/2013 4/11/2013 FAIL
DetailsSam Zahorka
Correction comments emailed to architect.
Routing - FIRE4/8/2013 4/10/2013 PASS
DetailsScott Arellano
Attached comments to plans.
1st review completed  4/10/2013 FAIL
Failed PW and ESC, Structural Review.
Route to Impact Fee Review4/1/20134/4/20134/9/2013 PASS
DetailsCindy M. Gould
Routing - PLAN CHECK4/5/2013 4/8/2013 PASS
DetailsSam Zahorka
Sam Zahorka
Routing - PLUMBING4/4/2013 4/5/2013 PASS
DetailsDaryl Spivey
Per plans and 2009 ISPC.
Routing - PLANNING4/5/2013 4/5/2013 PASS
DetailsSarah Schafer
DRH12-00319-Sarah Schafer

Approved per DRH12-00319 and as indicated on sheet A3.11.

Complies with requirements of CUP12-00067. CER-4/8/13
Routing - PUBLIC WORKS4/1/2013 4/4/2013 FAIL
DetailsConnie Baumgartner
Failed by Mike Hedge for lighting
Routing - Erosion and Sediment4/4/2013 4/4/2013 FAIL
DetailsKimberly M. Johnson
1. Please list any anticipated non-stormwater discharges and where the water will be discharged. Please note that any discharges to the MS4 system must have prior approval from ACHD.
2. Please describe what practices will be employed to stabilize the access routes within the 2.2 acre project (i.e. phasing, compacted pit run, asphalt, ect). The main concern is preventing the area from becoming entirely a dirt lot for any significant amount of time.
3. Please add to Table 1 removal of temporary BMPs after final stabilization is achieved.
4. Please create a comprehensive list of potential pollutants (i.e. paint, saw cutting, equipment fueling)
5. Page 5 states that the vegetative buffer between construction and the public roads will be preserved for as long as practical. Per our phone call, the buffer will be removed fairly quickly. Will perimeter controls need to be installed when the vegetative buffer is removed? Please show these BMPs on the map if needed.
6. Page 5 states that some existing vegetation will be preserved where construction activities are not required. Please show these areas on the map or delete this reference if no vegetation will be protected.
Routing PW Sewer Design4/3/2013 4/4/2013 PASS
DetailsKyle S. Rosenmeyer
Existing flush tank may exist at point of connection in Broad Street. Will check in field and inform the design engineer.
Routing PW Street Lights4/2/2013 4/4/2013 FAIL
DetailsMike D Hedge
1. Add note about removal of light on 6th, 2. Show light at Capitol and Broad tied to new lighting circuit, 3. Add jbox at each light pole, 4. Required notes missing from drawings, 5. Add reference for pole and concrete base details.
Plan Reviewer's activity  4/4/2013 DONE
DetailsSam Zahorka
Emailed the 1st structural plan review comments to the architect to forward to the engineer.
Routing PW Environmental  4/3/2013 PASS
DetailsWalt Baumgartner
No grease abatement. Trader Joes building - packaged foods only per owner/operator
Routing PW Drainage4/1/2013 4/2/2013 PASS
DetailsBrian Murphy
Routing - Addressing4/1/2013 4/1/2013 PASS
DetailsJason C. Taylor
Routing PW Sewer Rating4/1/2013 4/1/2013 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste  4/1/2013 PASS
DetailsPeter J. McCullough
Routing - PLANNING Land Div4/1/2013 4/1/2013 PASS
DetailsDave Abo
Parcel created by ROS 1364.
Application received 3/29/20133/29/2013 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  3/29/2013  
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  3/29/2013 DONE
DetailsBarbara Stitt
Telephone call  3/29/2013 DONE
DetailsTisha Gallop
called Action Couriers for pick up.
Intake Approval  3/29/2013 PASS
DetailsSam Zahorka