BLD-Final | 10/10/2013 | 10/11/2013 | 10/14/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
Letter of compliance/Occupancy | | | 10/14/2013 | | DONE |
Christina Prado
|
|
|
|
DOC - Permit Finaled | | | 10/14/2013 | | DONE |
Christina Prado
|
|
|
Per Dave Hannah
|
FIRE-Final Inspection | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Craig D. Hanson
|
|
|
all devices tested and passed
|
BLD-Energy code compliance | 9/23/2013 | 9/24/2013 | 9/25/2013 | P | PASS |
Dave Hannah
|
|
|
Early afternoon if possible. Thank You. Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Energy code compliance | 7/9/2013 | 7/9/2013 | 7/9/2013 | P | PASS |
Dave Hannah
|
|
|
Foundation Insulation Phone #: ###-#### >> Inspection requested via web by Chris Palmer
|
BLD-Foundation | 7/3/2013 | 7/3/2013 | 7/3/2013 | A | PART |
Dave Hannah
|
|
|
Stem walls. Pour scheduled for noon today. Phone #: ###-#### >> Inspection requested via web by Chris Palmer mti on site for spec. inspection
|
BLD-Footing | 6/27/2013 | 6/27/2013 | 6/27/2013 | P | PART |
Dave Hannah
|
|
|
Footing pour scheduled for 1pm. Phone #: ###-#### >> Inspection requested via web by Chris Palmer mti will be doing spec inspection on this project
|
BLD-Footing | 6/26/2013 | 6/26/2013 | 6/27/2013 | P | PART |
Dave Hannah
|
|
|
Footing rebar inspection. Pour scheduled for 3pm today. Call with any questions. Thanks, Phone #: ###-#### >> Inspection requested via web by Chris Palmer mti will be doing spec inspection on this project
|
Issue PAID IN FULL permit | | | 5/7/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (SRZ) | 3/29/2013 | 3/29/2013 | 4/23/2013 | | PASS |
Sam Zahorka
|
|
|
1st Review Completed.
|
Routing Off Site - STRUCTURAL | 3/29/2013 | | 4/23/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 4/10/2013 | | 4/23/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/23/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Erosion and Sediment | 4/23/2013 | | 4/23/2013 | | PASS |
Kimberly M. Johnson
|
|
|
approved under ESC13-00291
|
Inspection Record Card- Bld | | | 4/23/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 4/23/2013 | | DONE |
Christina Prado
|
|
|
called Andrew to advise permit is ready pending RP, GC & ACHD letter. Also gave fees due
|
Permit Ready to Issue | | | 4/23/2013 | | DONE |
Christina Prado
|
|
|
|
Routing PW Street Lights | 4/2/2013 | | 4/19/2013 | | PASS |
Mike D Hedge
|
|
|
|
Routing Off Site - STRUCTURAL | 4/18/2013 | | 4/19/2013 | | PASS |
Angela Brosious
|
|
|
Approved 4-18-13 with no further comments. called Action Couriers for pick up (expedited review)
|
Routing - PUBLIC WORKS | 4/18/2013 | | 4/19/2013 | | PASS |
Beverly Mountain
|
|
|
Resubmittals for Mike Hedge
|
Routing - Erosion and Sediment | 4/19/2013 | | 4/19/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
Resubmittals
|
Routing - PLUMBING | 4/18/2013 | | 4/18/2013 | | PASS |
Daryl Spivey
|
|
|
modifications
|
Plan resubmittals received | | | 4/18/2013 | | |
|
|
|
4-17-13 received 6 response,4 document changes, landscape revisions, structural review comments ,revision-structural, revisions-mechanical, summary –plumbing, summary-fire protection, structural calcs & 2 national historic listings & 4 copies of sheets FS-1.00,FS-2.00,A0.01,C1.1,C1.2,C2.1,C3.1,C3.2,C4.0,C5.0,L1.0,L1.1,L1.2,L2.0,A1.11,A1.21,A1.23,A2.11,A2.41,A2.42,A2.43,A2.44,A2.45,A2.46,A3.11,A5.13,A6.12,S0.00,S1.01,S1.02,S1.03,S1.12,S2.11,S2.21,S3.02,S3.21,S3.22,M2.1M3.1,P2.1,P2.2,P2.3,P2.4,P3.1,E1.1,E2.1,E2.2,E2.3,E2.4,E3.1,E4.1
|
Routing - FIRE | 4/18/2013 | | 4/18/2013 | | PASS |
Scott Arellano
|
|
|
Modifications to sheets FS-1.00 amd FS-2.00 regarding removal of fire sprinklers from non-combusible canopies and notes for clarification.
|
1st review completed | | | 4/10/2013 | | FAIL |
|
|
|
Failed PW.
|
Routing - FIRE | 4/18/2013 | | 4/10/2013 | | PASS |
Scott Arellano
|
|
|
Attached fire code comments to plans.
|
Route to Impact Fee Review | 4/1/2013 | 4/4/2013 | 4/9/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 4/5/2013 | | 4/8/2013 | | PASS |
Cody Riddle
|
|
|
CUP12-00067-Cody Riddle
Complies with requirements of CUP12-00067. CER-4/8/13
|
Routing - PLAN CHECK | 4/8/2013 | | 4/8/2013 | | PASS |
Sam Zahorka
|
|
|
Sam Zahorka
|
Routing - PLUMBING | | | 4/5/2013 | | PASS |
Daryl Spivey
|
|
|
Per pklans and 2009 ISPC.
|
Routing - PLANNING | | | 4/5/2013 | | PASS |
Sarah Schafer
|
|
|
DRH12-00319-Sarah Schafer
Approved per DRH12-00319 and as indicated on sheet A3.11.
|
Routing - PUBLIC WORKS | 4/1/2013 | | 4/4/2013 | | FAIL |
Connie Baumgartner
|
|
|
failed by Mike Hedge for lighting
|
Routing - Erosion and Sediment | 4/4/2013 | | 4/4/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
|
Routing PW Sewer Design | 4/3/2013 | | 4/4/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Existing flush tank may exist at point of connection in Broad Street. Will check in field and inform the design engineer.
|
Routing PW Environmental | | | 4/3/2013 | | PASS |
Walt Baumgartner
|
|
|
shell and core, 1500 gal GI shown, ok
|
Routing PW Drainage | 4/1/2013 | | 4/2/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING Land Div | 4/1/2013 | | 4/1/2013 | | PASS |
Dave Abo
|
|
|
Parcel created by ROS 1364.
|
Routing - Addressing | 4/1/2013 | | 4/1/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Sewer Rating | 4/1/2013 | | 4/1/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | | | 4/1/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Application received | | 3/29/2013 | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 3/29/2013 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up.
|
Intake Approval | | | 3/29/2013 | | PASS |
Sam Zahorka
|
|
|
|