Description
(FIRST AMERICAN TITLE AND ESCROW COMPANY - 8TH & MAIN BUILDING - SUITE 910) The fire sprinkler system is used for high-rise. To create a 2,045 square foot office tenant space located in the Northeast corner of the 9th story of a new high-rise building. Work is to include interior nonbearing walls, interior doors and glass sidelights, suspended acoustical ceilings, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. This tenant space shall not be occupied until the egress path to the 2nd stairway is defined by a corridor having exit signs and emergency lighting. All high-rise fire and life safety systems must also be installed and operational before occupancy. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/3/201410/9/2014 DONE
This permit finaled on the web by Adam Johnson
Third Notice 6/14/20148/29/2014 DONE
e-mailed to Adam Johnson
Third Notice 5/10/20146/9/2014 DONE
e-mailed to Adam Johnson
Third Notice 4/5/20145/5/2014 DONE
e-mailed to Adam Johnson
Second Notice 3/16/20143/31/2014 DONE
First Notice 2/3/20143/6/2014 DONE
BLD-Final1/24/20141/24/20141/24/2014PPASS
DetailsDave Hannah
Final Building walk of TI and exit corridor. PM inspection, First American Title, 9th Floor. Thanks AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
Permanent Occupancy  1/24/2014 DONE
DetailsBarbara Stitt
BLD-Final1/21/20141/22/20141/22/2014ANR
DetailsDave Hannah
Request for building final, 9th Floor, First American Title. Thanks. AKJ. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
FIRE-Final Inspection1/21/20141/21/20141/21/2014PPASS
DetailsCraig D. Hanson
Pass, good
Print Occupancy Form  1/8/2014 DONE
BLD-Conference1/3/20141/3/20141/6/2014PPASS
DetailsDave Hannah
Request conference with Dave H. On site w/Bob Ledford, PM, ESI field office. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Conference10/3/201310/4/201310/7/2013APEND
DetailsDave Hannah
Follow up on yesterdays FP conformation walk at perimeter. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson still needs brace welded column 6d
BLD-Framing/Rough-in10/2/201310/3/201310/7/2013APEND
DetailsDave Hannah
Recap Framing from yesterday. Thanks, Adam. Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in10/1/201310/1/201310/7/2013PPART
DetailsDave Hannah
First American Title - Framing Inspection. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson ok to cover walls all but for coulmn grid 6d
BLD-Framing/Rough-in9/20/20139/23/20139/23/2013APART
DetailsDave Hannah
Adam Phone #: ###-#### ok after other trades pass rough ins
Issue PAID IN FULL permit  8/8/2013 DONE
DetailsBarbara Stitt
Print Occupancy Form  8/7/2013 DONE
DetailsBarbara Stitt
Permit Ready to Issue  8/7/2013 DONE
DetailsBarbara Stitt
Plan Reviewer's activity  5/8/2013 DONE
Finished uploading revised sheets Emailed by the Architect's representative.
Plan assigned to (CJW)4/9/20134/9/20135/3/2013 PASS
DetailsCarl Westfall
FIRST AMERICAN TITLE - 9TH STORY (20 days - May 3) ePlanReview - 8th & Main - 9th Floor
Routing - PLAN CHECK5/1/2013 5/3/2013 PASS
DetailsCarl Westfall
The drawings were approved with "red lines".
PLANS/APPL TAKEN TO FRONT DESK  5/3/2013 DONE
Plan resubmittals received  5/1/2013 DONE
Plan resubmittals requested  4/24/2013 DONE
1st review completed  4/24/2013 DONE
Failed Building
Routing - PLAN CHECK4/9/2013 4/24/2013 FAIL
DetailsCarl Westfall
The IBC plan review was started on April 18 and was finished on April 24. Revised drawings were required. See the plan review report.
Routing - FIRE4/9/2013 4/16/2013 PASS
DetailsScott Arellano
Attached IFC comments to plans.
Routing - PLUMBING4/9/2013 4/10/2013 PASS
DetailsBill VanDegrift
Per plans and 2009 ISPC.
Routing PW Sewer Rating4/10/2013 4/10/2013 PASS
DetailsConnie Baumgartner
Routing - Addressing4/9/2013 4/10/2013 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS4/9/2013 4/10/2013 PASS
DetailsBeverly Mountain
Pending Assignment by JCB4/9/2013 4/9/2013 DONE
DetailsJason Blais
Intake Approval  4/8/2013 PASS
DetailsSam Zahorka
Application received  4/1/2013 DONE
Application submitted via PDS Online on Apr 1 2013 6:39PM