Third Notice | | 7/14/2015 | 7/17/2015 | | DONE |
|
|
|
This permit finaled on the web by Teri Kiser
|
Second Notice | | 6/20/2015 | 7/9/2015 | | DONE |
|
|
|
Mailed 7-10-15
|
First Notice | | 5/29/2015 | 6/10/2015 | | DONE |
|
|
|
Mailed out 6-10-15
|
Permanent Occupancy | | | 5/19/2015 | | DONE |
|
|
|
|
BLD-Final | 4/27/2015 | 4/27/2015 | 4/27/2015 | P | PASS |
Jim Storey
|
|
|
Cherry Phone #: ###-####
|
FIRE-Final Inspection | 4/24/2015 | 4/27/2015 | 4/27/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
PubWorks Occupancy Approval | 12/22/2014 | 12/22/2014 | 12/22/2014 | | DONE |
Brian Murphy
|
|
|
|
FIRE-Final Inspection | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PART |
Forrest France
|
|
|
Fire life safety inspection at the new hangar completed acceptable.
|
BLD-Final | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | PART |
Mike Jordan
|
|
|
for temp on hangar // Teri Phone #: ###-####. hangar ok, pending fire/life/safety.
|
BLD-Final | 10/3/2014 | 10/6/2014 | 10/6/2014 | A | PASS |
Jim Storey
|
|
|
Teri Phone #: ###-#### office ok boiller rm needs firestopped
|
FIRE-Final Inspection | 10/1/2014 | 10/1/2014 | 10/1/2014 | P | PART |
Troy Cobbley
|
|
|
Fire sprinkler, fire alarm and fire life safety complete in the new office area (basement, first & second floors). New office area only. The remaining new hanger area is not complete yet.
|
FIRE-Final Inspection | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | FAIL |
Troy Cobbley
|
|
|
To complete the life safety in the new office area only I need the fire alarm system corrections completed and all of the emergency lights and exit signs installed and functional.
|
FIRE-Final Inspection | 9/25/2014 | 9/25/2014 | 9/26/2014 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to time constraints.
|
BLD-Conference | 8/25/2014 | 8/26/2014 | 8/27/2014 | A | PASS |
Jim Storey
|
|
|
Terry Phone #: ###-####
|
BLD-Other | 7/17/2014 | 7/18/2014 | 7/18/2014 | A | PASS |
Jim Storey
|
|
|
Fire block on stairway - Terri Phone #: ###-#### fire stopping ok ok to instal hard lid
|
BLD-Conference | 7/16/2014 | 7/17/2014 | 7/17/2014 | A | PASS |
Jim Storey
|
|
|
Terry Phone #: ###-####
|
BLD-Framing/Rough-in | 7/14/2014 | 7/15/2014 | 7/15/2014 | A | PART |
Jim Storey
|
|
|
partial framing on west side of hangar & acoustical ceiling grid insp in basement // Teri Phone #: ###-#### all hard ceillings and part of east drop ceillings ok/ need to fire stop west stair above hard lid.
|
BLD-Framing/Rough-in | 6/2/2014 | 6/2/2014 | 6/2/2014 | P | PASS |
Jim Storey
|
|
|
Teri Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 6/2/2014 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 6/2/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/13/2014 | | |
|
|
|
|
BLD-Framing/Rough-in | 5/9/2014 | 5/13/2014 | 5/13/2014 | A | PART |
Jim Storey
|
|
|
terri Phone #: ###-#### 2 hr exterior ok office framing ok pending review. and trade ri.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2014 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 5/13/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod batch stamped, fees due
|
Routing - PLAN CHECK | 5/6/2014 | | 5/13/2014 | | PASS |
John Menard
|
|
|
|
Plan assigned to (JCM) | 5/6/2014 | | 5/13/2014 | | PASS |
John Menard
|
|
|
Plan Modification to basement. JCM
|
Routing - FIRE | 5/6/2014 | | 5/12/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Mod 05-12-14
|
Routing - PLUMBING | 5/6/2014 | | 5/9/2014 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing PW Sewer Rating | 5/6/2014 | | 5/7/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2014 | | 5/6/2014 | | PASS |
Beverly Mountain
|
|
|
|
Plan resubmittals received | | | 5/5/2014 | | DONE |
|
|
|
started work flow
|
CHANGE STATUS TO (ISS) | | | 4/23/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod
|
OVERRIDE | | | 4/17/2014 | | |
|
|
|
|
Plan assigned to (JCM) | 4/16/2014 | | 4/17/2014 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 4/17/2014 | | 4/17/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2014 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 4/17/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 4/16/2014 | | 4/16/2014 | | FAIL |
John Menard
|
|
|
|
Plan Modification Accepted | | | 4/15/2014 | | DONE |
Tisha Gallop
|
|
|
workflow started to modify fire rated wall
|
BLD-Conference | 4/8/2014 | 4/8/2014 | 4/8/2014 | P | FAIL |
Jim Storey
|
|
|
arch to provide to planreview east wall [ ie 2hr exterior wall ] details and listing not per the aproved plan. 5a-3.4 grid linec-2 thrur c6.
|
BLD-Conference | 4/4/2014 | 4/7/2014 | 4/7/2014 | P | PART |
Jim Storey
|
|
|
Skip Jones Phone #: ###-#### need to meet with plan review.
|
BLD-Framing/Rough-in | 3/18/2014 | 3/19/2014 | 3/19/2014 | A | PASS |
Jim Storey
|
|
|
terri Phone #: ###-#### bathrm west bldg ok to cover/ vent fan ducted thru roof.
|
BLD-Framing/Rough-in | 3/13/2014 | 3/14/2014 | 3/14/2014 | A | FAIL |
Jim Storey
|
|
|
Teri Phone #: ###-#### duct in 2 hr wall no protection/ backing ada
|
BLD-Wall cover | 2/24/2014 | 2/25/2014 | 2/25/2014 | A | PASS |
Tom Arcoraci
|
|
|
Reinspection of fire wall in existing hangar, Also erection of stair systems has begun and open for review. Observation of hangar door rail system work in wip of 2 hr wall ok
|
BLD-Grading Inspection | 1/24/2014 | 1/27/2014 | 1/27/2014 | P | PART |
Jim Storey
|
|
|
Slab on grade base rock ready for insp. Planning spray on insulation/vapor barrier Tues. Also have MTI Density tests Monday afternoon. Phone #: ###-#### >> Inspection requested via web by Teri Kiser mti to verify.
|
BLD-Foundation | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | PART |
Jim Sly
|
|
|
Door rail lower foundation slab gridline 2. Please visit any time before 10am as concrete is scheduled for Noon. Thanks Phone #: ###-#### >> Inspection requested via web by Teri Kiser Door rail slab OK pending MTI special inspection, tests and approvals. MTI approval of soil bearing.
|
BLD-Foundation | 1/16/2014 | 1/17/2014 | 1/17/2014 | A | PASS |
Jim Storey
|
|
|
Please if possible visit by 9am, col. pedestal B/5 and small frost wall (less than 2 yds). Conc. pour @ 10am. Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Foundation | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | PASS |
Jim Storey
|
|
|
Prefer visit btw 10am & 11am, foundation pedestals @ B line, ftg B/5, walls 8 line, north ftg @ 2 line. Concrete scheduled for 1pm w/ MTI rebar insp and samples. Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Foundation | 1/10/2014 | 1/13/2014 | 1/13/2014 | A | PASS |
Jim Storey
|
|
|
Column pedestals & foundation walls line C, also ftgs line B. Prefer approx. visit btw 10am & 11am due to concrete pour set up for 1pm. As always MTI to insp rebar w/ conc. samples. Phone #: ###-#### >> Inspection requested via web by Teri Kiser engineer to adress changes with si insp.
|
BLD-Footing | 1/6/2014 | 1/7/2014 | 1/7/2014 | A | PASS |
Jim Storey
|
|
|
Btw 10am & 11Am preferred to insp ftgs, MTI insp due @ 12:30pm, concrete scheduled for 1pm... Also, steel deck puddle welding insp (which prev. passed insp by MTI) Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Wall cover | 12/26/2013 | 12/26/2013 | 12/26/2013 | P | PART |
Jim Storey
|
|
|
frmg @ mech rm, puddle welding L1 decking, grading existing pipe Hazwhopper ops per EPA Phone #: ###-#### >> Inspection requested via web by Teri Kiser / nr/ 2hr wall esisting building top of wall and ends to be extented.
|
BLD-Foundation | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Jim Storey
|
|
|
10:00 am pour time remaining bsmt wall MTI monitoring Cold weather concreting plan established Heaters, tenting etc... Phone #: ###-#### >> Inspection requested via web by Teri Kiser heat and protection in place/ si on site/ rebar ok to place concrete/ drainage protection aplied to exterior wall ok to start back fil.
|
Print Occupancy Form | | | 12/10/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/10/2013 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/10/2013 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 12/3/2013 | | 12/6/2013 | | PASS |
John Menard
|
|
|
Plan Mod.
|
Routing - PLAN CHECK | 12/3/2013 | | 12/6/2013 | | PASS |
John Menard
|
|
|
Plan modification for office layout changes.
|
Routing - PLUMBING | 12/3/2013 | | 12/4/2013 | | PASS |
Daryl Spivey
|
|
|
1. Vent on oil separater tank required.
2. All non potable water to be marked as required by ISPC.
3. Wrong pump listed on plumbing schedule for ejector.
4. RPBP required on filtered water for coffee machine.
|
Routing - PUBLIC WORKS | 12/3/2013 | | 12/3/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - FIRE | 12/3/2013 | | 12/3/2013 | | PASS |
Craig D. Hanson
|
|
|
No further comments from previous report
|
Routing PW Sewer Rating | 12/3/2013 | | 12/3/2013 | | PASS |
Connie Baumgartner
|
|
|
|
BLD-Concrete | 11/27/2013 | 12/2/2013 | 12/2/2013 | P | PASS |
Jim Storey
|
|
|
SOG at basement Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
Plan Modification Accepted | | | 12/2/2013 | | DONE |
Christina Prado
|
|
|
Plan modification requested for proposed changes to Basement - including revised breakroom locations, revised bathroom layouts and fixture changes as well as revised first floor copier room to accomodate for coffee bar, counters & cabinets addition. Also propesed changes to 2nd floor copier room.
|
BLD-Footing | 11/22/2013 | 11/25/2013 | 11/25/2013 | A | PASS |
Jim Storey
|
|
|
Ftg line 6 btw stairwell and elevator pit Should be ready for insp after 10am Phone #: ###-#### >> Inspection requested via web by Teri Kiser
|
BLD-Foundation | 11/21/2013 | 11/22/2013 | 11/22/2013 | P | PASS |
Jim Storey
|
|
|
Bsmt walls line B and 6 Phone #: ###-#### >> Inspection requested via web by Teri Kiser west end 1/2 of northeast walls ok
|
BLD-Foundation | 11/20/2013 | 11/21/2013 | 11/21/2013 | P | CANC |
Jim Storey
|
|
|
Basement walls lines B and 6 MTI to follow with SI prior to pour Phone #: ###-#### >> Inspection requested via web by Teri Kiser Inspection cancelled from web by: Teri Kiser
|
BLD-Concrete | 11/13/2013 | 11/14/2013 | 11/14/2013 | P | PASS |
Jim Storey
|
|
|
Walls on south and east end of basement Phone #: ###-#### >> Inspection requested via web by Teri Kiser ft north side 1/2 east to west/ wall ok pending si reports.
|
BLD-Footing | 11/6/2013 | 11/7/2013 | 11/7/2013 | P | PART |
Jim Storey
|
|
|
Includes elev pit walls Phone #: ###-#### >> Inspection requested via web by Teri Kiser west ft ok pending si
|
BLD-Footing | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | PART |
Jim Storey
|
|
|
MARK Phone #: ###-#### si ok east end ft ok.
|
OVERRIDE | | | 10/23/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/23/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/23/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2013 | | DONE |
John Menard
|
|
|
|
Permit Ready to Issue | | | 10/23/2013 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 8/28/2013 | | 10/23/2013 | | PASS |
John Menard
|
|
|
1st Review complette 10-7-2013
|
Routing Off Site - STRUCTURAL | 10/16/2013 | | 10/22/2013 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 10/16/2013 | | 10/18/2013 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 8/28/2013 | 8/28/2013 | 10/8/2013 | | PASS |
Craig D. Hanson
|
|
|
.
|
Routing Off Site - STRUCTURAL | 10/8/2013 | | 10/8/2013 | | FAIL |
John Menard
|
|
|
E-mailed the consulting structural engineer a response letter for review. JCM
|
Plan resubmittals requested | | | 10/8/2013 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
1st review completed | | | 10/7/2013 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 8/28/2013 | | 10/7/2013 | | FAIL |
John Menard
|
|
|
|
Routing PW Sewer Design | 10/4/2013 | | 10/4/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
See Notes on BLD13-02439.
|
Routing PW Drainage | 9/11/2013 | | 9/11/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 8/28/2013 | | 9/11/2013 | | FAIL |
John Menard
|
|
|
|
Routing - PLUMBING | 8/28/2013 | | 9/10/2013 | | PASS |
Daryl Spivey
|
|
|
Install a vent on intercepter tank and tie to downstream tank vent and run out seperately from sanitary.
Require an RPBP on filtered water to coffee maker.
|
Routing PW Sewer Design | 8/28/2013 | | 9/9/2013 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
See Notes on BLD13-02439.
|
Routing - Erosion and Sediment | 8/28/2013 | | 8/29/2013 | | PASS |
Jason C. Taylor
|
|
|
See ESC Permit For Comments. Jason Taylor ###-####
|
Routing - Addressing | 8/28/2013 | | 8/29/2013 | | PASS |
Jason C. Taylor
|
|
|
Address Corrected on applications.
|
Route to Impact Fee Review | 8/28/2013 | 9/3/2013 | 8/28/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 8/28/2013 | | 8/28/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 8/28/2013 | | 8/28/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 8/28/2013 | | 8/28/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 8/28/2013 | | 8/28/2013 | | PASS |
Walt Baumgartner
|
|
|
elevator sump pump, manual run
|
Routing - PLANNING Land Div | 8/28/2013 | | 8/28/2013 | | PASS |
Dave Abo
|
|
|
Parcel over 5 acres in size.
|
Pending Assignment by JCM | 8/28/2013 | | 8/28/2013 | | DONE |
John Menard
|
|
|
|
Routing PW Street Lights | 8/28/2013 | | 8/28/2013 | | PASS |
|
|
|
|
Routing - Design Review | 8/28/2013 | | 8/28/2013 | | PASS |
Josh Wilson
|
|
|
Ok per M-1 zone. No Design Review overlay.
|
Intake Approval | | | 8/27/2013 | | FAIL |
John Menard
|
|
|
The Aviation Specilaties, August 2013, structural calculations file is corrupt or is too large. I am not able to open that file. Please see if you can compress the file and re-upload those structural calculations.
|
Intake Approval | | | 8/27/2013 | | PASS |
John Menard
|
|
|
|
Application received | | | 4/16/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2013 6:33PM
|