Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD13-00948
StatusFinaled
Name OLDROCK COMPANIES INC
Site Address 801 W MAIN ST
Project NameLucky Fins Seafood Grill
Customer Number 
ePlanReviewYes
Description
(LUCKY FINS SEAFOOD GRILL) (7-27-13 PLAN MODIFICATION TO EXPAND THE KITCHEN AREA INTO AN ADJACENT INTERIOR AREA BY ABOUT 220 SQUARE FEET. THE ENTIRE EXPANSION AREA WILL BE OCCUPIED BY AN ENLARGED WALK-IN COOLER AND FREEZER. THE KITCHEN EXPANSION WILL ALSO ALLOW A FOOD PREPARATION AREA TO BE LARGER.) The fire sprinkler system is used for increased floor area and for increased occupant load within the fire area. To remodel an existing tenant space for a new restaurant tenant. The 730 square foot building addition was constructed under permit BLD13-00537. Interior nonstructural demolition was done under permit BLD13-00410. This tenant space will have a floor area of about 4,393 square feet inside at grade, 582 square feet on the mezzanine, and 1,933 square feet on the patio. Work is to include interior nonbearing walls, 2 restrooms accessible to the disabled, suspended acoustical ceilings, gypsum board soffits, grease hoods, grease ducts, a grease trap, a sewage ejector pump, a dishwasher hood and duct, interior finishes, an exterior overhead door, new exterior doors, and exterior windows. Penetrations through the 3-hr fire-resistance-rated floor are required to be fire stopped to maintain the fire rating of the floor. Structural work includes construction a new steel awning, modifying a portion of the mezzanine, and filling in a floor opening. Special inspection is required for welding, bolting, expansion anchors, and epoxy anchors. Before holes are created in the 3-hr fire-resistance rated floor, the floor is required to be X-rayed to ensure that no reinforcement will be cut. The work is required to comply with the approved drawings, with the plan review report, with the structural design, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 6/14/20147/2/2014 DONE
This permit finaled on the web by Andrew George
Third Notice 5/10/20146/9/2014 DONE
mailed with letter to Oldrock Companies
Third Notice 4/6/20145/5/2014 DONE
mailed
Third Notice 3/5/20144/1/2014 DONE
mailed
Second Notice 2/6/20142/28/2014 DONE
DetailsChristina Prado
mailed 2-28-14
First Notice 1/20/20141/27/2014 DONE
BLD-Final1/10/20141/10/20141/10/2014PPASS
DetailsDave Hannah
Andrew-Please call prior to inspection Phone #: ###-####
Permanent Occupancy  1/10/2014 DONE
DetailsChristina Prado
Change Expiration Date Only  12/6/2013 DONE
DetailsBarbara Stitt
FIRE-Final Inspection9/16/20139/17/20139/17/2013APASS
DetailsForrest France
Verified EM lighting at the patio area and exit discharge lighting has been installed per previous C/N notice. Door hardware issues to be corrected prior to structural final as agreed.
BLD-Final9/12/20139/13/20139/17/2013PPART
DetailsDave Hannah
andrew Phone #: ###-#### ok for temp occ needs other trades to go perm and add gate in patio area change some door hardware move sink in mens restroom add gaurds at roll up doors ok to change design per caril and andria.
Temporary Occupancy9/16/201312/15/20139/16/2013 DONE
DetailsTisha Gallop
FIRE-Final Inspection9/13/20139/13/20139/13/2013PPART
DetailsTroy Cobbley
A temporary occupancy is being given with Romeo's permission until the patio lighting and exit discharge lighting has been installed and tested. Patio not to be used until the lighting has been installed. Dave is going to cover the outstanding door hardware issues.
FIRE-Final Inspection9/12/20139/13/20139/13/2013AFAIL
DetailsTroy Cobbley
Provide panic hardware on the designated doors and provide single action hardware on the exit to lobby door and the mezzanine office door. Provide second exit/gate from teh Patio seating area. Provide emergency lighting for the Patio area and exit discharge lighting for all of the other required exits. Install the missing sprinkler canopies.
Meeting  9/13/2013 DONE
DetailsBarbara Stitt
Per Brian Murphy no public works signature required//9-13-13
BLD-Ceiling Grid Inspection8/19/20138/19/20138/19/2013APASS
DetailsDave Hannah
As early as possible due to limited access as day progresses due to flooring issues. Thanks in advance. Phone #: ###-#### >> Inspection requested via web by Andrew George
BLD-Ceiling Grid Inspection8/15/20138/16/20138/16/2013ACANC
DetailsDave Hannah
ANDREW Phone #: ###-####
OVERRIDE  7/31/2013  
CHANGE STATUS TO (ISS)  7/31/2013 DONE
DetailsChristina Prado
(F) Reprint permit  7/31/2013 DONE
DetailsChristina Prado
Print Occupancy Form  7/31/2013 DONE
DetailsChristina Prado
BLD-Framing/Rough-in7/24/20137/25/20137/30/2013APASS
DetailsDave Hannah
andrew Phone #: ###-####
BLD-Framing/Rough-in7/29/20137/29/20137/30/2013PPASS
DetailsDave Hannah
andrew Phone #: ###-#### fireproofing holes in 3hr floor ok to cover.
Plan assigned to (CJW)7/23/20137/23/20137/27/2013 PASS
DetailsCarl Westfall
Lucky Fins - PLAN MOD
Routing - PLAN CHECK7/23/2013 7/27/2013 PASS
DetailsCarl Westfall
Plan Mod completed
Routing Off Site - C.D.H7/23/2013 7/25/2013 PASS
Plan Mod - Central District Healt Department
Routing - FIRE7/23/20137/23/20137/24/2013 PASS
DetailsScott Arellano
Attached updated plan review comments to case.
Routing PW Environmental7/23/2013 7/24/2013 PASS
DetailsWalt Baumgartner
Routing - PLUMBING7/23/2013 7/24/2013 PASS
DetailsBill VanDegrift
Plan Mod
Routing - Addressing7/23/2013 7/23/2013 PASS
Plan Mod
Routing - PUBLIC WORKS7/23/2013 7/23/2013 PASS
DetailsBeverly Mountain
Plan Modification Accepted  7/23/2013 DONE
DetailsTisha Gallop
plan mod started in e-plan review to explan tenant space approx 200 sf in adjacent tenant space for freezer, cooler, kitchen prep area.
Routing PW Sewer Rating7/23/2013 7/23/2013 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste7/23/2013 7/23/2013 PASS
DetailsPeter J. McCullough
BLD-Energy code compliance7/12/20137/12/20137/12/2013PPART
DetailsJim Sly
addition - andrew Phone #: ###-####
Energy OK in addition only. New soffits framed in addition appear to be OK. Also, contractor said that Architect looked at them and said they were OK.
BLD-Framing/Rough-in7/10/20137/10/20137/11/2013PPART
DetailsDave Hannah
Partial for addition only - andrew Phone #: ###-#### new area on back needs city set of aproved plans ok from engineer on jack studs and headers at 10 opennings and a soffit detail
Plan assigned to (CJW)4/26/20134/26/20136/7/2013 PASS
DetailsCarl Westfall
LUCKY FINS SEAFOOD GRILL (20 days - May 23) ePlanReview
Routing - FIRE6/4/2013 6/7/2013 PASS
DetailsScott Arellano
Transfer red lines.
PLANS/APPL TAKEN TO FRONT DESK  6/7/2013 DONE
Review completed
Permit Ready to Issue  6/7/2013  
Print Occupancy Form  6/7/2013 DONE
Issue PAID IN FULL permit  6/7/2013 DONE
Routing - PLAN CHECK6/4/2013 6/4/2013 PASS
DetailsCarl Westfall
Drawings approved with "red lines".
Plan resubmittals received  6/4/2013 DONE
Routing - Design Review6/4/2013 6/4/2013 PASS
DetailsJosh Wilson
Addition of guards in front of overhead doors
Plan resubmittals requested  6/3/2013 DONE
Routing - PLAN CHECK5/31/2013 6/3/2013 FAIL
DetailsCarl Westfall
Resubmittal prescreen failed. Revised sheets were uploaded into the documents folder instead of the drawings folder. The Plans Examiner corrected this except for Sheet A1.2 that did not upload properly. Also, one type of floor sink will be 10 inches deep. Need a detail for how the 3-hr rating of the floor will be maintained at that type of sink. Called and discussed with the Architect.
Plan resubmittals received  5/31/2013 DONE
1st review completed  5/23/2013 DONE
Plan resubmittals requested  5/23/2013 DONE
Routing - PLAN CHECK4/26/2013 5/23/2013 FAIL
DetailsCarl Westfall
The IBC plan review was started on May 3 and was finished on May 23. Once started, this project was set aside to do an extensive project that came in first. Revised drawings were required.
Routing - PLUMBING4/26/2013 5/2/2013 PASS
DetailsBill VanDegrift
May require additional backflow protection on equipment.
Per plan and 2009 ISPC
Routing - Addressing4/26/2013 5/1/2013 PASS
DetailsJason C. Taylor
Routing PW Sewer Rating4/26/2013 5/1/2013 PASS
DetailsConnie Baumgartner
Routing PW Environmental4/26/2013 4/30/2013 PASS
DetailsWalt Baumgartner
Grease interceptor in basement to lift station.
Routing - FIRE4/26/2013 4/30/2013 PASS
DetailsScott Arellano
Attached plan review comments to case and plans.
Routing - Design Review4/26/2013 4/30/2013 PASS
DetailsJosh Wilson
Josh Wilson - DRH13-00034
Payment Received  4/26/2013 DONE
Payment received via Govolutions
Intake Approval  4/26/2013 PASS
DetailsJason Blais
Prescreen passed on 4/24/13 by Adele Schaffeld-Griffin. Plan Review Fees paid on 4/26/13.
Pending Assignment by JCB4/26/2013 4/26/2013 DONE
DetailsJason Blais
Routing - PUBLIC WORKS4/26/2013 4/26/2013 PASS
DetailsBeverly Mountain
Routing Off Site - C.D.H4/26/2013 4/26/2013 PASS
Intake Approval  4/23/2013 FAIL
DetailsAdele J Schaffeld-Griffin
The scope of this project places it in the major tenant improvment catagory. Please upload the required check list to begin the pre-screen.

Thank you
Application received  4/19/2013 DONE
Application submitted via PDS Online on Apr 19 2013 11:08AM