(BODIES IN MOTION – Mezzanine and Stair) Planning approval under CUP10-00018. The fire sprinkler system is used for building area increase and for fire area. To remodel an existing excise facility. The daycare is limited to 30 children by the conditional use permit. The 1st story will have a floor area of about 11,820 square feet. The new mezzanine will have a floor area of about 2,124 square feet. A children’s play structure will be installed. Work is to include: construction of a new stairway with handrails and additional exit signs. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Application received 4/23/201311/29/2013 DONE
Third Follow up  11/29/2013 DONE
DetailsTisha Gallop
company hold 11-29-13 /// received1-9-14
Third Notice 10/6/201310/31/2013 DONE
faxed with letter
Third Notice 9/4/201310/1/2013 DONE
mailed
Third Notice 8/10/20138/30/2013 DONE
faxed to Van Auker
Second Notice 7/12/20138/5/2013 DONE
First Notice 6/20/20137/2/2013 DONE
Faxed 7-2-13
Permanent Occupancy  6/10/2013 DONE
DetailsTisha Gallop
BLD-Final6/6/20136/7/20136/7/2013PPASS
DetailsTony Young
requests around 2 - Ron Phone #: ###-####
FIRE-Final Inspection6/6/20136/7/20136/7/2013PPASS
DetailsTroy Cobbley
life safety passed
BLD-Framing/Rough-in5/28/20135/28/20135/28/2013PPASS
DetailsJim Storey
ron Phone #: ###-####
Issue PAID IN FULL permit  5/8/2013 DONE
DetailsBarbara Stitt
Plan assigned to (TLW)4/23/2013 5/3/2013 PASS
DetailsTim L. Woodard
Routing - FIRE5/2/2013 5/3/2013 PASS
DetailsScott Arellano
1st review completed  5/3/2013 PASS
Routing - PLAN CHECK5/3/2013 5/3/2013 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  5/3/2013 DONE
DetailsTim L. Woodard
Case Summary (BLD)  5/3/2013 DONE
DetailsTim L. Woodard
Print Occupancy Form  5/3/2013 DONE
DetailsChristina Prado
Permit Ready to Issue  5/3/2013  
Telephone call  5/3/2013  
5-3-13 called Gayle Jensen permit ready and fee given ///dld
Routing - PLAN CHECK4/23/2013 5/2/2013 PASS
DetailsTim L. Woodard
Plans ACCEPTED BY PLAN TECH  4/23/2013  
ok per Tim W for a level 2
Recd Pcfee & Taken To Pln CK  4/23/2013