Second Notice | | 1/9/2014 | 2/11/2014 | | DONE |
|
|
|
|
Print Statement | | | 2/11/2014 | | DONE |
Tisha Gallop
|
|
|
mailed to EKC
|
First Notice | 12/17/2013 | 12/17/2013 | 12/30/2013 | | DONE |
Mike Jordan
|
|
|
Faxed 12-30-13
|
BLD-Final | 12/16/2013 | 12/17/2013 | 12/17/2013 | P | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####
|
DOC - Permit Finaled | 12/17/2013 | 12/17/2013 | 12/17/2013 | P | PASS |
Mike Jordan
|
|
|
Open electrical permit should be attached to T.I. bld13-01879.
|
FIRE-Final Inspection | 12/16/2013 | 12/17/2013 | 12/17/2013 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 12/16/2013 | 12/16/2013 | 12/16/2013 | P | FAIL |
Troy Cobbley
|
|
|
Provide no parking signage as per the approved plans
|
BLD-Final | 12/12/2013 | 12/13/2013 | 12/13/2013 | P | CANC |
Mike Jordan
|
|
|
james Phone #: ###-#### Inspection cancelled from web by: Barbara Stitt
|
Zoning Approval | 12/10/2013 | 12/10/2013 | 12/10/2013 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 10/30/2013 | 11/5/2013 | 11/5/2013 | P | CANC |
Mike Jordan
|
|
|
james Phone #: ###-#### 11-4-13 per James cancel this inspection not ready
|
FIRE-Final Inspection | 10/31/2013 | 11/1/2013 | 11/1/2013 | P | CANC |
Craig D. Hanson
|
|
|
Per James. Not ready
|
FIRE-Final Inspection | 10/30/2013 | 10/31/2013 | 10/31/2013 | A | CANC |
Troy Cobbley
|
|
|
james Phone #: ###-####// cancelled per phone call from James, called inspector
|
BLD-Wall Bracing | 9/19/2013 | 9/19/2013 | 9/19/2013 | P | PASS |
Mike Jordan
|
|
|
james Phone #: ###-####. Sheathing at canopy.
|
BLD-Framing/Rough-in | 9/13/2013 | 9/16/2013 | 9/16/2013 | A | PASS |
Mike Jordan
|
|
|
James Phone #: ###-####. canopy fra ming ok.
|
BLD-Wall Bracing | 8/1/2013 | 8/2/2013 | 8/2/2013 | P | PASS |
Mike Jordan
|
|
|
JAMES Phone #: ###-####
|
BLD-Framing/Rough-in | 7/25/2013 | 7/26/2013 | 7/26/2013 | P | PASS |
Mike Jordan
|
|
|
james Phone #: ###-####. Hold downs and additional framing for shearwall on gridline D.
|
BLD-Foundation | 7/16/2013 | 7/17/2013 | 7/17/2013 | A | PART |
Tom Arcoraci
|
|
|
rebar inspection please-As early as possible please-James Phone #: ###-#### mti on site needs small docks for plan
|
Inspection Record Card- Bld | | | 6/19/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 6/19/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/11/2013 | | |
|
|
|
|
OVERRIDE | | | 6/11/2013 | | |
|
|
|
|
Telephone call | | | 6/11/2013 | | DONE |
Christina Prado
|
|
|
Called Brian with EKC to advise permit is ready pending ACHD and gave fees due. Also advised of current hold on account
|
Permit Ready to Issue | | | 6/11/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JCM) | 5/8/2013 | | 6/10/2013 | | PASS |
John Menard
|
|
|
1st Review complete 5-18-2013 JCM
|
Routing - PUBLIC WORKS | 6/10/2013 | | 6/10/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 6/10/2013 | | 6/10/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PLAN CHECK | 6/10/2013 | | 6/10/2013 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2013 | | DONE |
John Menard
|
|
|
|
Routing - FIRE | 5/31/2013 | | 6/5/2013 | | PASS |
Tim Frost
|
|
|
|
Routing - PLAN CHECK | 5/31/2013 | | 6/5/2013 | | PASS |
John Menard
|
|
|
|
Routing PW Solid Waste | 5/31/2013 | | 6/3/2013 | | FAIL |
Peter J. McCullough
|
|
|
|
Plan Reviewer's activity | | | 6/3/2013 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and non-structural revisions with redlined note. JCM
|
Routing - PUBLIC WORKS | 5/31/2013 | | 5/31/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 5/31/2013 | | 5/31/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing PW Drainage | 5/9/2013 | | 5/29/2013 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 5/29/2013 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 5/8/2013 | 5/8/2013 | 5/23/2013 | | FAIL |
Tim Frost
|
|
|
e-plan review
|
Routing - PLAN CHECK | 5/23/2013 | | 5/23/2013 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 5/23/2013 | | DONE |
|
|
|
Emailed failed review to RP
|
Routing - PLAN CHECK | 5/8/2013 | | 5/18/2013 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 5/8/2013 | | 5/16/2013 | | FAIL |
John Menard
|
|
|
|
Route to Impact Fee Review | 5/8/2013 | 5/13/2013 | 5/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 5/8/2013 | 5/13/2013 | 5/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Erosion and Sediment | 5/8/2013 | | 5/10/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
1. Include demo work in construction activity description and sequence of events. 2. Include comprehensive list of the potential pollutants. This should include sediment, saw cutting slurry, washout runoff.
|
Routing PW Sewer Rating | 5/9/2013 | | 5/10/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 5/9/2013 | | 5/9/2013 | | FAIL |
Peter J. McCullough
|
|
|
Trash enclosure location does not meet specifications.
###-####
|
Routing - PLUMBING | 5/9/2013 | | 5/9/2013 | | PASS |
Daryl Spivey
|
|
|
Per plan and 2009 ISPC.
|
Routing - Design Review | 5/8/2013 | | 5/9/2013 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Street Lights | 5/9/2013 | | 5/9/2013 | | PASS |
Mike D Hedge
|
|
|
|
Routing - PLANNING Land Div | 5/8/2013 | | 5/9/2013 | | PASS |
Dave Abo
|
|
|
Parcel is over 5 acres in size.
|
Routing - Addressing | 5/8/2013 | | 5/9/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2013 | | 5/9/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCM | 5/8/2013 | | 5/8/2013 | | DONE |
John Menard
|
|
|
|
Intake Approval | | | 4/30/2013 | | PASS |
Sam Zahorka
|
|
|
|
Plan Reviewer's activity | | | 4/30/2013 | | DONE |
Sam Zahorka
|
|
|
No early start for foundation until structural review is approved. Separate permit and certificate of value required for early foundation permit after structural has passed per Jason Blais.
|
Intake Approval | | | 4/29/2013 | | FAIL |
Sam Zahorka
|
|
|
|
Application received | | | 4/23/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2013 4:12PM
|