Third Notice | | 2/8/2014 | 2/7/2014 | | DONE |
Christina Prado
|
|
|
|
Third Notice | | 12/29/2013 | 2/3/2014 | | DONE |
|
|
|
faxed to Steed
|
Second Notice | | 10/11/2013 | 12/24/2013 | | DONE |
|
|
|
|
First Notice | | 9/5/2013 | 10/1/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/26/2013 | | DONE |
|
|
|
|
BLD-Final | 8/22/2013 | 8/23/2013 | 8/23/2013 | P | PASS |
Jim Storey
|
|
|
later the better - rick Phone #: ###-####
|
FIRE-Final Inspection | 8/15/2013 | 8/16/2013 | 8/16/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety okay pending door door hardware at the relocated exit meets approved plan review and IBC requirements- to be verified at structural final.
|
BLD-Final | 8/15/2013 | 8/16/2013 | 8/16/2013 | P | NR |
Jim Storey
|
|
|
rick Phone #: ###-####
|
BLD-Energy code compliance | 7/26/2013 | 7/29/2013 | 7/29/2013 | A | PASS |
Jim Storey
|
|
|
rick Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2013 | 7/24/2013 | 7/24/2013 | A | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-####
|
BLD-Wall Bracing | 7/17/2013 | 7/18/2013 | 7/18/2013 | P | PASS |
Jim Storey
|
|
|
Rick Phone #: ###-#### sheer vwalls nailling ok
|
BLD-Footing | 7/12/2013 | 7/15/2013 | 7/15/2013 | A | PASS |
Jim Storey
|
|
|
Foundation also - Rick Phone #: ###-####
|
OVERRIDE | | | 7/12/2013 | | |
|
|
|
|
BLD-Footing | 7/11/2013 | 7/12/2013 | 7/12/2013 | A | FAIL |
Jim Storey
|
|
|
Rick carley-Mono Pour Phone #: ###-#### permit not isued no insp.
|
Print Occupancy Form | | | 7/12/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/12/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 7/12/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/26/2013 | | |
|
|
|
|
OVERRIDE | | | 6/26/2013 | | |
|
|
|
|
OVERRIDE | | | 6/26/2013 | | |
|
|
|
|
OVERRIDE | | | 6/26/2013 | | |
|
|
|
|
Override - Parcel Holds | | | 6/26/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 6/26/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CJW) | 5/30/2013 | 5/30/2013 | 6/25/2013 | | PASS |
Carl Westfall
|
|
|
MONTESSORI SCHOOL - PARTIAL DEMOLITION AND NEW EXTERIOR WALL (20 days - June 26) ePlanReview
|
Routing - Addressing | 6/24/2013 | | 6/25/2013 | | PASS |
Jason C. Taylor
|
|
|
This address may be used until the ROS has been completed. After the ROS has been recorded the new address muts be used. Jason Taylor ###-####.
|
Routing - PLAN CHECK | 6/24/2013 | | 6/25/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved with "red lines".
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/24/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/17/2013 | | |
|
|
|
|
Plan resubmittals requested | | | 6/10/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/30/2013 | | 6/10/2013 | | FAIL |
Carl Westfall
|
|
|
Revised drawings and additional structural evaluation required.
|
1st review completed | | | 6/10/2013 | | FAIL |
Carl Westfall
|
|
|
|
Routing - PLANNING | 5/30/2013 | | 6/6/2013 | | PASS |
Susan Riggs
|
|
|
Susan Riggs - CUP13-00026
|
Routing - FIRE | 5/30/2013 | | 6/4/2013 | | PASS |
Scott Arellano
|
|
|
No plan review comments attached to case. Demolition work only.
|
Routing - Addressing | 5/30/2013 | | 6/3/2013 | | FAIL |
Jason C. Taylor
|
|
|
Address does not exist.
|
Routing - PUBLIC WORKS | 5/30/2013 | | 5/31/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 5/30/2013 | | 5/31/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing PW Drainage | 5/31/2013 | | 5/31/2013 | | PASS |
Brian Murphy
|
|
|
|
Payment Received | | | 5/30/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Pending Assignment by JCB | 5/30/2013 | | 5/30/2013 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/30/2013 | | PASS |
|
|
|
Passed prescreen and plan review fees paid.
|
Application received | | | 4/23/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2013 4:47PM
|