Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD13-01113
StatusFinaled
Name CSDI CONSTRUCTION INC
Site Address 276 N 8TH ST
Project NameIDAHO BLDG - 1ST FLR
Customer Number 
ePlanReviewNo
Description
(YOKOZUNA TERIYAKI RESTAURANT - IDAHO BLDG - 1ST FLR) To remodel a 1,588 sq.ft. existing restaurant created under BLD10-01904 (BAGUETTE DELI - IDAHO BLDG - 1ST FLR) for a new restaurant. Work includes demo of interior non-bearing walls, in fill of 2 doors not part of exit system as shown on the approved plans. Attached approval from ACHD, attached plan review comments, attached mechanial revision, attached plumbing fixture calculaiton, attached calculations for non protected openings in rated wall and all plan review conditions attached to plans by all reviewing agencies. Scope of work includes: installation of new kitchen equipment, installation of a new type I hood, (Big Dipper) grease trap under sink to remain, and finishes in compliance with chapter 8 of the 2009 IBC. This building is fully sprinklered per 1994 UCBC because it is too tall and has too many stories. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **AJS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 9/26/201310/4/2013 DONE
Permanent Occupancy  9/16/2013 DONE
DetailsChristina Prado
BLD-Final9/11/20139/11/20139/11/2013PPASS
DetailsDave Hannah
jack Phone #: ###-####
Temporary Occupancy8/20/201311/18/20138/20/2013 DONE
DetailsDarla L Downs
BLD-Final8/9/20138/12/20138/12/2013PPART
DetailsDave Hannah
call 30 min before // Jack Phone #: ###-#### ok for temp occ ok for perm occ after mec gos perm
FIRE-Final Inspection8/9/20138/12/20138/12/2013APASS
DetailsForrest France
Fire life safety inspection completed acceptable.
FIRE-Sprinkler Rough-in6/24/20136/24/20136/24/2013APART
DetailsForrest France
Okay to cover fire sprinkler modifications at the grid ceilings.
BLD-Framing/Rough-in6/14/20136/17/20136/17/2013APART
DetailsDave Hannah
Ceiling grid Please contact John if you have questions Phone #: ###-#### ok to cover
FIRE-Conference6/12/20136/12/20136/12/2013ADONE
DetailsForrest France
Regarding hood suppression work and fire life safety inspection items.
Plan assigned to (AJS)5/8/20135/8/20135/22/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed/Due 5/17 Level 2 TI
Routing - PLAN CHECK5/22/2013 5/22/2013 PASS
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  5/22/2013 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  5/22/2013 DONE
Print Occupancy Form  5/22/2013 DONE
DetailsTisha Gallop
Permit Ready to Issue  5/22/2013  
Issue PAID IN FULL permit  5/22/2013 DONE
Plan resubmittals received  5/20/2013 DONE
DetailsTisha Gallop
received response from Architect, response from Engineer, Plumbing Fixture Requirements, and two copies of plan sheet A1.0; taken to Adele
1st review completed  5/13/2013 FAIL
DetailsAdele J Schaffeld-Griffin
emailed plan review comments to John at TAO 5/13/13
Routing - PLAN CHECK5/8/2013 5/13/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see plan review comments in documents
Routing - PUBLIC WORKS5/7/2013 5/8/2013 PASS
DetailsConnie Baumgartner
Plan assigned to (TLW)5/8/2013 5/8/2013 DEFR
DetailsTim L. Woodard
assigned ot Adele
Routing PW Sewer Rating5/7/2013 5/8/2013 PASS
DetailsConnie Baumgartner
Routing PW Environmental5/7/2013 5/7/2013 PASS
DetailsWalt Baumgartner
existing big dipper noted on plans for existing triple sink
Routing - Addressing5/6/2013 5/7/2013 PASS
DetailsJason C. Taylor
Plans ACCEPTED BY PLAN TECH  5/6/2013 DONE
DetailsChristina Prado
Intake Approval  5/6/2013 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  5/6/2013 DONE
DetailsChristina Prado
Application received 5/6/2013