BLD-Final | 11/26/2013 | 11/26/2013 | 11/26/2013 | P | PASS |
Tom Arcoraci
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 11/26/2013 | 11/26/2013 | 11/26/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 10/4/2013 | 10/4/2013 | 10/4/2013 | P | PASS |
Mike Jordan
|
|
|
Fire wall - Kevin Phone #: ###-####
|
BLD-Framing/Rough-in | 9/30/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Energy code compliance | 9/26/2013 | 9/27/2013 | 9/27/2013 | P | FAIL |
Jim Storey
|
|
|
Mike Phone #: ###-#### c/n not done
|
BLD-Framing/Rough-in | 9/25/2013 | 9/25/2013 | 9/25/2013 | P | FAIL |
Mike Jordan
|
|
|
MIKE Phone #: ###-####. Complete the draft stop between unitsat roof valley, provide hangars on B2B trusses. Ok to insulate. Also noted that will need to see 5/8 type x sheet rock attachment and continuity for 1hr. wall between units.
|
BLD-Framing/Rough-in | 9/18/2013 | 9/19/2013 | 9/19/2013 | A | NR |
Mike Jordan
|
|
|
mike Phone #: ###-####. Complete airseal package correction notice posted.
|
Plan resubmittals received | | | 9/10/2013 | | DONE |
|
|
|
new manual j east and west unit
|
Routing - MECHANICAL | 9/10/2013 | | 9/10/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j for west and east unit
|
BLD-Wall Bracing | 8/21/2013 | 8/22/2013 | 8/22/2013 | A | PASS |
Mike Jordan
|
|
|
mike Phone #: ###-####
|
BLD-Footing | 7/31/2013 | 7/31/2013 | 7/31/2013 | P | PASS |
Mike Jordan
|
|
|
Interior footings ok.
|
BLD-Foundation | 6/26/2013 | 6/26/2013 | 6/26/2013 | P | PASS |
Mike Jordan
|
|
|
found wall//Jared Phone #: ###-####
|
BLD-Footing | 6/25/2013 | 6/25/2013 | 6/25/2013 | P | PASS |
Mike Jordan
|
|
|
Jared Draper Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/17/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/12/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 5/7/2013 | 5/7/2013 | 6/12/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed, Due 5/24 Duplex
|
Routing - MECHANICAL | 6/12/2013 | | 6/12/2013 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/12/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 6/12/2013 | | DONE |
Tisha Gallop
|
|
|
reprinted card
|
Telephone call | | | 6/12/2013 | | DONE |
Tisha Gallop
|
|
|
called Michael and left vm permit is ready, fee and need RP
|
Routing - MECHANICAL | 6/11/2013 | | 6/11/2013 | | FAIL |
Troy James
|
|
|
emailed and talked to sam at kartchner engineering
|
Routing - PLAN CHECK | 6/10/2013 | | 6/10/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 6/10/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Telephone call | | | 6/10/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
called applicant and let him know that builing plans were complete but that the mechanical plans have not yet been corrected.
|
Plan resubmittals received | | | 6/3/2013 | | DONE |
Christina Prado
|
|
|
Received two set s revised plan sheets marked A1, A2, A3, A4, A5, A6, A7, A8 & EN as well as two sets revised REScheck; plans taken to Adele for further review
|
Routing - PLAN CHECK | 5/14/2013 | | 5/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see plan review letter in documents
|
1st review completed | | | 5/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emailed Mike 5/16/13
|
Routing - MECHANICAL | 5/9/2013 | | 5/14/2013 | | FAIL |
Troy James
|
|
|
emailed correction to Kartchner
|
Routing - PLANNING | 5/8/2013 | | 5/9/2013 | | PASS |
Andrea Tuning
|
|
|
Ok per SAR and ANT
|
Route to Impact Fee Review | 5/7/2013 | 5/10/2013 | 5/8/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 5/7/2013 | | 5/8/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 5/7/2013 | | 5/7/2013 | | PASS |
Jason C. Taylor
|
|
|
JASON, NEED TO ADDRESS THIS DUPLEX - DONE JCT
|
Intake Approval | | | 5/6/2013 | | PASS |
|
|
|
|
Application received | | 5/6/2013 | | | |
|
|
|
|