Third Notice | | 3/10/2014 | 3/18/2014 | | DONE |
|
|
|
|
Second Notice | | 2/6/2014 | 3/5/2014 | | DONE |
|
|
|
|
First Notice | | 1/2/2014 | 1/27/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 11/26/2013 | 11/27/2013 | 11/27/2013 | P | PASS |
Tom Arcoraci
|
|
|
Larry Phone #: ###-####
|
FIRE-Final Inspection | 11/26/2013 | 11/27/2013 | 11/27/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed pending EM lighting is provided as discussed at suite 184.
|
Temporary Occupancy | 11/27/2013 | 2/25/2014 | 11/27/2013 | | DONE |
Christina Prado
|
|
|
|
FIRE-Sprinkler Rough-in | 11/18/2013 | 11/18/2013 | 11/19/2013 | P | DONE |
Forrest France
|
|
|
|
BLD-Ceiling Grid Inspection | 11/5/2013 | 11/6/2013 | 11/6/2013 | A | PASS |
Dave Hannah
|
|
|
Larry Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/1/2013 | 11/1/2013 | 11/1/2013 | P | PASS |
Dave Hannah
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 9/23/2013 | 9/23/2013 | 9/23/2013 | P | PASS |
Dave Hannah
|
|
|
larry Phone #: ###-####
|
Print Occupancy Form | | | 8/9/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/9/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/9/2013 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 6/27/2013 | 6/27/2013 | 6/27/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/27/2013 | | 6/27/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2013 | | DONE |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 5/21/2013 | 5/21/2013 | 6/21/2013 | | PASS |
Sam Zahorka
|
|
|
1st Review completed.
|
Routing - Design Review | 5/21/2013 | | 6/21/2013 | | PASS |
Matthew A Halitsky
|
|
|
Matt Halitsky - DRH12-00327
|
Routing - PLAN CHECK | 6/21/2013 | | 6/21/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing Off Site - C.D.H | 5/21/2013 | | 6/14/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/14/2013 | | 6/14/2013 | | PEND |
Sam Zahorka
|
|
|
Pending DR planning to PASS
|
1st review completed | | | 6/6/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 5/21/2013 | | 6/6/2013 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - FIRE | 5/21/2013 | | 5/31/2013 | | PASS |
Scott Arellano
|
|
|
Attached plan review comments to case.
|
Plan Reviewer's activity | | | 5/23/2013 | | DONE |
Sam Zahorka
|
|
|
Recieved No Impact Fees Due letter from ACHD. attached under documents in ePlan Review.
|
Routing - PLUMBING | 5/21/2013 | | 5/23/2013 | | PASS |
Bill VanDegrift
|
|
|
mount R.P.-1 over a floor sink or install an R.P.
|
Routing PW Sewer Rating | 5/21/2013 | | 5/22/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 5/21/2013 | | 5/22/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Plan Reviewer's activity | | | 5/21/2013 | | DONE |
Jason Blais
|
|
|
Emailed architect rep to contact ACHD to evaluate if any impact fees are due. Written verification from ACHD needs to be provided to our Permit Counter prior to the building permit being issued.
|
Pending Assignment by JCB | 5/21/2013 | | 5/21/2013 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 5/21/2013 | | 5/21/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 5/21/2013 | | 5/21/2013 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 5/17/2013 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | | 5/15/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2013 12:46PM
|