BLD-Final | 9/13/2013 | 9/13/2013 | 9/13/2013 | P | PASS |
Jim Sly
|
|
|
Micah Phone #: ###-####
|
DOC - Permit Finaled | 9/13/2013 | 9/13/2013 | 9/13/2013 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 7/19/2013 | 7/22/2013 | 7/22/2013 | P | PASS |
Jim Sly
|
|
|
austin Phone #: ###-####
|
BLD-Framing/Rough-in | 7/17/2013 | 7/17/2013 | 7/17/2013 | P | PASS |
Tom Arcoraci
|
|
|
austin Phone #: ###-####
|
BLD-Wall Bracing | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PASS |
Jim Sly
|
|
|
Micah Phone #: ###-####
|
BLD-Foundation | 6/5/2013 | 6/6/2013 | 6/7/2013 | P | PASS |
Jim Sly
|
|
|
matt Phone #: ###-####
|
BLD-Footing | 6/4/2013 | 6/5/2013 | 6/5/2013 | P | PASS |
Jim Sly
|
|
|
dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/31/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/24/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 5/16/2013 | 5/16/2013 | 5/24/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Due 5/30
|
Telephone call | | | 5/24/2013 | | DONE |
Tisha Gallop
|
|
|
called Greg and told him permit is ready and fee.
|
Routing - PLAN CHECK | 5/24/2013 | | 5/24/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 5/24/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 5/24/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 5/20/2013 | | 5/22/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
13991 W Milford Dr.
Gary, I have a quick question for you the above referenced plans. You show a girder truss running the length of the home from front to back. There was a beam calc provided for the garage header it bears on. I will red line in the expanded footings that will be needed as the bearing ends of the header also has a girder truss bearing in the same place. The girder truss shown between the master suite and the great room picks up the wall and truss loading from above along with an additional floor girder. There are no point load locations or expanded footings shown on the plans. There is a wall shown but the foundation plan does not indicate that the wall is load bearing so I would assume the truss has some point loads.
Can you just clarify the load paths for the girder truss’s?
Adele
|
Routing - PLANNING | 5/17/2013 | | 5/22/2013 | | PASS |
Colleen T Carroll
|
|
|
|
1st review completed | | | 5/22/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emailed sent to Gary for additional clarification on the plans 5/22/13.
|
Routing - MECHANICAL | | | 5/20/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/16/2013 | 5/21/2013 | 5/17/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 5/16/2013 | | 5/17/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 5/16/2013 | 5/16/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 5/16/2013 | | PASS |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/16/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - Addressing | 5/16/2013 | | 5/16/2013 | | PASS |
Jason C. Taylor
|
|
|
|