Second Notice | | 8/11/2013 | 8/1/2013 | | DONE |
|
|
|
|
First Notice | | 7/19/2013 | 8/1/2013 | | DONE |
|
|
|
Faxed 8/1/13
|
Permanent Occupancy | | | 7/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | PASS |
Mike Jordan
|
|
|
Cal Phone #: ###-####. Ok for perm occ. racking also ok.
|
FIRE-Final Inspection | 6/27/2013 | 6/27/2013 | 6/27/2013 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | NR |
Mike Jordan
|
|
|
Cal Phone #: ###-####
|
BLD-Final | 6/13/2013 | 6/14/2013 | 6/14/2013 | P | PART |
Mike Jordan
|
|
|
Cal Phone #: ###-####. Ok for temp occ.
|
BLD-Final | 6/13/2013 | 6/14/2013 | 6/14/2013 | A | CANC |
Mike Jordan
|
|
|
Cal Phone #: ###-####. Moved to pm.
|
FIRE-Final Inspection | 6/13/2013 | 6/14/2013 | 6/14/2013 | A | PASS |
Forrest France
|
|
|
Previous correction items verified for completion. Fire life safety finaled. New openings at the south side are finished- doors and landings not yet installed.
|
Temporary Occupancy | 6/14/2013 | 9/12/2013 | 6/14/2013 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 6/13/2013 | 6/13/2013 | 6/13/2013 | P | FAIL |
Troy Cobbley
|
|
|
Repair all of the non-functional exit signs and emergency lights as marked on the plans. Provide the missing exit/emergency lights as per the approved plans. Provide an additional fire extinguisher in the southeast corner as discussed.
|
(F) Reprint permit | | | 6/13/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/13/2013 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/13/2013 | | DONE |
Sam Zahorka
|
|
|
Spoke with the inspector and the architect about required electrical and plumbing permits being required prior to TCO. The architect said he would call the contractor and get the trade permits pulled and inspected prior to a TCO request.
|
Plan assigned to (SRZ) | 6/11/2013 | 6/11/2013 | 6/12/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - FIRE | 6/11/2013 | | 6/12/2013 | | PASS |
Tim Frost
|
|
|
Previous review did not require changes.
|
Routing - PLAN CHECK | 6/12/2013 | | 6/12/2013 | | PASS |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 6/12/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 6/12/2013 | | DONE |
Tisha Gallop
|
|
|
called Cal Emerson and told him plan mod is ready and fee due.
|
Case Summary (BLD) | | | 6/11/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 6/11/2013 | | 6/11/2013 | | PASS |
Sam Zahorka
|
|
|
PLAN MODIFICATIONS. SELECT RACKING AND EXIT SIGNAGE REMOVAL PLAN MODIFICATION PER BLD13-01232.
|
Plan Reviewer's activity | | | 6/11/2013 | | DONE |
Sam Zahorka
|
|
|
Plan modification to remove select racks and the proposed exit signage above the rear North walls approved under BLD13-01232 (Racking Permit). NO T.C.O. without approval from Building Official and Fire Marshall.
|
Plan Modification Accepted | | | 6/11/2013 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted for Bld13-01231 (Rugby AB Products) to relocate fireman access doors as previously shown on the drawings. Doors are to be hollow metal door and frame instead of aluminum store front. No additional panel reinforcing will be required since the doors will be located inthe pre-designed "knock out panel" area; Submitted on plan sheets A1.0, A1.1, A2.0; roued to Sam Zahorka.
|
Plan assigned to (SRZ) | 5/17/2013 | 5/17/2013 | 6/5/2013 | | PASS |
Sam Zahorka
|
|
|
1st review completed.
|
1st review completed | | | 6/5/2013 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/5/2013 | | 6/5/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2013 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 6/5/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
called Clinton and left vm permit is ready, fee and need GC.
|
Issue PAID IN FULL permit | | | 6/5/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - FIRE | 5/30/2013 | | 6/5/2013 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Routing - PLAN CHECK | 5/21/2013 | | 5/30/2013 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 5/30/2013 | | DONE |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 5/30/2013 | | DONE |
|
|
|
|
Routing - Addressing | 5/17/2013 | | 5/20/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 5/20/2013 | | 5/20/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/17/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/17/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/17/2013 | | DONE |
Christina Prado
|
|
|
|
Pending Assignment by JCB | 5/17/2013 | | 5/17/2013 | | DONE |
Jason Blais
|
|
|
|
Application received | | 5/17/2013 | | | |
|
|
|
|
Routing - Design Review | 5/20/2013 | | | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - New storefront door and enlarged overhead door.
Approved the minor exterior changes through the building permit.
|